up_reraStatus: Completed
CASE ID: 0901126020242024

Appellant / Complainant

Uppal Chadha Hi-Tech Developers Pvt. Ltd.

VS

Respondent

Jai Kanwar Gupta

Developer Firm

uppal chadha hi-tech developers pvt. ltd.

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

9 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126020242024 by Uppal Chadha Hi-Tech Developers Pvt. Ltd. against Jai Kanwar Gupta before up_rera.

2
Stage 103/01/2025

Delay condonation

The Tribunal allowed the withdrawal of the appeal following an amicable settlement between the parties and directed the release of the amount deposited under Section 43(5) of the Act to the appellant promoter via RTGS, including any accrued interest.

3
Stage 205/12/2024

Delay condonation

The Tribunal adjourned the appeal to 03.01.2025 and directed both parties to complete their pleadings in the interim.

4
Stage 304/11/2024

Delay condonation

The Tribunal noted the absence of advocates due to a Bar Council resolution and no litigants appearing in person, subsequently adjourning the appeal to 05.12.2024.

5
Stage 424/09/2024

Delay condonation

The appellant's counsel requested an adjournment of the proceedings, and the matter has been rescheduled for orders/hearing on 04.11.2024.

6
Stage 522/08/2024

Delay condonation

The Tribunal noted sufficient service of notice upon the respondent and granted them 10 days to file objections, with the matter scheduled for hearing on 24.09.2024.

7
Stage 619/07/2024

Delay condonation

The Tribunal issued notice to the respondent following the appellant's compliance with Section 43(5) deposit and scheduled the matter for further orders on 22.08.2024.

8
Stage 7Final Ruling Order

Tribunal Order #0901126020242024-03-01-2025

The Tribunal allowed the withdrawal of the appeal following an amicable settlement between the parties and directed the release of the amount deposited under Section 43(5) of the Act to the appellant promoter via RTGS, including any accrued interest.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal allowed the withdrawal of the appeal following an amicable settlement between the parties and directed the release of the amount deposited under Section 43(5) of the Act to the appellant promoter via RTGS, including any accrued interest. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal allowed the withdrawal of the appeal following an amicable settlement between the parties and directed the release of the amount deposited under Section 43(5) of the Act to the appellant promoter via RTGS, including any accrued interest.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Naveen Kumar Tiwari

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126020242024-03-01-2025

The Tribunal allowed the withdrawal of the appeal following an amicable settlement between the parties and directed the release of the amount deposited under Section 43(5) of the Act to the appellant promoter via RTGS, including any accrued interest.

TathyaGrid RERA Intelligence AI

Need to research all rulings for uppal chadha hi-tech developers pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →