up_reraStatus: Completed
CASE ID: 0901126020022022

Appellant / Complainant

U.P. Awas Evam Vikas Parishad

VS

Respondent

Priyanka Singh

Disputed Amount

3,48,485

Disposal Award

Partial

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

35 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126020022022 by U.P. Awas Evam Vikas Parishad against Priyanka Singh before up_rera.

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability
2
Stage 120/11/2024

Hearing

The Tribunal set aside the Adjudicating Officer's order and directed a mutual interest settlement: the promoter must pay delay interest to the allottee from the promised completion date until the dues were deposited, minus the interest owed by the allottee on outstanding dues.

3
Stage 215/10/2024

Hearing

The Tribunal granted the Appellant (U.P. Avas Evam Vikas Parishad) additional time to file an affidavit regarding project timelines and possession details, scheduling the final hearing for November 20, 2024.

4
Stage 304/09/2024

Hearing

The Tribunal granted an adjournment requested by the respondent's counsel and scheduled the appeal for hearing on 15.10.2024, to be heard alongside Cross Appeal No. 592/2022.

5
Stage 402/08/2024

Hearing

No text available.

6
Stage 511/07/2024

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel and scheduled the appeal for orders/hearing on 02.08.2024.

7
Stage 614/05/2024

Final Hearing

The Tribunal noted the appellant's application for amendment of grounds of appeal and directed that the respondent file objections within a week, scheduling the next hearing for July 11, 2024.

8
Stage 722/04/2024

Final Hearing

The Tribunal granted a request for adjournment from both parties and rescheduled the appeal for hearing/orders on 14.05.2024.

9
Stage 802/04/2024

Final Hearing

The Tribunal has rescheduled the hearing for Appeal-222/2022 and Appeal-592/2022 to 22.04.2024 following a joint request from the counsel for both parties.

10
Stage 905/03/2024

Final Hearing

The Tribunal granted a request to club this appeal with Appeal No. 592/2022 and scheduled both matters for hearing on 02.04.2024.

11
Stage 1030/01/2024

Final Hearing

The Tribunal granted an adjournment requested by the appellant's counsel and scheduled the appeal for a hearing on March 5, 2024.

12
Stage 1131/10/2023

Final Hearing

No text available.

13
Stage 1219/09/2023

Final Hearing

The Tribunal allowed the appellant's application to amend the grounds of appeal (adding grounds Q to U) and established a timeline for filing amended copies and subsequent objections.

14
Stage 1309/08/2023

Final Hearing

The Tribunal granted the appellant one week to file an application for amending the grounds of appeal regarding the jurisdiction of the Adjudicating Officer, subject to a cost of Rs. 1/- and specific procedural requirements for electronic service of documents.

15
Stage 1429/05/2023

Final Hearing

The Tribunal granted an adjournment requested by the appellant's counsel due to him being out of station and rescheduled the matter for hearing on 09.08.2023.

16
Stage 1518/04/2023

Final Hearing

The Tribunal has ordered the adjournment of Appeal-222/2022 and directed it to be heard alongside the respondent's cross-appeal (Appeal No. 592/2022) on 29.05.2023.

17
Stage 1617/03/2023

Final Hearing

The Tribunal directed the appellant in Appeal No. 592/2022 to file a reply to the respondent's objections within 10 days and scheduled both related appeals for a joint hearing on 18.04.2023.

18
Stage 1708/02/2023

Final Hearing

No text available.

19
Stage 1810/01/2023

Final Hearing

This is a header/caption of an order from the U.P. Real Estate Appellate Tribunal regarding Appeal-222/2022 between U.P. Awas Evam Vikas Parishad and Priyanka Singh, dated 10.01.2023.

20
Stage 1921/12/2022

Final Hearing

The Tribunal granted an adjournment requested by the respondent's counsel and ordered that this appeal be listed alongside Appeal No. 492/2022 on January 10, 2023.

21
Stage 2025/11/2022

Final Hearing

The Tribunal granted an adjournment requested by the appellant's counsel and scheduled the appeal for a hearing on 21.12.2022, noting that pleadings are complete.

22
Stage 2120/10/2022

For Order

The Tribunal has scheduled the appeal for a final hearing on November 25, 2022.

23
Stage 2221/09/2022

Hearing

The Tribunal has adjourned the appeal to 20.10.2022 to be heard alongside Appeal No. 592/2022, following a joint request from the counsels of both parties.

24
Stage 2313/09/2022

Hearing

The Tribunal directed that Appeal No. 222/2022 be listed together with the respondent's cross-appeal (Appeal No. 592/2022) on 21.09.2022 and ordered the parties to exchange pleadings in the cross-appeal.

25
Stage 2422/08/2022

Hearing

The Tribunal accepted the Vakalatnama of Shri Saghar Mehdi as counsel for the respondent and adjourned the appeal to 13.09.2022 upon the joint request of both parties.

26
Stage 2501/08/2022

Hearing

The Tribunal granted three days to the respondent's counsel to file a Vakalatnama and directed the Registry to convert the defective appeal into a regular appeal upon confirmation of defect removal. The case is scheduled for hearing on 22.08.2022.

27
Stage 2618/07/2022

Notice

The Tribunal granted the respondent three days to upload objections to the appeal on the e-portal and allowed the appellant ten days to file a reply, scheduling the next hearing for August 1, 2022.

28
Stage 2731/05/2022

Notice

The Tribunal granted the respondent 15 days to file objections to the application for condonation of delay and the grounds of appeal, scheduling the matter for hearing on July 18, 2022.

29
Stage 2805/05/2022

Defect Removal

The Tribunal issued notice to the respondent after verifying that the appellant complied with Section 43(5) of the Act by depositing Rs. 8,44,327/- and provided specific instructions for service of process via speed-post and email.

30
Stage 2928/04/2022

Defect Removal

The Tribunal directed the appellant to rectify procedural defects in the memo of appeal, including providing the respondent's email ID and uploading a C.A. Certificate, and scheduled the matter for 05.05.2022.

31
Stage 30Interim Order

Tribunal Order #0901126020022022-01-08-2022

The Tribunal granted three days to the respondent's counsel to file a Vakalatnama and directed the Registry to convert the defective appeal into a regular appeal upon confirmation of defect removal. The case is scheduled for hearing on 22.08.2022.

32
Stage 31Final Ruling Order

Tribunal Order #0901126020022022-20-11-2024

The Tribunal set aside the Adjudicating Officer's order and directed a mutual interest settlement: the promoter must pay delay interest to the allottee from the promised completion date until the dues were deposited, minus the interest owed by the allottee on outstanding dues.

33
Stage 32Interim Order

Tribunal Order #0901126020022022-09-08-2023

The Tribunal granted the appellant one week to file an application for amending the grounds of appeal regarding the jurisdiction of the Adjudicating Officer, subject to a cost of Rs. 1/- and specific procedural requirements for electronic service of documents.

34
Stage 33Interim Order

Tribunal Order #0901126020022022-05-05-2022

The Tribunal issued notice to the respondent after verifying that the appellant complied with Section 43(5) of the Act by depositing Rs. 8,44,327/- and provided specific instructions for service of process via speed-post and email.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal set aside the Adjudicating Officer's order and directed a mutual interest settlement: the promoter must pay delay interest to the allottee from the promised completion date until the dues were deposited, minus the interest owed by the allottee on outstanding dues. Awarded in favor of Partial.

Disposal Winner: PartialStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal set aside the Adjudicating Officer's order and directed a mutual interest settlement: the promoter must pay delay interest to the allottee from the promised completion date until the dues were deposited, minus the interest owed by the allottee on outstanding dues.

Ruling Awarded To

Partial

Interest Period

delay interest from 02.08.2015 till 19.02.2020; interest on outstanding dues from 17.10.2018 till 19.02.2020

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Anurag Singh
  • Shikhar Srivastava

Respondent Advocate(s)

  • Saghar Mehdi
  • Shashi Kant Verma

Official RERA Tribunal Orders (4)

INTERIM_ORDEROrder ID: 0901126020022022-01-08-2022

The Tribunal granted three days to the respondent's counsel to file a Vakalatnama and directed the Registry to convert the defective appeal into a regular appeal upon confirmation of defect removal. The case is scheduled for hearing on 22.08.2022.

FINAL_ORDEROrder ID: 0901126020022022-20-11-2024

The Tribunal set aside the Adjudicating Officer's order and directed a mutual interest settlement: the promoter must pay delay interest to the allottee from the promised completion date until the dues were deposited, minus the interest owed by the allottee on outstanding dues.

INTERIM_ORDEROrder ID: 0901126020022022-09-08-2023

The Tribunal granted the appellant one week to file an application for amending the grounds of appeal regarding the jurisdiction of the Adjudicating Officer, subject to a cost of Rs. 1/- and specific procedural requirements for electronic service of documents.

INTERIM_ORDEROrder ID: 0901126020022022-05-05-2022

The Tribunal issued notice to the respondent after verifying that the appellant complied with Section 43(5) of the Act by depositing Rs. 8,44,327/- and provided specific instructions for service of process via speed-post and email.