up_reraStatus: Completed
CASE ID: 0901126019462021

Appellant / Complainant

Lucknow Development Authority

VS

Respondent

Hari Prakash Saxena

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

25 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126019462021 by Lucknow Development Authority against Hari Prakash Saxena before up_rera.

Delay in PossessionDelay Compensation / Interest
2
Stage 114/09/2023

for delivery of Judgment/Order

The Appellate Tribunal dismissed the appeal filed by Lucknow Development Authority, upholding the Regulatory Authority's order to pay interest (MCLR+1%) for delayed possession and directing the transfer of the promoter's pre-deposited amount to U.P. RERA for disbursement to the allottee.

3
Stage 213/09/2023

for delivery of Judgment/Order

No text available.

4
Stage 312/09/2023

for delivery of Judgment/Order

No text available.

5
Stage 424/08/2023

Hearing

The Tribunal heard arguments from both the appellant (Lucknow Development Authority) and the respondent regarding an appeal against a Regulatory Authority order, but reserved judgment for a later date.

6
Stage 509/08/2023

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel on personal grounds and rescheduled the hearing for August 24, 2023.

7
Stage 629/05/2023

Hearing

The Tribunal directed the applicant to pay the previously ordered cost of Rs. 5000/- for condonation of delay by the next listing date.

8
Stage 718/04/2023

Hearing

The Tribunal granted an adjournment requested by the respondent's counsel due to his COVID-19 infection and rescheduled the hearing for 29.05.2023.

9
Stage 816/03/2023

Hearing

The proceedings for Appeal-263/2021 were adjourned due to the counsel for the appellant being on sanctioned leave, with the matter rescheduled for hearing on 18.04.2023.

10
Stage 928/02/2023

Hearing

The Tribunal ordered the appeal to be listed for a fresh hearing on 16.03.2023 because the previous judgment was reserved but could not be delivered due to the Presiding Member of Bench No. 2 demitting office.

11
Stage 1024/03/2022

Hearing

The Tribunal condoned a 412-day delay in filing the appeal, subject to a cost of Rs. 5000/- to be split between the respondent and the Tribunal fund, and ordered the defective appeal to be registered as a Regular Appeal.

12
Stage 1125/02/2022

Delay condonation

The Tribunal granted the appellant 10 days to file a reply to the respondent's objections regarding the condonation of delay and directed both parties to exchange pleadings and upload them to the e-portal before the next hearing on 24.03.2022.

13
Stage 1217/01/2022

Delay condonation

No text available.

14
Stage 1315/12/2021

Delay condonation

The Tribunal directed the respondent to file an objection against the limitation application and scheduled the matter for 17.01.2022 to dispose of said application.

15
Stage 1422/11/2021

Compliance of section 43(5)

The Tribunal issued a notice to the respondent via registered post and e-mail due to their non-appearance and scheduled the matter for further orders on 15.12.2021.

16
Stage 1525/10/2021

Compliance of section 43(5)

The Tribunal noted the appellant's compliance with Section 43(5) regarding deposit requirements and directed that notice be issued to the respondent via registered post and email.

17
Stage 1605/10/2021

Compliance of section 43(5)

The Tribunal directed the appellant to rectify registry defects, specifically regarding compliance with Section 43(5) of the Act, warning that failure to comply by the next hearing date will result in dismissal.

18
Stage 1719/04/2021

Compliance of section 43(5)

No text available.

19
Stage 1802/04/2021

Defect Removal

No text available.

20
Stage 1922/03/2021

Defect Removal

The Tribunal granted the appellant a one-week extension to rectify registry defects, specifically regarding compliance with Section 43(5) of the Act, and scheduled the matter for April 2, 2021.

21
Stage 20Interim Order

Tribunal Order #0901126019462021-29-05-2023

The Tribunal directed the applicant to pay the previously ordered cost of Rs. 5000/- for condonation of delay by the next listing date.

22
Stage 21Final Ruling Order

Tribunal Order #0901126019462021-14-09-2023

The Appellate Tribunal dismissed the appeal filed by Lucknow Development Authority, upholding the Regulatory Authority's order to pay interest (MCLR+1%) for delayed possession and directing the transfer of the promoter's pre-deposited amount to U.P. RERA for disbursement to the allottee.

23
Stage 22Interim Order

Tribunal Order #0901126019462021-24-03-2022

The Tribunal condoned a 412-day delay in filing the appeal, subject to a cost of Rs. 5000/- to be split between the respondent and the Tribunal fund, and ordered the defective appeal to be registered as a Regular Appeal.

24
Stage 23Interim Order

Tribunal Order #0901126019462021-05-10-2021

The Tribunal directed the appellant to rectify registry defects, specifically regarding compliance with Section 43(5) of the Act, warning that failure to comply by the next hearing date will result in dismissal.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Appellate Tribunal dismissed the appeal filed by Lucknow Development Authority, upholding the Regulatory Authority's order to pay interest (MCLR+1%) for delayed possession and directing the transfer of the promoter's pre-deposited amount to U.P. RERA for disbursement to the allottee. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.

Disposal Winner: RespondentInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Appellate Tribunal dismissed the appeal filed by Lucknow Development Authority, upholding the Regulatory Authority's order to pay interest (MCLR+1%) for delayed possession and directing the transfer of the promoter's pre-deposited amount to U.P. RERA for disbursement to the allottee.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+1%

Interest Period

from 18.08.2014 to 25.04.2019

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Abhishek Khare

Respondent Advocate(s)

  • Hridesh Srivastava

Official RERA Tribunal Orders (4)

INTERIM_ORDEROrder ID: 0901126019462021-29-05-2023

The Tribunal directed the applicant to pay the previously ordered cost of Rs. 5000/- for condonation of delay by the next listing date.

FINAL_ORDEROrder ID: 0901126019462021-14-09-2023

The Appellate Tribunal dismissed the appeal filed by Lucknow Development Authority, upholding the Regulatory Authority's order to pay interest (MCLR+1%) for delayed possession and directing the transfer of the promoter's pre-deposited amount to U.P. RERA for disbursement to the allottee.

INTERIM_ORDEROrder ID: 0901126019462021-24-03-2022

The Tribunal condoned a 412-day delay in filing the appeal, subject to a cost of Rs. 5000/- to be split between the respondent and the Tribunal fund, and ordered the defective appeal to be registered as a Regular Appeal.

INTERIM_ORDEROrder ID: 0901126019462021-05-10-2021

The Tribunal directed the appellant to rectify registry defects, specifically regarding compliance with Section 43(5) of the Act, warning that failure to comply by the next hearing date will result in dismissal.