up_reraStatus: Completed
CASE ID: 0901126019432023

Appellant / Complainant

Ratan Buildtech Private Limited

VS

Respondent

Ved Prakash Singh

Developer Firm

ratan buildtech private limited

Disposal Award

Partial

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

23 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126019432023 by Ratan Buildtech Private Limited against Ved Prakash Singh before up_rera.

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability
2
Stage 114/05/2025

Hearing

The Tribunal set aside the Adjudicating Officer's order due to lack of jurisdiction but directly settled the dispute by awarding delay interest to the respondent at MCLR+1% for the period from 01.01.2020 to 30.09.2022, excluding a six-month COVID-19 force majeure period.

3
Stage 221/04/2025

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel and scheduled the next hearing for May 14, 2025, noting that no further adjournments will be permitted.

4
Stage 321/03/2025

Hearing

The Tribunal has adjourned the matter to 21.04.2025 for orders following a joint request by the parties.

5
Stage 428/02/2025

Hearing

The Tribunal granted a request for adjournment on behalf of the appellant's counsel and scheduled the appeal for hearing on 21.03.2025, noting that no further adjournments will be permitted.

6
Stage 505/02/2025

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel due to personal illness and rescheduled the hearing for February 28, 2025.

7
Stage 624/09/2024

for delivery of Judgment/Order

The Tribunal condoned the delay in filing 12 appeals by Ratan Buildtech Pvt. Ltd., ruling that because the impugned orders prima facie appeared to be passed without jurisdiction, the delay should be excused to allow for a merit-based adjudication of the jurisdictional issue.

8
Stage 714/08/2024

Delay condonation

The Tribunal heard arguments regarding the application for condonation of delay and has reserved its order.

9
Stage 816/07/2024

Delay condonation

The Tribunal has scheduled the appeal for orders/hearing on 14.08.2024, referring to a previous order passed in Appeal No. 260/2023.

10
Stage 916/05/2024

Delay condonation

No text available.

11
Stage 1010/05/2024

Delay condonation

The Tribunal has scheduled the appeal for a hearing on 16.05.2024 following information regarding similar cases being listed on that date.

12
Stage 1124/04/2024

Delay condonation

The Tribunal noted that pleadings have been exchanged and scheduled the appeal for hearing on 10.05.2024.

13
Stage 1229/03/2024

Delay condonation

The Tribunal refers the matter to a previous order passed in Appeal No. D382/2023 for directions.

14
Stage 1315/03/2024

Delay condonation

The Tribunal granted the appellant's counsel time to examine potential deficiencies in compliance with Section 43(5) of the Act and scheduled the matter for hearing on March 29, 2024.

15
Stage 1413/02/2024

Delay condonation

The Tribunal granted the appellant one week to file a reply to the respondent's objection and scheduled the matter for hearing on 15.03.2024 regarding the application for condonation of delay.

16
Stage 1505/01/2024

Delay condonation

The Tribunal granted the appellant a final two-week extension to file a reply to the respondent's objection regarding the condonation of delay, subject to a cost of Rs. 500/- to be used for the legal library.

17
Stage 1628/09/2023

Delay condonation

No text available.

18
Stage 1717/08/2023

Delay condonation

The Tribunal granted extensions of time to both parties for filing replies and objections regarding the application for condonation of delay and the grounds of appeal, scheduling the next hearing for September 28, 2023.

19
Stage 1821/06/2023

Delay condonation

The Tribunal issued notice to the respondent regarding the appellant's application for condonation of delay and directed the service of process via speed-post and email.

20
Stage 19Final Ruling Order

Tribunal Order #0901126019432023-14-05-2025

The Tribunal set aside the Adjudicating Officer's order due to lack of jurisdiction but directly settled the dispute by awarding delay interest to the respondent at MCLR+1% for the period from 01.01.2020 to 30.09.2022, excluding a six-month COVID-19 force majeure period.

21
Stage 20Interim Order

Tribunal Order #0901126019432023-24-09-2024

The Tribunal condoned the delay in filing 12 appeals by Ratan Buildtech Pvt. Ltd., ruling that because the impugned orders prima facie appeared to be passed without jurisdiction, the delay should be excused to allow for a merit-based adjudication of the jurisdictional issue.

22
Stage 21Interim Order

Tribunal Order #0901126019432023-05-01-2024

The Tribunal granted the appellant a final two-week extension to file a reply to the respondent's objection regarding the condonation of delay, subject to a cost of Rs. 500/- to be used for the legal library.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal set aside the Adjudicating Officer's order due to lack of jurisdiction but directly settled the dispute by awarding delay interest to the respondent at MCLR+1% for the period from 01.01.2020 to 30.09.2022, excluding a six-month COVID-19 force majeure period. Awarded in favor of Partial. Awarded interest rate: MCLR+1%.

Disposal Winner: PartialInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal set aside the Adjudicating Officer's order due to lack of jurisdiction but directly settled the dispute by awarding delay interest to the respondent at MCLR+1% for the period from 01.01.2020 to 30.09.2022, excluding a six-month COVID-19 force majeure period.

Ruling Awarded To

Partial

Awarded Interest Rate

MCLR+1%

Interest Period

from 01.01.2020 to 30.09.2022 (excluding six months force majeure period due to Covid-19)

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Mahima Pahwa

Respondent Advocate(s)

  • Shivendra Rao

Official RERA Tribunal Orders (3)

FINAL_ORDEROrder ID: 0901126019432023-14-05-2025

The Tribunal set aside the Adjudicating Officer's order due to lack of jurisdiction but directly settled the dispute by awarding delay interest to the respondent at MCLR+1% for the period from 01.01.2020 to 30.09.2022, excluding a six-month COVID-19 force majeure period.

INTERIM_ORDEROrder ID: 0901126019432023-24-09-2024

The Tribunal condoned the delay in filing 12 appeals by Ratan Buildtech Pvt. Ltd., ruling that because the impugned orders prima facie appeared to be passed without jurisdiction, the delay should be excused to allow for a merit-based adjudication of the jurisdictional issue.

INTERIM_ORDEROrder ID: 0901126019432023-05-01-2024

The Tribunal granted the appellant a final two-week extension to file a reply to the respondent's objection regarding the condonation of delay, subject to a cost of Rs. 500/- to be used for the legal library.

TathyaGrid RERA Intelligence AI

Need to research all rulings for ratan buildtech private limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →