up_reraStatus: Completed
CASE ID: 0901126018432020

Appellant / Complainant

Brijesh Chandra

VS

Respondent

Lucknow Development Authority

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Jurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

23 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126018432020 by Brijesh Chandra against Lucknow Development Authority before up_rera.

Jurisdiction & Maintainability
2
Stage 122/08/2022

Delay condonation

The Tribunal dismissed the appeal, ruling that the complaint was not maintainable because the project was not required to be registered under RERA based on the percentage of sale deeds executed prior to the Act's enforcement. However, the appellant was granted liberty to approach RERA on an administrative side to seek registration if the project is still ongoing.

3
Stage 227/07/2022

Delay condonation

The Tribunal adjourned the case to 22.08.2022 due to the illness of the appellant's counsel and scheduled it for consideration of a condonation of delay application.

4
Stage 315/07/2022

Delay condonation

The respondent's counsel requested and was granted a three-day extension to ensure compliance with the previous order dated 11.07.2022, with the matter rescheduled for 27.07.2022.

5
Stage 411/07/2022

Delay condonation

The Tribunal granted the respondent two days to file correct documents regarding Sector-6, Gomti Nagar Extension, and directed the applicant to provide evidence concerning the lack of advertised amenities. The matter is scheduled for further hearing on 15.07.2022.

6
Stage 508/07/2022

Delay condonation

The Tribunal noted that the project is unregistered with RERA and directed the appellant's counsel to explain the maintainability of the case in light of the Supreme Court judgment in M/s Newtech Promoters & Developers Pvt. Ltd. Vs. State of U.P.

7
Stage 631/05/2022

Delay condonation

The Tribunal granted a final one-week extension to the respondent to place on record the status of the project's Occupancy Certificate (OC) or Completion Certificate (CC), directing them to email the documents to the applicant within 7 days.

8
Stage 725/05/2022

Delay condonation

The Tribunal granted the respondent three days to file the status of the project's Occupancy Certificate (OC) or Completion Certificate (CC) and directed them to email copies to the applicant and counsel. The matter is scheduled for hearing on May 31, 2022, regarding the application for condonation of delay.

9
Stage 812/05/2022

Delay condonation

The Tribunal granted a one-week extension to the Lucknow Development Authority to file the status of the Occupancy Certificate (OC) and Completion Certificate (CC) for the project in question.

10
Stage 907/04/2022

Delay condonation

The Tribunal directed the respondent to file a status report regarding OC/CC before the next hearing and ordered both parties to appear at the next listing.

11
Stage 1021/03/2022

Delay condonation

The Tribunal granted a one-week extension to the respondent's counsel to seek instructions regarding the receipt of the Occupancy Certificate (O.C.) for the project and rescheduled the hearing to 07.04.2022.

12
Stage 1107/03/2022

Delay condonation

The Tribunal granted the appellant's counsel time to seek instructions regarding a maintainability objection raised by the respondent and adjourned the matter to 21.03.2022.

13
Stage 1205/01/2022

Delay condonation

The Tribunal granted the respondent one week to file a Vakalatnama and objections against the limitation application, directing that copies be emailed to the applicant before the next hearing on 24.01.2022.

14
Stage 1329/11/2021

Further Order

The Tribunal directed the respondent's counsel to file a Vakalatnama within three days and granted permission to file an objection against the limitation application, scheduling the matter for January 5, 2022.

15
Stage 1428/10/2021

Delay condonation

The Tribunal adjourned the matter to 29.11.2021 for further orders due to the absence of the respondent.

16
Stage 1519/02/2021

Delay condonation

No text available.

17
Stage 16Interim Order

Tribunal Order #0901126018432020-25-05-2022

The Tribunal granted the respondent three days to file the status of the project's Occupancy Certificate (OC) or Completion Certificate (CC) and directed them to email copies to the applicant and counsel. The matter is scheduled for hearing on May 31, 2022, regarding the application for condonation of delay.

18
Stage 17Final Ruling Order

Tribunal Order #0901126018432020-22-08-2022

The Tribunal dismissed the appeal, ruling that the complaint was not maintainable because the project was not required to be registered under RERA based on the percentage of sale deeds executed prior to the Act's enforcement. However, the appellant was granted liberty to approach RERA on an administrative side to seek registration if the project is still ongoing.

19
Stage 18Interim Order

Tribunal Order #0901126018432020-11-07-2022

The Tribunal granted the respondent two days to file correct documents regarding Sector-6, Gomti Nagar Extension, and directed the applicant to provide evidence concerning the lack of advertised amenities. The matter is scheduled for further hearing on 15.07.2022.

20
Stage 19Interim Order

Tribunal Order #0901126018432020-08-07-2022

The Tribunal noted that the project is unregistered with RERA and directed the appellant's counsel to explain the maintainability of the case in light of the Supreme Court judgment in M/s Newtech Promoters & Developers Pvt. Ltd. Vs. State of U.P.

21
Stage 20Interim Order

Tribunal Order #0901126018432020-31-05-2022

The Tribunal granted a final one-week extension to the respondent to place on record the status of the project's Occupancy Certificate (OC) or Completion Certificate (CC), directing them to email the documents to the applicant within 7 days.

22
Stage 21Interim Order

Tribunal Order #0901126018432020-12-05-2022

The Tribunal granted a one-week extension to the Lucknow Development Authority to file the status of the Occupancy Certificate (OC) and Completion Certificate (CC) for the project in question.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal dismissed the appeal, ruling that the complaint was not maintainable because the project was not required to be registered under RERA based on the percentage of sale deeds executed prior to the Act's enforcement. However, the appellant was granted liberty to approach RERA on an administrative side to seek registration if the project is still ongoing. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal dismissed the appeal, ruling that the complaint was not maintainable because the project was not required to be registered under RERA based on the percentage of sale deeds executed prior to the Act's enforcement. However, the appellant was granted liberty to approach RERA on an administrative side to seek registration if the project is still ongoing.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Kushagra Dikshit

Respondent Advocate(s)

  • Saurabh Misra

Official RERA Tribunal Orders (6)

INTERIM_ORDEROrder ID: 0901126018432020-25-05-2022

The Tribunal granted the respondent three days to file the status of the project's Occupancy Certificate (OC) or Completion Certificate (CC) and directed them to email copies to the applicant and counsel. The matter is scheduled for hearing on May 31, 2022, regarding the application for condonation of delay.

FINAL_ORDEROrder ID: 0901126018432020-22-08-2022

The Tribunal dismissed the appeal, ruling that the complaint was not maintainable because the project was not required to be registered under RERA based on the percentage of sale deeds executed prior to the Act's enforcement. However, the appellant was granted liberty to approach RERA on an administrative side to seek registration if the project is still ongoing.

INTERIM_ORDEROrder ID: 0901126018432020-11-07-2022

The Tribunal granted the respondent two days to file correct documents regarding Sector-6, Gomti Nagar Extension, and directed the applicant to provide evidence concerning the lack of advertised amenities. The matter is scheduled for further hearing on 15.07.2022.

INTERIM_ORDEROrder ID: 0901126018432020-08-07-2022

The Tribunal noted that the project is unregistered with RERA and directed the appellant's counsel to explain the maintainability of the case in light of the Supreme Court judgment in M/s Newtech Promoters & Developers Pvt. Ltd. Vs. State of U.P.

INTERIM_ORDEROrder ID: 0901126018432020-31-05-2022

The Tribunal granted a final one-week extension to the respondent to place on record the status of the project's Occupancy Certificate (OC) or Completion Certificate (CC), directing them to email the documents to the applicant within 7 days.

INTERIM_ORDEROrder ID: 0901126018432020-12-05-2022

The Tribunal granted a one-week extension to the Lucknow Development Authority to file the status of the Occupancy Certificate (OC) and Completion Certificate (CC) for the project in question.

TathyaGrid RERA Intelligence AI

Need to research all rulings for a builder?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →