CASE ID: 0901126018392020

Appellant / Complainant

Air Force Naval Housing Board

VS

Respondent

Gajinder Kumar

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionRefund of InvestmentDelay Compensation / InterestNon-Compliance & Execution

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

20 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126018392020 by Air Force Naval Housing Board against Gajinder Kumar before up_rera.

Delay in PossessionRefund of InvestmentDelay Compensation / InterestNon-Compliance & Execution
2
Stage 107/05/2024

for delivery of Judgment/Order

The Tribunal dismissed 48 appeals filed by the Air Force Naval Housing Board, upholding the U.P. RERA's orders regarding interest at MCLR+1% and directing that pre-deposited funds be transferred to U.P. RERA for distribution to allottees during execution proceedings.

3
Stage 215/02/2024

Hearing

The tribunal directs the parties to refer to the orders previously passed in Appeal No. D 21/2023.

4
Stage 313/02/2024

Hearing

This is a procedural order directing the parties to refer to a previously passed order dated in Appeal No. D 866/2021 for the relevant directions.

5
Stage 412/02/2024

Delay condonation

The Tribunal has ordered the matter to be listed for hearing on 13.02.2024.

6
Stage 510/10/2023

Delay condonation

No text available.

7
Stage 630/08/2023

Delay condonation

No text available.

8
Stage 712/07/2023

Delay condonation

No text available.

9
Stage 802/05/2023

Delay condonation

The Tribunal has scheduled the case for consideration of an application for condonation of delay and a subsequent hearing on 12.07.2023.

10
Stage 921/03/2023

Delay condonation

No text available.

11
Stage 1010/02/2023

Delay condonation

No text available.

12
Stage 1106/01/2023

Delay condonation

No text available.

13
Stage 1202/12/2022

Notice

The Tribunal granted the respondent 10 days to file objections to the application for condonation of delay and grounds of appeal, with subsequent timelines set for replies and e-portal uploads.

14
Stage 1318/11/2022

Notice

The Tribunal permitted the appellant to file an application for service of notice on the respondent through publication due to insufficient address and scheduled the matter for orders on 02.12.2022.

15
Stage 1413/10/2022

Notice

No text available.

16
Stage 1513/09/2022

Notice

The Tribunal issued a notice to the respondent for the next hearing on 13.10.2022 and outlined the procedural steps for service of notice and filing of objections/replies.

17
Stage 1629/08/2022

Notice

No text available.

18
Stage 1709/10/2020

Compliance of section 43(5)

No text available.

19
Stage 18Final Ruling Order

Tribunal Order #0901126018392020-07-05-2024

The Tribunal dismissed 48 appeals filed by the Air Force Naval Housing Board, upholding the U.P. RERA's orders regarding interest at MCLR+1% and directing that pre-deposited funds be transferred to U.P. RERA for distribution to allottees during execution proceedings.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal dismissed 48 appeals filed by the Air Force Naval Housing Board, upholding the U.P. RERA's orders regarding interest at MCLR+1% and directing that pre-deposited funds be transferred to U.P. RERA for distribution to allottees during execution proceedings. Awarded in favor of Respondent. Awarded interest rate: MCLR + 1%.

Disposal Winner: RespondentInterest Rate: MCLR + 1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal dismissed 48 appeals filed by the Air Force Naval Housing Board, upholding the U.P. RERA's orders regarding interest at MCLR+1% and directing that pre-deposited funds be transferred to U.P. RERA for distribution to allottees during execution proceedings.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR + 1%

Interest Period

w.e.f. 01.07.2012 till offer of possession or obtaining of OC whichever is later

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 40Section 63Section 64

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Ashish Kumar Singh
  • Kushagra Dikshit

Respondent Advocate(s)

  • Shilpa Kaushik

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126018392020-07-05-2024

The Tribunal dismissed 48 appeals filed by the Air Force Naval Housing Board, upholding the U.P. RERA's orders regarding interest at MCLR+1% and directing that pre-deposited funds be transferred to U.P. RERA for distribution to allottees during execution proceedings.