up_reraStatus: Completed
CASE ID: 0901126018252025

Appellant / Complainant

Yash Dua, Nisha Dua

VS

Respondent

Floral Realcon Pvt Ltd

Developer Firm

floral realcon pvt ltd

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Non-Compliance & Execution

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

10 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126018252025 by Yash Dua, Nisha Dua against Floral Realcon Pvt Ltd before up_rera.

Non-Compliance & Execution
2
Stage 131/10/2025

For Order

The Tribunal, following a High Court remand, restores the original complaint to U.P. RERA and directs that the matter be decided on its merits within three months.

3
Stage 217/10/2025

For Order

The Tribunal granted an adjournment requested by the respondent's counsel and scheduled the matter for orders on 31.10.2025, directing the respondent to file an objection before the next hearing.

4
Stage 317/09/2025

For Order

The Tribunal granted the applicant seven days to reply to the respondent's objections and scheduled the next hearing for October 17, 2025.

5
Stage 401/09/2025

For Order

The Tribunal granted the respondent's counsel additional time to respond to the Interlocutory Application (IA-605/2025) and scheduled the matter for orders on 17.09.2025.

6
Stage 506/08/2025

For Order

The Tribunal has adjourned the hearing of IA No. 605/2025 to 01.09.2025, following a request by the respondent's counsel to await the disposal of a pending correction application in the High Court.

7
Stage 616/07/2025

For Order

The Tribunal granted the applicant 10 days to file a reply and scheduled the matter for a subsequent hearing on 06.08.2025.

8
Stage 723/05/2025

For Order

The Tribunal issued a notice to the respondent and directed the applicants to serve the notice and appeal documents via speed-post and email, scheduling the next hearing for July 16, 2025.

9
Stage 8Final Ruling Order

Tribunal Order #0901126018252025-31-10-2025

The Tribunal, following a High Court remand, restores the original complaint to U.P. RERA and directs that the matter be decided on its merits within three months.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal, following a High Court remand, restores the original complaint to U.P. RERA and directs that the matter be decided on its merits within three months. Awarded in favor of Appellant.

Disposal Winner: AppellantStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal, following a High Court remand, restores the original complaint to U.P. RERA and directs that the matter be decided on its merits within three months.

Ruling Awarded To

Appellant

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 40Section 63Section 64

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Amit Yadav

Respondent Advocate(s)

  • Harish Pandey

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126018252025-31-10-2025

The Tribunal, following a High Court remand, restores the original complaint to U.P. RERA and directs that the matter be decided on its merits within three months.