up_reraStatus: Completed
CASE ID: 0901126018252020

Appellant / Complainant

Air Force Naval Housing Board

VS

Respondent

Saurabh Ranjan

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionRefund of InvestmentDelay Compensation / InterestNon-Compliance & Execution

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

21 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126018252020 by Air Force Naval Housing Board against Saurabh Ranjan before up_rera.

Delay in PossessionRefund of InvestmentDelay Compensation / InterestNon-Compliance & Execution
2
Stage 107/05/2024

for delivery of Judgment/Order

The Tribunal dismissed 48 connected appeals filed by the Air Force Naval Housing Board against UP RERA orders, upholding the award of interest at MCLR+1% for delayed possession. The Tribunal further directed that all pre-deposited amounts be transferred to U.P. RERA for distribution to allottees during execution proceedings.

3
Stage 215/02/2024

Hearing

The order refers the parties to a previous substantive order passed in Appeal No. D 21/2023.

4
Stage 313/02/2024

For Order

This is a procedural order referring the parties to a previous order passed in Appeal No. D 866/2021.

5
Stage 412/02/2024

For Order

The Tribunal has ordered the matter to be listed for hearing on February 13, 2024.

6
Stage 510/10/2023

For Order

No text available.

7
Stage 630/08/2023

For Order

No text available.

8
Stage 712/07/2023

For Order

No text available.

9
Stage 802/05/2023

For Order

The Tribunal has scheduled the case for 12.07.2023 to consider an application for condonation of delay and for a hearing.

10
Stage 921/03/2023

For Order

No text available.

11
Stage 1010/02/2023

For Order

No text available.

12
Stage 1106/01/2023

For Order

No text available.

13
Stage 1214/12/2022

For Order

The Tribunal allowed the appellant's application to amend the prayer clause, limiting the challenge specifically to the Regulatory Authority's direction regarding interest for delayed possession.

14
Stage 1318/11/2022

Hearing

The Tribunal granted the applicant two weeks to file a reply to the respondent's objections regarding the application for condonation of delay and scheduled the matter for hearing on 14.12.2022.

15
Stage 1413/10/2022

Hearing

No text available.

16
Stage 1513/09/2022

Notice

The Tribunal granted the respondent 10 days to file objections to the application for condonation of delay and the grounds of appeal, scheduling the next hearing for 13.10.2022.

17
Stage 1629/08/2022

Notice

No text available.

18
Stage 1709/10/2020

Compliance of section 43(5)

No text available.

19
Stage 18Final Ruling Order

Tribunal Order #0901126018252020-07-05-2024

The Tribunal dismissed 48 connected appeals filed by the Air Force Naval Housing Board against UP RERA orders, upholding the award of interest at MCLR+1% for delayed possession. The Tribunal further directed that all pre-deposited amounts be transferred to U.P. RERA for distribution to allottees during execution proceedings.

20
Stage 19Interim Order

Tribunal Order #0901126018252020-14-12-2022

The Tribunal allowed the appellant's application to amend the prayer clause, limiting the challenge specifically to the Regulatory Authority's direction regarding interest for delayed possession.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal dismissed 48 connected appeals filed by the Air Force Naval Housing Board against UP RERA orders, upholding the award of interest at MCLR+1% for delayed possession. The Tribunal further directed that all pre-deposited amounts be transferred to U.P. RERA for distribution to allottees during execution proceedings. Awarded in favor of Respondent. Awarded interest rate: MCLR + 1% per annum.

Disposal Winner: RespondentInterest Rate: MCLR + 1% per annumStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal dismissed 48 connected appeals filed by the Air Force Naval Housing Board against UP RERA orders, upholding the award of interest at MCLR+1% for delayed possession. The Tribunal further directed that all pre-deposited amounts be transferred to U.P. RERA for distribution to allottees during execution proceedings.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR + 1% per annum

Interest Period

w.e.f. 01.07.2012 till offer of possession or obtaining of OC whichever is later

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 40Section 63Section 64

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Harsh Vardhan
  • N A

Respondent Advocate(s)

  • Rakesh Kumar Rana

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126018252020-07-05-2024

The Tribunal dismissed 48 connected appeals filed by the Air Force Naval Housing Board against UP RERA orders, upholding the award of interest at MCLR+1% for delayed possession. The Tribunal further directed that all pre-deposited amounts be transferred to U.P. RERA for distribution to allottees during execution proceedings.

INTERIM_ORDEROrder ID: 0901126018252020-14-12-2022

The Tribunal allowed the appellant's application to amend the prayer clause, limiting the challenge specifically to the Regulatory Authority's direction regarding interest for delayed possession.