CASE ID: 0901126018082020

Appellant / Complainant

Logix City Developers Private Limited, Ajay Kumar Rai

VS

Respondent

Lucknow Development Authority

Developer Firm

logix city developers private limited

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestStructural Defects & QualityPromotional Misrepresentation

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

24 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126018082020 by Logix City Developers Private Limited, Ajay Kumar Rai against Lucknow Development Authority before up_rera.

Delay in PossessionDelay Compensation / InterestStructural Defects & QualityPromotional Misrepresentation
2
Stage 127/09/2022

for delivery of Judgment/Order

The Tribunal partially allowed the allottee's appeal by modifying the interest period for delay from 01.11.2016 to 29.05.2019 to the full period from 24.12.2012 to 29.05.2019, while dismissing the LDA's appeal and directing the transfer of pre-deposited funds to U.P. RERA for execution.

3
Stage 204/08/2022

Delay condonation

The Tribunal heard arguments regarding the appellant's challenge to an order curtailing interest due to delay and has reserved its judgment.

4
Stage 303/08/2022

Delay condonation

No text available.

5
Stage 418/07/2022

Delay condonation

The Tribunal adjourned the proceedings due to the appellant's counsel's illness and directed the applicant to file a reply to the respondent's objections within one week.

6
Stage 509/05/2022

Delay condonation

The Tribunal granted the appellant's request for an extension to file a replication against the respondent's reply and scheduled the next hearing for 18.07.2022.

7
Stage 620/04/2022

Delay condonation

The Tribunal granted the appellant one week to file a reply to the respondent's objections and ordered that this case be listed alongside Appeal No. 625/2021 on 09.05.2022.

8
Stage 706/04/2022

Delay condonation

The Tribunal granted the applicant one week to file a reply to the respondent's objections regarding the application for condonation of delay and scheduled the matter for hearing on 20.04.2022.

9
Stage 814/03/2022

Delay condonation

The Tribunal granted the appellant one week to file a reply to the respondent's objections and scheduled the case for April 6, 2022, to consider the application for condonation of delay.

10
Stage 922/02/2022

Delay condonation

The Tribunal granted an adjournment requested by the appellant's counsel and directed the applicant to file a reply to the respondent's objections within 10 days. The case is scheduled for hearing on 14.03.2022.

11
Stage 1012/01/2022

Delay condonation

No text available.

12
Stage 1116/12/2021

Delay condonation

The Tribunal noted the presence of counsel for both parties and directed the respondent to file their Vakalatnama and objections against the limitation application before the next hearing. The case is scheduled for further orders on 12.01.2022.

13
Stage 1223/11/2021

Delay condonation

The Tribunal granted the appellant a final opportunity to file a replication/rejoinder affidavit and adjourned the matter to 26.11.2021.

14
Stage 1326/10/2021

Delay condonation

The Tribunal granted an adjournment requested by the appellant and rescheduled the case to 23.11.2021 for the disposal of a limitation application and objections.

15
Stage 1429/09/2021

Delay condonation

The Tribunal allowed the application to condone delay and recalled the dismissal order dated 09.11.2020, thereby restoring the case to its original number.

16
Stage 1509/09/2021

Delay condonation

The Tribunal granted the respondent two weeks to file objections to the condonation of delay application and grounds of appeal, while also adjourning the case upon request from the appellant's counsel.

17
Stage 1627/04/2021

Delay condonation

No text available.

18
Stage 1702/04/2021

Hearing on Recall App

No text available.

19
Stage 1809/03/2021

Delay condonation

The Tribunal granted the respondent one week to file objections regarding the application for condonation of delay and recall of the order dated 09.11.2020, with the matter scheduled for hearing on 02.04.2021.

20
Stage 1918/02/2021

Hearing

No text available.

21
Stage 2028/01/2021

Hearing

No text available.

22
Stage 21Final Ruling Order

Tribunal Order #0901126018082020-27-09-2022

The Tribunal partially allowed the allottee's appeal by modifying the interest period for delay from 01.11.2016 to 29.05.2019 to the full period from 24.12.2012 to 29.05.2019, while dismissing the LDA's appeal and directing the transfer of pre-deposited funds to U.P. RERA for execution.

23
Stage 22Interim Order

Tribunal Order #0901126018082020-29-09-2021

The Tribunal allowed the application to condone delay and recalled the dismissal order dated 09.11.2020, thereby restoring the case to its original number.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal partially allowed the allottee's appeal by modifying the interest period for delay from 01.11.2016 to 29.05.2019 to the full period from 24.12.2012 to 29.05.2019, while dismissing the LDA's appeal and directing the transfer of pre-deposited funds to U.P. RERA for execution. Awarded in favor of Respondent. Awarded interest rate: SBI's MCLR+1%.

Disposal Winner: RespondentInterest Rate: SBI's MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal partially allowed the allottee's appeal by modifying the interest period for delay from 01.11.2016 to 29.05.2019 to the full period from 24.12.2012 to 29.05.2019, while dismissing the LDA's appeal and directing the transfer of pre-deposited funds to U.P. RERA for execution.

Ruling Awarded To

Respondent

Awarded Interest Rate

SBI's MCLR+1%

Interest Period

from 24.12.2012 to 29.05.2019

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 14(3)Section 12

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Anoop Kumar

Respondent Advocate(s)

  • Saurabh Misra

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126018082020-27-09-2022

The Tribunal partially allowed the allottee's appeal by modifying the interest period for delay from 01.11.2016 to 29.05.2019 to the full period from 24.12.2012 to 29.05.2019, while dismissing the LDA's appeal and directing the transfer of pre-deposited funds to U.P. RERA for execution.

INTERIM_ORDEROrder ID: 0901126018082020-29-09-2021

The Tribunal allowed the application to condone delay and recalled the dismissal order dated 09.11.2020, thereby restoring the case to its original number.

TathyaGrid RERA Intelligence AI

Need to research all rulings for logix city developers private limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →