CASE ID: 0901126018072024

Appellant / Complainant

Sangeeta Saxena

VS

Respondent

Astha Infracity Limited

Developer Firm

astha infracity limited

Disputed Amount

24,30,000

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionUnfair Cancellation & Forfeiture

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

19 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126018072024 by Sangeeta Saxena against Astha Infracity Limited before up_rera.

Delay in PossessionUnfair Cancellation & Forfeiture
2
Stage 123/07/2025

Hearing

The Tribunal quashed the U.P. RERA order and restored the appellant's complaint, directing U.P. RERA to decide the matter afresh, including the legality and validity of the unit's cancellation, within 12 weeks.

3
Stage 208/07/2025

Hearing

The Tribunal granted the respondent 10 days to file objections to the appellant's amendment application and scheduled the next hearing for July 23, 2025.

4
Stage 308/05/2025

For Order

The Tribunal adjourned the appeal to 08.07.2025 for orders and directed the parties to exchange pleadings in the interim.

5
Stage 415/04/2025

For Order

The Tribunal has adjourned the appeal to 08.05.2025 upon the joint request of the parties and directed that pleadings be exchanged in the interim.

6
Stage 519/03/2025

For Order

The Tribunal granted a request from the appellant's counsel to reschedule the hearing of the appeal to 15.04.2025.

7
Stage 618/02/2025

For Order

The Tribunal granted a request to list the appeal for hearing on 19.03.2025 and directed the parties to exchange pleadings in the interim.

8
Stage 724/01/2025

For Order

The Tribunal granted a prayer to list the appeal on 18.02.2025.

9
Stage 820/12/2024

For Order

The Tribunal noted a procedural objection regarding the lack of endorsement on the respondent's objections and directed the parties to complete the exchange of pleadings before the next hearing on 24.01.2025.

10
Stage 927/11/2024

Admission

The Tribunal granted an adjournment requested by the respondent's counsel and scheduled the matter for orders on 20.12.2024, noting that no further adjournments will be permitted.

11
Stage 1022/10/2024

Admission

The Tribunal adjourned the matter to 27.11.2024 for orders upon the appellant's request and directed the respondent to file any objections in the interim.

12
Stage 1112/09/2024

Admission

The Tribunal granted an adjournment due to the appellant's counsel's illness and directed the respondent to file objections within seven days, with the appellant to reply thereafter.

13
Stage 1209/08/2024

For Order

The Tribunal granted the respondent seven days to file a vakalatnama and objections, with a subsequent one-week deadline for the appellant to file a reply, and scheduled the case for orders on 12.09.2024.

14
Stage 1311/07/2024

For Order

The Tribunal granted the respondent 10 days to file objections and provide a soft copy to the appellant, with the appellant permitted to file a reply within one week thereafter. The matter is scheduled for hearing on 09.08.2024.

15
Stage 1414/05/2024

Defect Removal

The Tribunal converted the defective appeal into a regular appeal and directed the issuance of notice to the respondent, with the next hearing scheduled for 11.07.2024.

16
Stage 1502/05/2024

Defect Removal

The Tribunal granted the appellant one week to rectify registry defects and directed that typed copies be uploaded if scanned documents are illegible. The matter is scheduled for orders on 14.05.2024.

17
Stage 1622/04/2024

Defect Removal

The Tribunal noted the absence of the appellant's counsel and ordered the defective appeal to be listed for orders on 02.05.2024.

18
Stage 17Final Ruling Order

Tribunal Order #0901126018072024-23-07-2025

The Tribunal quashed the U.P. RERA order and restored the appellant's complaint, directing U.P. RERA to decide the matter afresh, including the legality and validity of the unit's cancellation, within 12 weeks.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal quashed the U.P. RERA order and restored the appellant's complaint, directing U.P. RERA to decide the matter afresh, including the legality and validity of the unit's cancellation, within 12 weeks. Awarded in favor of Appellant.

Disposal Winner: AppellantStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal quashed the U.P. RERA order and restored the appellant's complaint, directing U.P. RERA to decide the matter afresh, including the legality and validity of the unit's cancellation, within 12 weeks.

Ruling Awarded To

Appellant

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(5)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Aniket Raj

Respondent Advocate(s)

  • Samrat Vaish

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126018072024-23-07-2025

The Tribunal quashed the U.P. RERA order and restored the appellant's complaint, directing U.P. RERA to decide the matter afresh, including the legality and validity of the unit's cancellation, within 12 weeks.