Appellant / Complainant
Antriksh Reatech Pvt. Ltd.
Respondent
Prem Babu Gupta
antriksh reatech pvt. ltd.
₹2,11,000
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126018032022 by Antriksh Reatech Pvt. Ltd. against Prem Babu Gupta before up_rera.
For Order
The Tribunal corrected a typographical error in its previous order dated 31.05.2022, changing the date of the impugned Regulatory Authority order from 15.03.2019 to 31.12.2018.
For Order
The Tribunal rejected the appellant's application for the release of pre-deposited funds and directed that the amount be transferred to the U.P. RERA to be distributed to the respondent/allottee in accordance with existing execution proceedings.
For Order
The Tribunal granted the respondent one week's time to file objections regarding an application for the release of funds deposited under Section 43(5) of the Act and scheduled the matter for May 31, 2022.
Tribunal Order #0901126018032022-31-05-2022
The Tribunal rejected the appellant's application for the release of pre-deposited funds and directed that the amount be transferred to the U.P. RERA to be distributed to the respondent/allottee in accordance with existing execution proceedings.
Tribunal Disposal & Final Award Ruling
The Tribunal rejected the appellant's application for the release of pre-deposited funds and directed that the amount be transferred to the U.P. RERA to be distributed to the respondent/allottee in accordance with existing execution proceedings. Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal rejected the appellant's application for the release of pre-deposited funds and directed that the amount be transferred to the U.P. RERA to be distributed to the respondent/allottee in accordance with existing execution proceedings.
Ruling Awarded To
Respondent
Statutory Sections Cited (RERA Act 2016)
Official RERA Tribunal Orders (1)
The Tribunal rejected the appellant's application for the release of pre-deposited funds and directed that the amount be transferred to the U.P. RERA to be distributed to the respondent/allottee in accordance with existing execution proceedings.
Need to research all rulings for antriksh reatech pvt. ltd.?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.