Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126018002020 by Paarth Infrabuild Pvt. Ltd. against Sushil Kumar Saxena, Paarth Infrabuild Pvt. Ltd. before up_rera.
Hearing
The Tribunal allowed the appellant to withdraw the appeal and directed that the amount deposited under Section 43(5) of the Act be handled by the Regulatory Authority to ensure proper distribution to the allottee or refund to the promoter.
Hearing
The Tribunal issued notice to the respondent following compliance with Section 43(5) of the Act and established a procedural timeline for filing objections and replies.
Hearing on Appeal
The Tribunal granted an adjournment requested by the counsel for the applicant due to the illness of the Senior Advocate and rescheduled the hearing for 04.01.2022.
Hearing on Appeal
The Tribunal granted a request by the appellant's counsel to adjourn the matter and rescheduled the case for hearing on 20.12.2021 to coincide with related cases.
Hearing
The Tribunal issued a notice to the respondents and directed the appellant to serve the memo of appeal via speed post and email, with the matter scheduled for hearing on 10.11.2021.
Further Hearing
The Tribunal issued notice to respondent numbers 3 and 4, permitting the appellant to serve them via dasti summons and directing the filing of a reply to objections from respondents 1 and 2.
Compliance of section 43(5)
The appeal was adjourned due to advocates abstaining from work on the call of the Oudh Bar Association, with the matter rescheduled for 15.03.2021.
Further Order
The Tribunal granted a request by the appellant's counsel to adjourn the matter and rescheduled the case for further hearing on 24.02.2021.
Tribunal Order #0901126018002020-08-03-2022
The Tribunal allowed the appellant to withdraw the appeal and directed that the amount deposited under Section 43(5) of the Act be handled by the Regulatory Authority to ensure proper distribution to the allottee or refund to the promoter.
Tribunal Disposal & Final Award Ruling
The Tribunal allowed the appellant to withdraw the appeal and directed that the amount deposited under Section 43(5) of the Act be handled by the Regulatory Authority to ensure proper distribution to the allottee or refund to the promoter. Awarded in favor of Appellant.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal allowed the appellant to withdraw the appeal and directed that the amount deposited under Section 43(5) of the Act be handled by the Regulatory Authority to ensure proper distribution to the allottee or refund to the promoter.
Ruling Awarded To
Appellant
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Rajiv Shukla
- Rahul Shukla
Respondent Advocate(s)
- In Person
Official RERA Tribunal Orders (1)
The Tribunal allowed the appellant to withdraw the appeal and directed that the amount deposited under Section 43(5) of the Act be handled by the Regulatory Authority to ensure proper distribution to the allottee or refund to the promoter.
Need to research all rulings for paarth infrabuild pvt. ltd.?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.