up_reraStatus: Completed
CASE ID: 0901126017942025

Appellant / Complainant

Mohit Tyagi

VS

Respondent

U.P. Awas Evam Vikas Parishad

Disputed Amount

5,20,000

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Non-Compliance & Execution

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

25 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126017942025 by Mohit Tyagi against U.P. Awas Evam Vikas Parishad before up_rera.

Non-Compliance & Execution
2
Stage 120/05/2026

Execution

The Tribunal disposed of the execution application (EA-14/2025) as the decree has been satisfied following the recovery of Rs. 5,20,000/- by the District Collector Meerut.

3
Stage 220/04/2026

Execution

The Tribunal issued bailable warrants to the District Collector of Meerut for failure to comply with previous orders regarding the recovery of Rs. 5,20,000/-, requiring him to show cause why coercive measures should not be taken against him.

4
Stage 325/03/2026

Execution

The Tribunal directed the Registry to send a reminder to the District Collector of Meerut regarding the recovery of Rs. 5,20,000/- as per the previous order dated 10.02.2026.

5
Stage 409/03/2026

Execution

The Tribunal granted the decree holder seven days to upload the bank details of the judgment debtor and adjourned the matter to March 25, 2026.

6
Stage 510/02/2026

Execution

The Tribunal directed the District Collector of Meerut to issue a recovery notice for Rs. 5,20,000/- by attaching the bank accounts of the respondent-judgment debtor (U.P. Awas Evam Vikas Parishad) due to non-compliance with a previous judgment and decree.

7
Stage 613/01/2026

Execution

The Tribunal noted that the High Court is currently handling an injunction application related to this matter and has adjourned the case for orders to 10.02.2026.

8
Stage 708/12/2025

Execution

The Tribunal adjourned the matter to 13.01.2026 and advised the respondent/judgment debtor to seek an appropriate order under Order-41 Rule-5 of the CPC in the interim.

9
Stage 813/11/2025

Execution

No text available.

10
Stage 910/11/2025

Execution

The Tribunal directed the respondent (judgment debtor) to comply with the existing judgment and decree and scheduled the application for hearing before an appropriate Bench on 13.11.2025.

11
Stage 1008/10/2025

Execution

The Tribunal granted a request by the counsel for the judgment debtor to adjourn the application (E.A. No. 14/2025) and scheduled it for hearing on 10.11.2025.

12
Stage 1115/09/2025

Execution

The Tribunal recorded an undertaking from the respondent to issue a fresh bank draft directly in favor of the decree holder to satisfy the decree after objections were raised regarding the previous payment method.

13
Stage 1229/08/2025

Execution

The Tribunal rejected the respondent's request to stay execution due to a pending High Court appeal and instead ordered the judgment debtor to show cause why their bank account should not be attached to satisfy the decree.

14
Stage 1312/08/2025

Execution

The Tribunal has adjourned the matter to 29.08.2025 following a submission that a RERA Appeal has been filed before the Hon'ble High Court.

15
Stage 1411/07/2025

Execution

The respondent-judgment debtor is directed to file a compliance affidavit satisfying the decree, and the matter is scheduled for hearing on 12.08.2025.

16
Stage 1521/05/2025

Execution

The Tribunal issued a notice to the respondent regarding EA No. 14 of 2025 and outlined the procedural requirements for service of notice and filing of objections before the next hearing on July 11, 2025.

17
Stage 16Interim Order

Tribunal Order #0901126017942025-20-04-2026

The Tribunal issued bailable warrants to the District Collector of Meerut for failure to comply with previous orders regarding the recovery of Rs. 5,20,000/-, requiring him to show cause why coercive measures should not be taken against him.

18
Stage 17Interim Order

Tribunal Order #0901126017942025-10-11-2025

The Tribunal directed the respondent (judgment debtor) to comply with the existing judgment and decree and scheduled the application for hearing before an appropriate Bench on 13.11.2025.

19
Stage 18Interim Order

Tribunal Order #0901126017942025-29-08-2025

The Tribunal rejected the respondent's request to stay execution due to a pending High Court appeal and instead ordered the judgment debtor to show cause why their bank account should not be attached to satisfy the decree.

20
Stage 19Interim Order

Tribunal Order #0901126017942025-11-07-2025

The respondent-judgment debtor is directed to file a compliance affidavit satisfying the decree, and the matter is scheduled for hearing on 12.08.2025.

21
Stage 20Final Ruling Order

Tribunal Order #0901126017942025-20-05-2026

The Tribunal disposed of the execution application (EA-14/2025) as the decree has been satisfied following the recovery of Rs. 5,20,000/- by the District Collector Meerut.

22
Stage 21Interim Order

Tribunal Order #0901126017942025-25-03-2026

The Tribunal directed the Registry to send a reminder to the District Collector of Meerut regarding the recovery of Rs. 5,20,000/- as per the previous order dated 10.02.2026.

23
Stage 22Interim Order

Tribunal Order #0901126017942025-10-02-2026

The Tribunal directed the District Collector of Meerut to issue a recovery notice for Rs. 5,20,000/- by attaching the bank accounts of the respondent-judgment debtor (U.P. Awas Evam Vikas Parishad) due to non-compliance with a previous judgment and decree.

24
Stage 23Interim Order

Tribunal Order #0901126017942025-15-09-2025

The Tribunal recorded an undertaking from the respondent to issue a fresh bank draft directly in favor of the decree holder to satisfy the decree after objections were raised regarding the previous payment method.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal disposed of the execution application (EA-14/2025) as the decree has been satisfied following the recovery of Rs. 5,20,000/- by the District Collector Meerut. Awarded in favor of Appellant.

Disposal Winner: AppellantStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal disposed of the execution application (EA-14/2025) as the decree has been satisfied following the recovery of Rs. 5,20,000/- by the District Collector Meerut.

Ruling Awarded To

Appellant

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 40Section 63Section 64

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Rishindra Vikram Singh

Respondent Advocate(s)

  • Vinay Kumar Pandey

Official RERA Tribunal Orders (8)

INTERIM_ORDEROrder ID: 0901126017942025-20-04-2026

The Tribunal issued bailable warrants to the District Collector of Meerut for failure to comply with previous orders regarding the recovery of Rs. 5,20,000/-, requiring him to show cause why coercive measures should not be taken against him.

INTERIM_ORDEROrder ID: 0901126017942025-10-11-2025

The Tribunal directed the respondent (judgment debtor) to comply with the existing judgment and decree and scheduled the application for hearing before an appropriate Bench on 13.11.2025.

INTERIM_ORDEROrder ID: 0901126017942025-29-08-2025

The Tribunal rejected the respondent's request to stay execution due to a pending High Court appeal and instead ordered the judgment debtor to show cause why their bank account should not be attached to satisfy the decree.

INTERIM_ORDEROrder ID: 0901126017942025-11-07-2025

The respondent-judgment debtor is directed to file a compliance affidavit satisfying the decree, and the matter is scheduled for hearing on 12.08.2025.

FINAL_ORDEROrder ID: 0901126017942025-20-05-2026

The Tribunal disposed of the execution application (EA-14/2025) as the decree has been satisfied following the recovery of Rs. 5,20,000/- by the District Collector Meerut.

INTERIM_ORDEROrder ID: 0901126017942025-25-03-2026

The Tribunal directed the Registry to send a reminder to the District Collector of Meerut regarding the recovery of Rs. 5,20,000/- as per the previous order dated 10.02.2026.

INTERIM_ORDEROrder ID: 0901126017942025-10-02-2026

The Tribunal directed the District Collector of Meerut to issue a recovery notice for Rs. 5,20,000/- by attaching the bank accounts of the respondent-judgment debtor (U.P. Awas Evam Vikas Parishad) due to non-compliance with a previous judgment and decree.

INTERIM_ORDEROrder ID: 0901126017942025-15-09-2025

The Tribunal recorded an undertaking from the respondent to issue a fresh bank draft directly in favor of the decree holder to satisfy the decree after objections were raised regarding the previous payment method.