Appellant / Complainant
Sameer Kumar Mishra
Respondent
Lucknow Development Authority
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126017902021 by Sameer Kumar Mishra against Lucknow Development Authority before up_rera.
for delivery of Judgment/Order
The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the period from 27.04.2013 to 26.10.2016, while directing the transfer of deposited funds under Section 43(5) to the Regulatory Authority.
Further Order
The U.P. Real Estate Appellate Tribunal has scheduled Appeal-924/2021 for the delivery of judgment on December 30, 2022.
Further Order
The Tribunal granted a joint request from the counsels of both parties to adjourn the matter and rescheduled the hearing for 29.11.2022, to be heard alongside Appeal No. 47/2021.
Further Order
The Tribunal noted the absence of the appellant and directed both counsels to be present at the next hearing, scheduling the appeal for 30.09.2022.
Further Order
The Tribunal directed the parties to exchange a list of dates, events, and relied-upon cases at least 10 days prior to the next hearing, scheduling the matter for final hearing on 01.09.2022.
Hearing
The Tribunal records that the appeal has already been directed to be listed on 11.08.2022 via a previous order dated 21.07.2022.
Hearing
The Tribunal granted the appellant's request to file a replication against the respondent's reply and directed the matter to be listed for hearing on 21.07.2022.
Delay condonation
The Tribunal condoned the 83-day delay in filing the appeal due to the COVID-19 pandemic period recognized by the Supreme Court and directed the appellant to file a replication/rejoinder before the next hearing.
Delay condonation
The Tribunal granted an adjournment requested by the appellant's counsel due to illness and scheduled the matter for April 5, 2022, to consider the application for condonation of delay.
Defect Removal
The Tribunal directed the respondent's counsel to correctly upload his Vakalatnama on the e-portal and granted the applicant ten days to file a reply to the respondent's objections.
Defect Removal
The Tribunal directed the issuance of notice to the respondent via registered post and email and scheduled the case for January 12, 2022, to dispose of a limitation application.
Tribunal Order #0901126017902021-30-12-2022
The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the period from 27.04.2013 to 26.10.2016, while directing the transfer of deposited funds under Section 43(5) to the Regulatory Authority.
Tribunal Order #0901126017902021-05-04-2022
The Tribunal condoned the 83-day delay in filing the appeal due to the COVID-19 pandemic period recognized by the Supreme Court and directed the appellant to file a replication/rejoinder before the next hearing.
Tribunal Disposal & Final Award Ruling
The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the period from 27.04.2013 to 26.10.2016, while directing the transfer of deposited funds under Section 43(5) to the Regulatory Authority. Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the period from 27.04.2013 to 26.10.2016, while directing the transfer of deposited funds under Section 43(5) to the Regulatory Authority.
Ruling Awarded To
Respondent
Interest Period
from 27.04.2013 to 26.10.2016
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Alok Sinha
Respondent Advocate(s)
- Amit Yadav
Official RERA Tribunal Orders (2)
The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the period from 27.04.2013 to 26.10.2016, while directing the transfer of deposited funds under Section 43(5) to the Regulatory Authority.
The Tribunal condoned the 83-day delay in filing the appeal due to the COVID-19 pandemic period recognized by the Supreme Court and directed the appellant to file a replication/rejoinder before the next hearing.
Need to research all rulings for a builder?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.