up_reraStatus: Completed
CASE ID: 0901126017872020

Appellant / Complainant

U.P. Avas Evam Vikas Parishad

VS

Respondent

Arvind Chaudhary, Uttar Pradesh Real Estate Regulatory Authority

Disposal Award

Unknown

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

26 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126017872020 by U.P. Avas Evam Vikas Parishad against Arvind Chaudhary, Uttar Pradesh Real Estate Regulatory Authority before up_rera.

2
Stage 126/09/2024

For Order

The Tribunal issued a corrective order to rectify a typographical error in the judgment dated 09.01.2024, changing the first digit of the RERA Complaint number from '6' to '9'.

3
Stage 224/09/2024

For Order

The Tribunal noted a clerical error regarding a digit in the Complaint Number in a previous judgment and scheduled the matter for orders on 26.09.2024.

4
Stage 309/01/2024

for delivery of Judgment/Order

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by U.P. Avas Evam Vikas Parishad, upholding the Regulatory Authority's order to pay interest for delayed possession and directing the transfer of the promoter's pre-deposited amount to the Regulatory Authority for disbursement to the allottee.

5
Stage 404/01/2024

Hearing

The Tribunal directed the release of Rs 4,000 to the respondent from a previously deposited amount and reserved judgment following arguments regarding whether litigation-induced delays constitute Force Majeure.

6
Stage 527/09/2023

Hearing

No text available.

7
Stage 614/08/2023

Hearing

No text available.

8
Stage 731/05/2023

Hearing

The Tribunal adjourned the appeal to 14.08.2023 because the counsel for the respondent was reported to be out of station.

9
Stage 820/04/2023

Hearing

The Tribunal granted an adjournment requested by the respondent's counsel due to illness and rescheduled the matter for 31.05.2023.

10
Stage 912/04/2023

Hearing

The Tribunal granted the appellant one week to comply with a previous order dated 23.03.2021 regarding the payment of costs, warning that failure to comply may result in enhanced penalties.

11
Stage 1001/03/2023

Hearing

The Tribunal has rescheduled the appeal for a fresh hearing on 12.04.2023 because the previous Bench's presiding member demitted office before the reserved judgment could be delivered.

12
Stage 1111/03/2022

Hearing

The Tribunal heard arguments from both parties regarding the legality of interest rates for delayed possession and reserved its judgment.

13
Stage 1210/01/2022

Hearing

The Tribunal scheduled the appeal for a final hearing on January 31, 2022.

14
Stage 1310/12/2021

Hearing

The Tribunal granted an adjournment application filed by the appellant's counsel and rescheduled the hearing for January 10, 2022.

15
Stage 1410/11/2021

Hearing

No text available.

16
Stage 1521/09/2021

Hearing

The Tribunal adjourned the appeal due to the absence of the Appellant and scheduled the next hearing for 10.11.2021.

17
Stage 1622/04/2021

Hearing

No text available.

18
Stage 1723/03/2021

Hearing on Appeal

The Tribunal imposed a cost of Rs. 8,000 on the appellant for failure to comply with previous directions and ordered both parties to exchange settlement proposals and certified calculation charts.

19
Stage 1827/01/2021

Hearing

The Tribunal directed the respondent to provide details of any remaining amounts receivable after adjusting Rs. 9,48,125/- and ordered the appellant to file a CA-certified calculation chart. Additionally, both parties are directed to appear for potential settlement on the next hearing date.

20
Stage 1914/12/2020

Hearing

No text available.

21
Stage 20Final Ruling Order

Tribunal Order #0901126017872020-09-01-2024

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by U.P. Avas Evam Vikas Parishad, upholding the Regulatory Authority's order to pay interest for delayed possession and directing the transfer of the promoter's pre-deposited amount to the Regulatory Authority for disbursement to the allottee.

22
Stage 21Interim Order

Tribunal Order #0901126017872020-04-01-2024

The Tribunal directed the release of Rs 4,000 to the respondent from a previously deposited amount and reserved judgment following arguments regarding whether litigation-induced delays constitute Force Majeure.

23
Stage 22Interim Order

Tribunal Order #0901126017872020-23-03-2021

The Tribunal imposed a cost of Rs. 8,000 on the appellant for failure to comply with previous directions and ordered both parties to exchange settlement proposals and certified calculation charts.

24
Stage 23Interim Order

Tribunal Order #0901126017872020-12-04-2023

The Tribunal granted the appellant one week to comply with a previous order dated 23.03.2021 regarding the payment of costs, warning that failure to comply may result in enhanced penalties.

25
Stage 24Interim Order

Tribunal Order #0901126017872020-27-01-2021

The Tribunal directed the respondent to provide details of any remaining amounts receivable after adjusting Rs. 9,48,125/- and ordered the appellant to file a CA-certified calculation chart. Additionally, both parties are directed to appear for potential settlement on the next hearing date.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by U.P. Avas Evam Vikas Parishad, upholding the Regulatory Authority's order to pay interest for delayed possession and directing the transfer of the promoter's pre-deposited amount to the Regulatory Authority for disbursement to the allottee. Awarded in favor of Unknown.

Disposal Winner: UnknownStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by U.P. Avas Evam Vikas Parishad, upholding the Regulatory Authority's order to pay interest for delayed possession and directing the transfer of the promoter's pre-deposited amount to the Regulatory Authority for disbursement to the allottee.

Ruling Awarded To

Unknown

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Akhand Pratap Singh
  • Vijay Pratap Singh Chauhan

Respondent Advocate(s)

  • Tushar Bahadur
  • Rakshit Raj Singh

Official RERA Tribunal Orders (5)

FINAL_ORDEROrder ID: 0901126017872020-09-01-2024

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by U.P. Avas Evam Vikas Parishad, upholding the Regulatory Authority's order to pay interest for delayed possession and directing the transfer of the promoter's pre-deposited amount to the Regulatory Authority for disbursement to the allottee.

INTERIM_ORDEROrder ID: 0901126017872020-04-01-2024

The Tribunal directed the release of Rs 4,000 to the respondent from a previously deposited amount and reserved judgment following arguments regarding whether litigation-induced delays constitute Force Majeure.

INTERIM_ORDEROrder ID: 0901126017872020-23-03-2021

The Tribunal imposed a cost of Rs. 8,000 on the appellant for failure to comply with previous directions and ordered both parties to exchange settlement proposals and certified calculation charts.

INTERIM_ORDEROrder ID: 0901126017872020-12-04-2023

The Tribunal granted the appellant one week to comply with a previous order dated 23.03.2021 regarding the payment of costs, warning that failure to comply may result in enhanced penalties.

INTERIM_ORDEROrder ID: 0901126017872020-27-01-2021

The Tribunal directed the respondent to provide details of any remaining amounts receivable after adjusting Rs. 9,48,125/- and ordered the appellant to file a CA-certified calculation chart. Additionally, both parties are directed to appear for potential settlement on the next hearing date.

TathyaGrid RERA Intelligence AI

Need to research all rulings for a builder?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →