Appellant / Complainant
Wall Rock Infratech Pvt Ltd
Respondent
Uttar Pradesh Real Estate Regulatory Authority, Priya Kapoor Das
wall rock infratech pvt ltd
Respondent
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126017832024 by Wall Rock Infratech Pvt Ltd against Uttar Pradesh Real Estate Regulatory Authority, Priya Kapoor Das before up_rera.
Delay condonation
The appellant, Wall Rock Infratech Pvt Ltd, requested to withdraw the appeal, and the Tribunal ordered the appeal to be dismissed as withdrawn.
Delay condonation
The Tribunal granted a request for adjournment due to the respondent's counsel being out of station and scheduled the case for orders on March 3, 2025.
Delay condonation
The Tribunal granted the appellant one week to file a rejoinder to the respondent's objections and scheduled the matter for hearing on February 6, 2025.
Delay condonation
The Tribunal granted the appellant's counsel two weeks to file a rejoinder and scheduled the next hearing for January 3, 2025.
Delay condonation
The Tribunal granted the appellant two weeks' time to file a rejoinder affidavit regarding the respondent's objections to the application for condonation of delay and scheduled the matter for orders on 11.11.2024.
Delay condonation
The Tribunal granted the respondent 10 days to file objections against the appeal and the application for condonation of delay, with a subsequent timeline set for the appellant's reply.
Delay condonation
The Tribunal provisionally accepts the appellant's payment of Rs. 67,11,191/- as sufficient compliance with Section 43(5) of the Act and directs that this amount be kept in a fixed deposit for two months without being released to the respondent pending further hearing.
Delay condonation
The Tribunal noted that the counsel for the appellant was out of station and ordered the defective appeal to be listed for orders on 30.07.2024.
Delay condonation
The Tribunal noted that the appellant failed to provide proof that the paid amount was specifically for the Recovery Certificate dated 04.10.2023 and has adjourned the matter to 31.05.2024 to allow the applicant to obtain a certificate from the Tehsildar.
Tribunal Order #0901126017832024-30-07-2024
The Tribunal provisionally accepts the appellant's payment of Rs. 67,11,191/- as sufficient compliance with Section 43(5) of the Act and directs that this amount be kept in a fixed deposit for two months without being released to the respondent pending further hearing.
Tribunal Disposal & Final Award Ruling
Dismissed as withdrawn Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
Dismissed as withdrawn
Ruling Awarded To
Respondent
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Amit Yadav
Respondent Advocate(s)
- Ankit Tripathi
- Ashutosh Ojha
Official RERA Tribunal Orders (1)
The Tribunal provisionally accepts the appellant's payment of Rs. 67,11,191/- as sufficient compliance with Section 43(5) of the Act and directs that this amount be kept in a fixed deposit for two months without being released to the respondent pending further hearing.