Appellant / Complainant
Banarasi Singh
Respondent
Ansal Properties & Infrastructure Ltd.
ansal properties & infrastructure ltd.
₹2,00,000
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126017832020 by Banarasi Singh against Ansal Properties & Infrastructure Ltd. before up_rera.
for delivery of Judgment/Order
The Tribunal dismissed the appeal, upholding the Regulatory Authority's decision that the Real Estate (Regulation and Development) Act 2016 is not applicable because the project had received its completion certificate prior to the enforcement of Section 3.
Final Hearing
The appellant challenges a RERA order regarding the non-maintainability of their complaint and seeks interest for delay under Section 18 of the Act; however, the Tribunal has reserved its judgment.
Hearing
The Tribunal granted an adjournment requested by the appellant and scheduled the appeal for a final hearing on 17.11.2021, with instructions that no further adjournments will be permitted.
Hearing
The Tribunal granted an adjournment following the appellant's counsel's request to withdraw his Vakalatnama and directed the appellant to file a reply to the respondent's objections by the next hearing date of 26.10.2021.
Hearing
The Tribunal directed both parties to file a list of dates and events along with relied-upon judgments within 10 days and scheduled the matter for hearing on 15.04.2021.
Hearing
The Tribunal granted an adjournment requested by the respondent's counsel due to illness and rescheduled the hearing for 18.03.2021.
Tribunal Order #0901126017832020-25-02-2022
The Tribunal dismissed the appeal, upholding the Regulatory Authority's decision that the Real Estate (Regulation and Development) Act 2016 is not applicable because the project had received its completion certificate prior to the enforcement of Section 3.
Tribunal Order #0901126017832020-17-11-2021
The appellant challenges a RERA order regarding the non-maintainability of their complaint and seeks interest for delay under Section 18 of the Act; however, the Tribunal has reserved its judgment.
Tribunal Disposal & Final Award Ruling
The Tribunal dismissed the appeal, upholding the Regulatory Authority's decision that the Real Estate (Regulation and Development) Act 2016 is not applicable because the project had received its completion certificate prior to the enforcement of Section 3. Awarded in favor of Respondent. Awarded interest rate: 18%.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal dismissed the appeal, upholding the Regulatory Authority's decision that the Real Estate (Regulation and Development) Act 2016 is not applicable because the project had received its completion certificate prior to the enforcement of Section 3.
Ruling Awarded To
Respondent
Awarded Interest Rate
18%
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Saurabh Misra
Respondent Advocate(s)
- Manoj Kumar
Official RERA Tribunal Orders (2)
The Tribunal dismissed the appeal, upholding the Regulatory Authority's decision that the Real Estate (Regulation and Development) Act 2016 is not applicable because the project had received its completion certificate prior to the enforcement of Section 3.
The appellant challenges a RERA order regarding the non-maintainability of their complaint and seeks interest for delay under Section 18 of the Act; however, the Tribunal has reserved its judgment.
Need to research all rulings for ansal properties & infrastructure ltd.?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.