up_reraStatus: Completed
CASE ID: 0901126017832020

Appellant / Complainant

Banarasi Singh

VS

Respondent

Ansal Properties & Infrastructure Ltd.

Developer Firm

ansal properties & infrastructure ltd.

Disputed Amount

2,00,000

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

12 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126017832020 by Banarasi Singh against Ansal Properties & Infrastructure Ltd. before up_rera.

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability
2
Stage 125/02/2022

for delivery of Judgment/Order

The Tribunal dismissed the appeal, upholding the Regulatory Authority's decision that the Real Estate (Regulation and Development) Act 2016 is not applicable because the project had received its completion certificate prior to the enforcement of Section 3.

3
Stage 217/11/2021

Final Hearing

The appellant challenges a RERA order regarding the non-maintainability of their complaint and seeks interest for delay under Section 18 of the Act; however, the Tribunal has reserved its judgment.

4
Stage 326/10/2021

Hearing

The Tribunal granted an adjournment requested by the appellant and scheduled the appeal for a final hearing on 17.11.2021, with instructions that no further adjournments will be permitted.

5
Stage 415/09/2021

Hearing

The Tribunal granted an adjournment following the appellant's counsel's request to withdraw his Vakalatnama and directed the appellant to file a reply to the respondent's objections by the next hearing date of 26.10.2021.

6
Stage 515/04/2021

Hearing

No text available.

7
Stage 618/03/2021

Hearing

The Tribunal directed both parties to file a list of dates and events along with relied-upon judgments within 10 days and scheduled the matter for hearing on 15.04.2021.

8
Stage 725/01/2021

Hearing

The Tribunal granted an adjournment requested by the respondent's counsel due to illness and rescheduled the hearing for 18.03.2021.

9
Stage 808/12/2020

Hearing

No text available.

10
Stage 9Final Ruling Order

Tribunal Order #0901126017832020-25-02-2022

The Tribunal dismissed the appeal, upholding the Regulatory Authority's decision that the Real Estate (Regulation and Development) Act 2016 is not applicable because the project had received its completion certificate prior to the enforcement of Section 3.

11
Stage 10Interim Order

Tribunal Order #0901126017832020-17-11-2021

The appellant challenges a RERA order regarding the non-maintainability of their complaint and seeks interest for delay under Section 18 of the Act; however, the Tribunal has reserved its judgment.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal dismissed the appeal, upholding the Regulatory Authority's decision that the Real Estate (Regulation and Development) Act 2016 is not applicable because the project had received its completion certificate prior to the enforcement of Section 3. Awarded in favor of Respondent. Awarded interest rate: 18%.

Disposal Winner: RespondentInterest Rate: 18%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal dismissed the appeal, upholding the Regulatory Authority's decision that the Real Estate (Regulation and Development) Act 2016 is not applicable because the project had received its completion certificate prior to the enforcement of Section 3.

Ruling Awarded To

Respondent

Awarded Interest Rate

18%

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Saurabh Misra

Respondent Advocate(s)

  • Manoj Kumar

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126017832020-25-02-2022

The Tribunal dismissed the appeal, upholding the Regulatory Authority's decision that the Real Estate (Regulation and Development) Act 2016 is not applicable because the project had received its completion certificate prior to the enforcement of Section 3.

INTERIM_ORDEROrder ID: 0901126017832020-17-11-2021

The appellant challenges a RERA order regarding the non-maintainability of their complaint and seeks interest for delay under Section 18 of the Act; however, the Tribunal has reserved its judgment.

TathyaGrid RERA Intelligence AI

Need to research all rulings for ansal properties & infrastructure ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →