up_reraStatus: Completed
CASE ID: 0901126017802022

Appellant / Complainant

Uttar Pradesh State Industrial Development Authority (Formerly Known As Upsidc)

VS

Respondent

Rashmi

Disputed Amount

22,88,656

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionRefund of InvestmentDelay Compensation / InterestPromotional MisrepresentationJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

8 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126017802022 by Uttar Pradesh State Industrial Development Authority (Formerly Known As Upsidc) against Rashmi before up_rera.

Delay in PossessionRefund of InvestmentDelay Compensation / InterestPromotional MisrepresentationJurisdiction & Maintainability
2
Stage 131/08/2022

for delivery of Judgment/Order

The Appellate Tribunal dismissed the appeals filed by UPSIDA, upholding the RERA order for a refund of deposited amounts with interest (MCLR+1%) due to project delays, and directed the transfer of pre-deposited funds to U.P. RERA for disbursement to the respondents.

3
Stage 225/07/2022

Further Order

The Tribunal condoned the delay in filing the appeal based on the Supreme Court's Suo Moto Writ (C) No. 3 of 2020 and directed the Registry to convert the defective appeal into a regular appeal before reserving judgment.

4
Stage 315/07/2022

Defect Removal

The Tribunal granted the appellant a one-week extension to file a reply to the respondent's objections and directed that a soft copy of the reply be emailed to the respondent.

5
Stage 411/07/2022

Defect Removal

The Tribunal granted an adjournment requested by the appellant's counsel and scheduled the defective appeal for further hearing on 15.07.2022, noting that compliance with Section 43(5) of the Act will be examined at that time.

6
Stage 5Final Ruling Order

Tribunal Order #0901126017802022-31-08-2022

The Appellate Tribunal dismissed the appeals filed by UPSIDA, upholding the RERA order for a refund of deposited amounts with interest (MCLR+1%) due to project delays, and directed the transfer of pre-deposited funds to U.P. RERA for disbursement to the respondents.

7
Stage 6Interim Order

Tribunal Order #0901126017802022-25-07-2022

The Tribunal condoned the delay in filing the appeal based on the Supreme Court's Suo Moto Writ (C) No. 3 of 2020 and directed the Registry to convert the defective appeal into a regular appeal before reserving judgment.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Appellate Tribunal dismissed the appeals filed by UPSIDA, upholding the RERA order for a refund of deposited amounts with interest (MCLR+1%) due to project delays, and directed the transfer of pre-deposited funds to U.P. RERA for disbursement to the respondents. Awarded in favor of Respondent. Awarded interest rate: MCLR + 1% p.a..

Disposal Winner: RespondentInterest Rate: MCLR + 1% p.a.Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Appellate Tribunal dismissed the appeals filed by UPSIDA, upholding the RERA order for a refund of deposited amounts with interest (MCLR+1%) due to project delays, and directed the transfer of pre-deposited funds to U.P. RERA for disbursement to the respondents.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR + 1% p.a.

Interest Period

till handing over of the possession

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 12Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Kartikey Dubey

Respondent Advocate(s)

  • Deepak Dwivedi

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126017802022-31-08-2022

The Appellate Tribunal dismissed the appeals filed by UPSIDA, upholding the RERA order for a refund of deposited amounts with interest (MCLR+1%) due to project delays, and directed the transfer of pre-deposited funds to U.P. RERA for disbursement to the respondents.

INTERIM_ORDEROrder ID: 0901126017802022-25-07-2022

The Tribunal condoned the delay in filing the appeal based on the Supreme Court's Suo Moto Writ (C) No. 3 of 2020 and directed the Registry to convert the defective appeal into a regular appeal before reserving judgment.

TathyaGrid RERA Intelligence AI

Need to research all rulings for a builder?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →