Appellant / Complainant
Singh Brothers
Respondent
Uttar Pradesh Real Estate Regulatory Authority Lucknow, Collage Group Infrastructure Pvt. Ltd., Lalit Kumar Singh
collage group infrastructure pvt. ltd.
₹80,12,481
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126017782024 by Singh Brothers against Uttar Pradesh Real Estate Regulatory Authority Lucknow, Collage Group Infrastructure Pvt. Ltd., Lalit Kumar Singh before up_rera.
for delivery of Judgment/Order
The Appellate Tribunal dismissed the appeal filed by M/s Singh Brothers, ruling that they qualify as 'promoters' under Section 2(zk) of the RERA Act and are therefore liable for the recovery certificate issued to satisfy a refund order.
Defect Removal
The Tribunal has heard the arguments from both the appellant and respondent parties and has reserved the judgment for further delivery.
Defect Removal
The Tribunal granted an urgency request from the appellant's counsel and rescheduled the matter for hearing on 31.05.2024.
Defect Removal
The Tribunal granted the respondent three days to file objections, warning that failure to comply may result in summoning the Secretary of U.P. RERA to appear in person with records.
Defect Removal
The Tribunal issued notice to the Respondent regarding the legality of amending a recovery certificate to include the applicant's name for a project in which they claim no promoter/developer liability. The matter is scheduled for hearing on 29.04.2024 to examine compliance with Section 43(5) of the RERA Act.
Tribunal Order #0901126017782024-14-05-2024
The Tribunal granted the respondent three days to file objections, warning that failure to comply may result in summoning the Secretary of U.P. RERA to appear in person with records.
Tribunal Order #0901126017782024-12-06-2024
The Appellate Tribunal dismissed the appeal filed by M/s Singh Brothers, ruling that they qualify as 'promoters' under Section 2(zk) of the RERA Act and are therefore liable for the recovery certificate issued to satisfy a refund order.
Tribunal Order #0901126017782024-22-04-2024
The Tribunal issued notice to the Respondent regarding the legality of amending a recovery certificate to include the applicant's name for a project in which they claim no promoter/developer liability. The matter is scheduled for hearing on 29.04.2024 to examine compliance with Section 43(5) of the RERA Act.
Tribunal Disposal & Final Award Ruling
The Appellate Tribunal dismissed the appeal filed by M/s Singh Brothers, ruling that they qualify as 'promoters' under Section 2(zk) of the RERA Act and are therefore liable for the recovery certificate issued to satisfy a refund order. Awarded in favor of Respondent. Awarded interest rate: MCLR+1% of SBI.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Appellate Tribunal dismissed the appeal filed by M/s Singh Brothers, ruling that they qualify as 'promoters' under Section 2(zk) of the RERA Act and are therefore liable for the recovery certificate issued to satisfy a refund order.
Ruling Awarded To
Respondent
Awarded Interest Rate
MCLR+1% of SBI
Interest Period
from the date payment of first premium till the date of last payment
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Prashant Kumar
- Fuhar Gupta
Respondent Advocate(s)
- Sireesh Kumar
- Sudhanshu Chauhan
Official RERA Tribunal Orders (3)
The Tribunal granted the respondent three days to file objections, warning that failure to comply may result in summoning the Secretary of U.P. RERA to appear in person with records.
The Appellate Tribunal dismissed the appeal filed by M/s Singh Brothers, ruling that they qualify as 'promoters' under Section 2(zk) of the RERA Act and are therefore liable for the recovery certificate issued to satisfy a refund order.
The Tribunal issued notice to the Respondent regarding the legality of amending a recovery certificate to include the applicant's name for a project in which they claim no promoter/developer liability. The matter is scheduled for hearing on 29.04.2024 to examine compliance with Section 43(5) of the RERA Act.