up_reraStatus: Completed
CASE ID: 0901126017602021

Appellant / Complainant

Dinesh Kumar Singh

VS

Respondent

U.P. Avas Evam Vikas Parishad

Disputed Amount

20,88,000

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

12 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126017602021 by Dinesh Kumar Singh against U.P. Avas Evam Vikas Parishad before up_rera.

Delay in PossessionDelay Compensation / Interest
2
Stage 110/03/2022

Further Order

The Tribunal allowed the appeal and modified the previous order to correct the apartment cost from Rs. 17.80 lacs to Rs. 20.88 lacs for the purpose of calculating compensation/interest.

3
Stage 206/01/2022

Further Order

The Tribunal noted the absence of the appellant and the respondent's counsel's submission regarding a clerical error in the impugned order; the case is adjourned to 28.01.2022.

4
Stage 302/12/2021

Further Order

The Tribunal granted an adjournment application filed by the appellant's counsel and directed the respondent to file a reply to the grounds of appeal within three days.

5
Stage 409/11/2021

Delay condonation

The Tribunal condoned a 30-day delay in filing the appeal by applying the Supreme Court's relaxation guidelines regarding the COVID-19 pandemic and converted the defective appeal into a regular appeal.

6
Stage 506/10/2021

Delay condonation

The Tribunal granted the respondent two weeks to file objections regarding the condonation of delay and grounds of appeal, with a subsequent deadline for the applicant's reply and a scheduled hearing on 09.11.2021.

7
Stage 620/04/2021

Delay condonation

No text available.

8
Stage 724/03/2021

Defect Removal

The Tribunal issued notice to the respondent regarding the application for condonation of delay and directed both parties to exchange applications, objections, and replies via email before the next hearing on 20.04.2021.

9
Stage 817/03/2021

Defect Removal

The Tribunal granted the appellant three days to rectify registry defects and scheduled the defective appeal for a hearing on March 24, 2021.

10
Stage 9Interim Order

Tribunal Order #0901126017602021-09-11-2021

The Tribunal condoned a 30-day delay in filing the appeal by applying the Supreme Court's relaxation guidelines regarding the COVID-19 pandemic and converted the defective appeal into a regular appeal.

11
Stage 10Final Ruling Order

Tribunal Order #0901126017602021-10-03-2022

The Tribunal allowed the appeal and modified the previous order to correct the apartment cost from Rs. 17.80 lacs to Rs. 20.88 lacs for the purpose of calculating compensation/interest.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal allowed the appeal and modified the previous order to correct the apartment cost from Rs. 17.80 lacs to Rs. 20.88 lacs for the purpose of calculating compensation/interest. Awarded in favor of Appellant. Awarded interest rate: MCLR+1% per annum.

Disposal Winner: AppellantInterest Rate: MCLR+1% per annumStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal allowed the appeal and modified the previous order to correct the apartment cost from Rs. 17.80 lacs to Rs. 20.88 lacs for the purpose of calculating compensation/interest.

Ruling Awarded To

Appellant

Awarded Interest Rate

MCLR+1% per annum

Interest Period

w.e.f. 31.08.2015 to 05.03.2018

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Azhar Ikram
  • Manish Singh

Respondent Advocate(s)

  • Vijay Pratap Singh Chauhan
  • Akhand Pratap Singh

Official RERA Tribunal Orders (2)

INTERIM_ORDEROrder ID: 0901126017602021-09-11-2021

The Tribunal condoned a 30-day delay in filing the appeal by applying the Supreme Court's relaxation guidelines regarding the COVID-19 pandemic and converted the defective appeal into a regular appeal.

FINAL_ORDEROrder ID: 0901126017602021-10-03-2022

The Tribunal allowed the appeal and modified the previous order to correct the apartment cost from Rs. 17.80 lacs to Rs. 20.88 lacs for the purpose of calculating compensation/interest.