up_reraStatus: Completed
CASE ID: 0901126017542021

Appellant / Complainant

Lakshmi Kant Azad

VS

Respondent

Greater Noida Industrial Development Authority

Disputed Amount

5,18,895

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Refund of InvestmentDelay Compensation / InterestSale Deed & Title Transfer

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

29 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126017542021 by Lakshmi Kant Azad against Greater Noida Industrial Development Authority before up_rera.

Refund of InvestmentDelay Compensation / InterestSale Deed & Title Transfer
2
Stage 129/02/2024

Delay condonation

The Uttar Pradesh Real Estate Appellate Tribunal rejected the applicant's application for condonation of delay of 414 days, ruling that pursuing compliance and execution of a previous order did not constitute 'sufficient cause' to excuse the delay in filing the appeal.

3
Stage 222/01/2024

Delay condonation

The Tribunal has scheduled the appeal for hearing on 29.02.2024 to consider an application for condonation of delay, alongside cross-appeal No. 282 of 2020.

4
Stage 318/10/2023

Delay condonation

No text available.

5
Stage 412/09/2023

Delay condonation

No text available.

6
Stage 524/07/2023

Delay condonation

No text available.

7
Stage 618/07/2023

Delay condonation

The Tribunal directed that the appeal be listed for a hearing on 24.07.2023.

8
Stage 723/05/2023

Delay condonation

The Tribunal ordered the listing of Appeal-224/2021 on 03.08.2023 to be heard alongside a cross-appeal filed by the Greater Noida Industrial Development Authority.

9
Stage 827/04/2023

Hearing

The Tribunal admonished the appellant's counsel for seeking an adjournment after lengthy arguments and scheduled a final hearing for May 23, 2023, warning that no further adjournments will be granted.

10
Stage 920/03/2023

Hearing

No text available.

11
Stage 1027/09/2022

Final Hearing

The Tribunal heard arguments regarding the point of delay in the appeal and subsequently reserved the judgment for further delivery.

12
Stage 1129/08/2022

Final Hearing

No text available.

13
Stage 1201/08/2022

Final Hearing

The Tribunal granted the respondent an additional opportunity to file a reply to the grounds of appeal, subject to a cost of Rs. 500/- to be deposited in the Tribunal's fund.

14
Stage 1323/05/2022

Final Hearing

The Tribunal granted the Respondent a final opportunity to file objections against the application for condonation of delay and the grounds of appeal, adjourning the matter to 01.08.2022.

15
Stage 1413/04/2022

Final Hearing

The Tribunal adjourned the matter to 23.05.2022 due to the absence of the respondent and the defective nature of the appeal.

16
Stage 1522/02/2022

Final Hearing

The Tribunal directed the respondent to file a reply to the appeal and scheduled the matter for hearing on 13.04.2022.

17
Stage 1612/01/2022

Final Hearing

No text available.

18
Stage 1721/12/2021

Delay condonation

The Tribunal granted an adjournment application filed by the respondent's counsel on personal grounds and rescheduled the matter to 12.01.2022 for the disposal of a limitation application.

19
Stage 1825/11/2021

Delay condonation

No text available.

20
Stage 1901/11/2021

Delay condonation

The Tribunal granted an adjournment requested by the respondent due to counsel's medical emergency and directed both parties to file objections and pleadings via email and the e-portal before the next hearing on 25.11.2021.

21
Stage 2018/10/2021

Delay condonation

The Tribunal directed the Registry to verify an uploaded affidavit of service and ordered the applicant's counsel to file a physical copy within two days, scheduling the case for 01.11.2021.

22
Stage 2113/09/2021

Delay condonation

The Tribunal directed the issuance of fresh notice to the respondent due to the applicant's failure to take previous steps and outlined the procedural timeline for service via speed post and email.

23
Stage 2229/04/2021

Delay condonation

No text available.

24
Stage 2306/04/2021

Delay condonation

No text available.

25
Stage 2409/03/2021

Delay condonation

The Tribunal issued notice on the application for condonation of delay and directed the parties to exchange applications, objections, and replies via email before the next hearing on 06.04.2021.

26
Stage 25Final Ruling Order

Tribunal Order #0901126017542021-29-02-2024

The Uttar Pradesh Real Estate Appellate Tribunal rejected the applicant's application for condonation of delay of 414 days, ruling that pursuing compliance and execution of a previous order did not constitute 'sufficient cause' to excuse the delay in filing the appeal.

27
Stage 26Interim Order

Tribunal Order #0901126017542021-27-04-2023

The Tribunal admonished the appellant's counsel for seeking an adjournment after lengthy arguments and scheduled a final hearing for May 23, 2023, warning that no further adjournments will be granted.

28
Stage 27Interim Order

Tribunal Order #0901126017542021-01-08-2022

The Tribunal granted the respondent an additional opportunity to file a reply to the grounds of appeal, subject to a cost of Rs. 500/- to be deposited in the Tribunal's fund.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Uttar Pradesh Real Estate Appellate Tribunal rejected the applicant's application for condonation of delay of 414 days, ruling that pursuing compliance and execution of a previous order did not constitute 'sufficient cause' to excuse the delay in filing the appeal. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.

Disposal Winner: RespondentInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Uttar Pradesh Real Estate Appellate Tribunal rejected the applicant's application for condonation of delay of 414 days, ruling that pursuing compliance and execution of a previous order did not constitute 'sufficient cause' to excuse the delay in filing the appeal.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+1%

Interest Period

from 30.01.2017 till offer of possession

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(4)(f)Section 17

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Nirmit Srivastava

Respondent Advocate(s)

  • Ajay Kumar Gupta
  • Rishindra Vikram Singh

Official RERA Tribunal Orders (3)

FINAL_ORDEROrder ID: 0901126017542021-29-02-2024

The Uttar Pradesh Real Estate Appellate Tribunal rejected the applicant's application for condonation of delay of 414 days, ruling that pursuing compliance and execution of a previous order did not constitute 'sufficient cause' to excuse the delay in filing the appeal.

INTERIM_ORDEROrder ID: 0901126017542021-27-04-2023

The Tribunal admonished the appellant's counsel for seeking an adjournment after lengthy arguments and scheduled a final hearing for May 23, 2023, warning that no further adjournments will be granted.

INTERIM_ORDEROrder ID: 0901126017542021-01-08-2022

The Tribunal granted the respondent an additional opportunity to file a reply to the grounds of appeal, subject to a cost of Rs. 500/- to be deposited in the Tribunal's fund.

TathyaGrid RERA Intelligence AI

Need to research all rulings for a builder?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →