up_reraStatus: Completed
CASE ID: 0901126017392025

Appellant / Complainant

R. R. Civil Tech Pvt Ltd

VS

Respondent

Sumit Bhagat, Dipti Bhagat

Developer Firm

r. r. civil tech pvt ltd

Disputed Amount

2,58,500

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionRefund of InvestmentDelay Compensation / InterestUnfair Cancellation & Forfeiture

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

18 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126017392025 by R. R. Civil Tech Pvt Ltd against Sumit Bhagat, Dipti Bhagat before up_rera.

Delay in PossessionRefund of InvestmentDelay Compensation / InterestUnfair Cancellation & Forfeiture
2
Stage 107/04/2026

Hearing

The Tribunal dismissed the appeal filed by R.R. Civil Tech Pvt Ltd, ruling that under Section 15(2) of the RERA Act, the transferee promoter is liable to fulfill all pending obligations and refund dues of the erstwhile promoter to the allottee.

3
Stage 216/03/2026

Hearing

The Tribunal granted the appellant ten days to file a rejoinder affidavit and scheduled the case for orders on April 7, 2026, while continuing any existing interim orders.

4
Stage 306/02/2026

Delay condonation

The Tribunal allowed the application for condonation of delay, converting the defective appeal into a regular appeal, and adjourned the matter to 16.03.2026 for orders upon completion of pleadings.

5
Stage 416/01/2026

Delay condonation

The Tribunal granted the appellant one week to file a rejoinder affidavit and scheduled the case for orders on February 6, 2026, while continuing any existing interim orders.

6
Stage 511/12/2025

Delay condonation

The Tribunal granted the appellant 10 days to file a rejoinder, directed parties to exchange pleadings, and extended any existing interim orders until the next hearing on 16.01.2026.

7
Stage 619/11/2025

Delay condonation

The Tribunal granted the respondent 10 days to file objections and directed that any rejoinder be filed within one week thereafter, listing the matter for hearing on 11.12.2025.

8
Stage 731/10/2025

Delay condonation

The Tribunal granted the respondent 10 days to file objections and extended any existing interim orders until the next hearing scheduled for 19.11.2025.

9
Stage 826/09/2025

Delay condonation

The Tribunal granted interim relief by restraining Revenue Authorities from taking any coercive action against the appellant regarding the recovery certificate dated 14.08.2025 until the next hearing on 31.10.2025.

10
Stage 924/09/2025

Delay condonation

The Tribunal granted a request by the appellant's counsel to list the defective appeal for consideration of a delay condonation application and a hearing on 26.09.2025.

11
Stage 1026/08/2025

Delay condonation

The Tribunal allowed the appellant's application to amend/substitute the postal address of the respondents and directed the Registry to issue notice upon the amendment.

12
Stage 1120/08/2025

Delay condonation

The Tribunal noted that the notice sent to the respondent returned undelivered; the appellant was advised to file an application for substituted service, and the matter is listed for hearing on 26.08.2025.

13
Stage 1230/07/2025

Delay condonation

The Tribunal directed the issuance of fresh notices to the respondent and outlined the procedural requirements for service of the appeal and application for condonation of delay.

14
Stage 1310/07/2025

Delay condonation

The Tribunal issued notice to the respondent and outlined the procedural steps for service of notice, filing of objections to the condonation of delay application, and subsequent replies, scheduling the matter for hearing on 30.07.2025.

15
Stage 14Final Ruling Order

Tribunal Order #0901126017392025-07-04-2026

The Tribunal dismissed the appeal filed by R.R. Civil Tech Pvt Ltd, ruling that under Section 15(2) of the RERA Act, the transferee promoter is liable to fulfill all pending obligations and refund dues of the erstwhile promoter to the allottee.

16
Stage 15Interim Order

Tribunal Order #0901126017392025-06-02-2026

The Tribunal allowed the application for condonation of delay, converting the defective appeal into a regular appeal, and adjourned the matter to 16.03.2026 for orders upon completion of pleadings.

17
Stage 16Interim Order

Tribunal Order #0901126017392025-26-09-2025

The Tribunal granted interim relief by restraining Revenue Authorities from taking any coercive action against the appellant regarding the recovery certificate dated 14.08.2025 until the next hearing on 31.10.2025.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal dismissed the appeal filed by R.R. Civil Tech Pvt Ltd, ruling that under Section 15(2) of the RERA Act, the transferee promoter is liable to fulfill all pending obligations and refund dues of the erstwhile promoter to the allottee. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.

Disposal Winner: RespondentInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal dismissed the appeal filed by R.R. Civil Tech Pvt Ltd, ruling that under Section 15(2) of the RERA Act, the transferee promoter is liable to fulfill all pending obligations and refund dues of the erstwhile promoter to the allottee.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+1%

Interest Period

from the date of deposit till the date of payment

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(5)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Aahuti Agarwal

Respondent Advocate(s)

  • Shivendra Rao

Official RERA Tribunal Orders (3)

FINAL_ORDEROrder ID: 0901126017392025-07-04-2026

The Tribunal dismissed the appeal filed by R.R. Civil Tech Pvt Ltd, ruling that under Section 15(2) of the RERA Act, the transferee promoter is liable to fulfill all pending obligations and refund dues of the erstwhile promoter to the allottee.

INTERIM_ORDEROrder ID: 0901126017392025-06-02-2026

The Tribunal allowed the application for condonation of delay, converting the defective appeal into a regular appeal, and adjourned the matter to 16.03.2026 for orders upon completion of pleadings.

INTERIM_ORDEROrder ID: 0901126017392025-26-09-2025

The Tribunal granted interim relief by restraining Revenue Authorities from taking any coercive action against the appellant regarding the recovery certificate dated 14.08.2025 until the next hearing on 31.10.2025.