up_reraStatus: Completed
CASE ID: 0901126017262022

Appellant / Complainant

Niteeka Gupta, Neetika Gupta, Divyanshu Gupta

VS

Respondent

Real Estate Regulatory Authority, Tulsiani Constructions and Developers Private Limited

Developer Firm

tulsiani constructions and developers private limited

Disputed Amount

46,12,073

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestNon-Compliance & Execution

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

23 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126017262022 by Niteeka Gupta, Neetika Gupta, Divyanshu Gupta against Real Estate Regulatory Authority, Tulsiani Constructions and Developers Private Limited before up_rera.

Delay in PossessionDelay Compensation / InterestNon-Compliance & Execution
2
Stage 122/05/2024

Delay condonation

The Tribunal set aside the Regulatory Authority's order dated 02.02.2022, which had erroneously disposed of execution proceedings based on a settlement deed belonging to a different case, and remanded the matter back to the Regulatory Authority for fresh execution proceedings.

3
Stage 222/04/2024

Delay condonation

The Tribunal noted that pleadings have been exchanged and scheduled the appeal for orders/hearing on 22.05.2024.

4
Stage 309/04/2024

Delay condonation

Upon the joint request of both counsels, the tribunal has scheduled the defective appeal for consideration regarding the application for condonation of delay on 22.04.2024.

5
Stage 420/03/2024

Delay condonation

The court noted the illness of the appellant's counsel and rescheduled the hearing for the application for condonation of delay to 09.04.2024.

6
Stage 521/02/2024

Delay condonation

The Tribunal noted that the appeal is ready for hearing and scheduled the matter for a subsequent hearing on 20.03.2024.

7
Stage 612/01/2024

Delay condonation

The Tribunal granted a request for adjournment due to the respondent's counsel being out of station and rescheduled the hearing for February 21, 2024.

8
Stage 711/10/2023

Delay condonation

No text available.

9
Stage 825/08/2023

Delay condonation

Upon the joint request of the counsels for both parties, the appeal has been adjourned and listed for hearing on 11.10.2023.

10
Stage 902/08/2023

Delay condonation

The Tribunal granted a 10-day extension to the appellant's counsel to file a reply to the objections due to his unavailability in the High Court.

11
Stage 1022/05/2023

Delay condonation

The Tribunal noted the absence of the respondent's counsel due to sanctioned leave and adjourned the matter to 02.08.2023 for orders or hearing.

12
Stage 1110/04/2023

Delay condonation

The Tribunal granted the appellant's counsel one week to file a reply to the respondent's objections and scheduled the matter for hearing on 22.05.2023.

13
Stage 1227/02/2023

Delay condonation

The Tribunal granted the appellant 10 days to file a reply to the respondent's objections and scheduled the case for hearing on April 10, 2023.

14
Stage 1325/01/2023

Delay condonation

No text available.

15
Stage 1415/12/2022

Delay condonation

The Tribunal noted the respondent's submission regarding an active NCLT moratorium affecting the builder company and adjourned the defective appeal to 25.01.2023.

16
Stage 1518/11/2022

Delay condonation

The Tribunal granted an adjournment application filed by the respondent's counsel and scheduled the matter for 15.12.2022 to address the disposal of a delay condonation application.

17
Stage 1619/10/2022

Delay condonation

The Tribunal granted respondent No. 2 a final opportunity to file a reply to the grounds of appeal and scheduled the matter for further orders on November 18, 2022.

18
Stage 1715/09/2022

Delay condonation

No text available.

19
Stage 1817/08/2022

Further Order

The Tribunal directed Respondent No. 2 (M/s. Tulsayani Construction Pvt. Ltd.) to file its Vakalatnama within 10 days and submit a reply to the grounds of appeal before the next hearing date.

20
Stage 1905/07/2022

Hearing

The Tribunal granted an adjournment requested by the applicant's counsel due to the unavailability of senior counsel and rescheduled the matter for August 17, 2022.

21
Stage 2013/05/2022

Defect Removal

The Tribunal issued notice to the respondent regarding the application for condonation of delay and directed the applicant to remove registry defects and serve notice via speed-post and email.

22
Stage 21Final Ruling Order

Tribunal Order #0901126017262022-22-05-2024

The Tribunal set aside the Regulatory Authority's order dated 02.02.2022, which had erroneously disposed of execution proceedings based on a settlement deed belonging to a different case, and remanded the matter back to the Regulatory Authority for fresh execution proceedings.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal set aside the Regulatory Authority's order dated 02.02.2022, which had erroneously disposed of execution proceedings based on a settlement deed belonging to a different case, and remanded the matter back to the Regulatory Authority for fresh execution proceedings. Awarded in favor of Appellant. Awarded interest rate: 10% per annum up to 30.04.2016 and thereafter at the rate of MCLR+1%.

Disposal Winner: AppellantInterest Rate: 10% per annum up to 30.04.2016 and thereafter at the rate of MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal set aside the Regulatory Authority's order dated 02.02.2022, which had erroneously disposed of execution proceedings based on a settlement deed belonging to a different case, and remanded the matter back to the Regulatory Authority for fresh execution proceedings.

Ruling Awarded To

Appellant

Awarded Interest Rate

10% per annum up to 30.04.2016 and thereafter at the rate of MCLR+1%

Interest Period

up to 30.04.2016 and thereafter for the remaining delay period

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 40Section 63Section 64

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Anurag Singh

Respondent Advocate(s)

  • Saurabh Misra

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126017262022-22-05-2024

The Tribunal set aside the Regulatory Authority's order dated 02.02.2022, which had erroneously disposed of execution proceedings based on a settlement deed belonging to a different case, and remanded the matter back to the Regulatory Authority for fresh execution proceedings.

TathyaGrid RERA Intelligence AI

Need to research all rulings for tulsiani constructions and developers private limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →