up_reraStatus: Completed
CASE ID: 0901126016672025

Appellant / Complainant

Sunil Kumar

VS

Respondent

Mr Proview Realtech Private Limited

Developer Firm

mr proview realtech private limited

Disputed Amount

25,63,720

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestUnfair Cancellation & Forfeiture

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

16 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126016672025 by Sunil Kumar against Mr Proview Realtech Private Limited before up_rera.

Delay in PossessionDelay Compensation / InterestUnfair Cancellation & Forfeiture
2
Stage 108/05/2026

Final Hearing

The Tribunal set aside the Regulatory Authority's order and remanded the complaint to be decided afresh, specifically directing the Authority to adjudicate the legality of the unit's cancellation and maintaining status quo on the unit until disposal.

3
Stage 208/04/2026

Final Hearing

The Tribunal granted an adjournment requested by the respondent's counsel and rescheduled the appeal for hearing on 08.05.2026.

4
Stage 316/03/2026

Admission

The Tribunal has adjourned the matter to 08.04.2026 for final hearing upon the joint request of the counsel, with a direction to the parties to submit dates and events.

5
Stage 411/02/2026

Admission

The Tribunal granted the appellant seven days to file a rejoinder and scheduled the next hearing for March 16, 2026.

6
Stage 519/01/2026

Admission

The Tribunal granted the respondent 10 days to file objections, with the appellant directed to file a reply within one week thereafter, and scheduled the next hearing for 11.02.2026.

7
Stage 608/12/2025

Admission

The Tribunal has adjourned the appeal to 19.01.2026 at the request of the parties and directed them to exchange pleadings in the interim.

8
Stage 720/11/2025

Admission

The Tribunal granted the appellant 10 days to file a reply and scheduled the case for orders on 08.12.2025.

9
Stage 829/10/2025

Admission

The Tribunal granted the respondent 10 days to file objections and scheduled the appeal for hearing on 20.11.2025.

10
Stage 924/09/2025

Admission

The Tribunal granted the respondent 10 days to file objections and directed the appellant to file a rejoinder within one week thereafter, with the next hearing scheduled for 29.10.2025.

11
Stage 1022/08/2025

Admission

The Tribunal granted the respondent ten days to file a Vakalatnama and objections, followed by seven days for the appellant to file a rejoinder, and scheduled the next hearing for 24.09.2025.

12
Stage 1111/08/2025

Admission

The Tribunal granted the appellant seven days to upload the postal department's track record and adjourned the matter to 22.08.2025.

13
Stage 1231/07/2025

Admission

The appeal was adjourned because no one appeared on behalf of the appellant; the matter is listed for orders on 11.08.2025.

14
Stage 1310/07/2025

Admission

The Tribunal issued notice to the respondent and established a procedural timeline for the service of appeal documents and the filing of objections and replies.

15
Stage 14Final Ruling Order

Tribunal Order #0901126016672025-08-05-2026

The Tribunal set aside the Regulatory Authority's order and remanded the complaint to be decided afresh, specifically directing the Authority to adjudicate the legality of the unit's cancellation and maintaining status quo on the unit until disposal.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal set aside the Regulatory Authority's order and remanded the complaint to be decided afresh, specifically directing the Authority to adjudicate the legality of the unit's cancellation and maintaining status quo on the unit until disposal. Awarded in favor of Appellant.

Disposal Winner: AppellantStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal set aside the Regulatory Authority's order and remanded the complaint to be decided afresh, specifically directing the Authority to adjudicate the legality of the unit's cancellation and maintaining status quo on the unit until disposal.

Ruling Awarded To

Appellant

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(5)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Rashi Jain

Respondent Advocate(s)

  • Abhishek Shukla

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126016672025-08-05-2026

The Tribunal set aside the Regulatory Authority's order and remanded the complaint to be decided afresh, specifically directing the Authority to adjudicate the legality of the unit's cancellation and maintaining status quo on the unit until disposal.

TathyaGrid RERA Intelligence AI

Need to research all rulings for mr proview realtech private limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →