up_reraStatus: Completed
CASE ID: 0901126016442020

Appellant / Complainant

Greater Noida Industrial Development Authority

VS

Respondent

Yaduvir Yadav

Disputed Amount

7,45,338

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

19 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126016442020 by Greater Noida Industrial Development Authority against Yaduvir Yadav before up_rera.

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferJurisdiction & Maintainability
2
Stage 108/09/2022

for delivery of Judgment/Order

The Appellate Tribunal dismissed the appeal filed by GNIDA, upholding the RERA order that directed the promoter to deliver possession and pay interest for delay. The Tribunal further directed that the pre-deposited amount be transferred to U.P. RERA for disbursement to the allottee during execution proceedings.

3
Stage 215/07/2022

Hearing

The Tribunal has framed a key legal question to determine whether the interest rate should be governed by the specific terms of the agreement/brochure (4%) or by the statutory provisions of the Real Estate Act, 2016.

4
Stage 325/05/2022

Final Hearing

The Tribunal granted a final 10-day extension to the appellant to file a reply to the respondent's objections, noting that failure to comply will result in the forfeiture of their right to file such a reply.

5
Stage 421/04/2022

Final Hearing

The Tribunal adjourned the matter to 25.05.2022 and directed the respondent, Yaduvir Yadav, to appear in person for the next hearing.

6
Stage 504/03/2022

Final Hearing

The Tribunal granted an adjournment application filed by the Appellant's counsel and rescheduled the hearing for April 21, 2022.

7
Stage 621/01/2022

Final Hearing

No text available.

8
Stage 706/01/2022

Final Hearing

The Tribunal granted the appellant 10 days to file a reply to the respondent's objections and scheduled the next hearing for January 21, 2022.

9
Stage 808/12/2021

Final Hearing

The Tribunal allowed the application for condonation of delay in filing the appeal, citing the Supreme Court's COVID-19 limitation extension orders, and directed the Registry to convert the defective appeal into a regular one.

10
Stage 917/11/2021

Hearing

No text available.

11
Stage 1027/10/2021

Hearing

The Tribunal directed the respondent to provide corrected objection documents within a week and ordered both parties to upload pleadings to the e-portal before the next hearing on 17.11.2021.

12
Stage 1127/09/2021

Delay condonation

The Tribunal directed the appellant's counsel to provide soft copies of the application for condonation of delay and the memo of appeal to the respondent via email to facilitate the filing of objections.

13
Stage 1222/02/2021

For Order

The appeal was dismissed for want of prosecution because no one appeared on behalf of the applicant and no request for adjournment was received.

14
Stage 1320/01/2021

Hearing

The Tribunal issued a fresh notice to the respondent via email due to their absence and directed the applicant to serve the appeal documents and application for condonation of delay to the respondent.

15
Stage 1415/12/2020

Hearing

No text available.

16
Stage 15Final Ruling Order

Tribunal Order #0901126016442020-08-09-2022

The Appellate Tribunal dismissed the appeal filed by GNIDA, upholding the RERA order that directed the promoter to deliver possession and pay interest for delay. The Tribunal further directed that the pre-deposited amount be transferred to U.P. RERA for disbursement to the allottee during execution proceedings.

17
Stage 16Interim Order

Tribunal Order #0901126016442020-08-12-2021

The Tribunal allowed the application for condonation of delay in filing the appeal, citing the Supreme Court's COVID-19 limitation extension orders, and directed the Registry to convert the defective appeal into a regular one.

18
Stage 17Interim Order

Tribunal Order #0901126016442020-15-07-2022

The Tribunal has framed a key legal question to determine whether the interest rate should be governed by the specific terms of the agreement/brochure (4%) or by the statutory provisions of the Real Estate Act, 2016.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Appellate Tribunal dismissed the appeal filed by GNIDA, upholding the RERA order that directed the promoter to deliver possession and pay interest for delay. The Tribunal further directed that the pre-deposited amount be transferred to U.P. RERA for disbursement to the allottee during execution proceedings. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.

Disposal Winner: RespondentInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Appellate Tribunal dismissed the appeal filed by GNIDA, upholding the RERA order that directed the promoter to deliver possession and pay interest for delay. The Tribunal further directed that the pre-deposited amount be transferred to U.P. RERA for disbursement to the allottee during execution proceedings.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+1%

Interest Period

from 16.06.2014 to 30.04.2016 at MCLR+1% and from 01.05.2016 till receipt of OC/CC or offer of possession, whichever is later

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(4)(f)Section 17Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Rajesh Chadha

Official RERA Tribunal Orders (3)

FINAL_ORDEROrder ID: 0901126016442020-08-09-2022

The Appellate Tribunal dismissed the appeal filed by GNIDA, upholding the RERA order that directed the promoter to deliver possession and pay interest for delay. The Tribunal further directed that the pre-deposited amount be transferred to U.P. RERA for disbursement to the allottee during execution proceedings.

INTERIM_ORDEROrder ID: 0901126016442020-08-12-2021

The Tribunal allowed the application for condonation of delay in filing the appeal, citing the Supreme Court's COVID-19 limitation extension orders, and directed the Registry to convert the defective appeal into a regular one.

INTERIM_ORDEROrder ID: 0901126016442020-15-07-2022

The Tribunal has framed a key legal question to determine whether the interest rate should be governed by the specific terms of the agreement/brochure (4%) or by the statutory provisions of the Real Estate Act, 2016.