up_reraStatus: Completed
CASE ID: 0901126016292020

Appellant / Complainant

U.P. Avas Evam Vikas Parishad

VS

Respondent

Dinesh Yadav

Disputed Amount

48,05,500

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

12 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126016292020 by U.P. Avas Evam Vikas Parishad against Dinesh Yadav before up_rera.

Delay in PossessionDelay Compensation / Interest
2
Stage 110/12/2021

Hearing

The Appellate Tribunal dismissed the appeal filed by U.P. Avas Evam Vikas Parishad, upholding the Adjudicating Officer's order for the promoter to pay interest for delayed possession, while modifying the compensation period from 01.08.2015 to 30.10.2018.

3
Stage 210/11/2021

Hearing

No text available.

4
Stage 306/10/2021

Hearing

The Tribunal adjourned the appeal to 10.11.2021 and directed that if the respondent fails to appear on the next date, the matter will be decided based on the existing records.

5
Stage 420/04/2021

Hearing

No text available.

6
Stage 525/03/2021

Hearing

The Tribunal granted a request for adjournment made by the respondent appearing in person and rescheduled the appeal for hearing on 20.04.2021.

7
Stage 603/03/2021

Hearing

The Tribunal adjourned the appeal to 25.03.2021 due to an advocates' strike and directed the Registry to summon the case records.

8
Stage 712/02/2021

Hearing

The Tribunal directed the Registry to convert the matter into a regular appeal and to summon the records of Complaint No. ADJ/12201825420 from the Regulatory Authority, Lucknow.

9
Stage 808/01/2021

Hearing

No text available.

10
Stage 9Final Ruling Order

Tribunal Order #0901126016292020-10-12-2021

The Appellate Tribunal dismissed the appeal filed by U.P. Avas Evam Vikas Parishad, upholding the Adjudicating Officer's order for the promoter to pay interest for delayed possession, while modifying the compensation period from 01.08.2015 to 30.10.2018.

11
Stage 10Interim Order

Tribunal Order #0901126016292020-12-02-2021

The Tribunal directed the Registry to convert the matter into a regular appeal and to summon the records of Complaint No. ADJ/12201825420 from the Regulatory Authority, Lucknow.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Appellate Tribunal dismissed the appeal filed by U.P. Avas Evam Vikas Parishad, upholding the Adjudicating Officer's order for the promoter to pay interest for delayed possession, while modifying the compensation period from 01.08.2015 to 30.10.2018. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.

Disposal Winner: RespondentInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Appellate Tribunal dismissed the appeal filed by U.P. Avas Evam Vikas Parishad, upholding the Adjudicating Officer's order for the promoter to pay interest for delayed possession, while modifying the compensation period from 01.08.2015 to 30.10.2018.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+1%

Interest Period

from 01.08.2015 to 30.10.2018

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • N N Pandey

Respondent Advocate(s)

  • Dinesh Kumar Yadav

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126016292020-10-12-2021

The Appellate Tribunal dismissed the appeal filed by U.P. Avas Evam Vikas Parishad, upholding the Adjudicating Officer's order for the promoter to pay interest for delayed possession, while modifying the compensation period from 01.08.2015 to 30.10.2018.

INTERIM_ORDEROrder ID: 0901126016292020-12-02-2021

The Tribunal directed the Registry to convert the matter into a regular appeal and to summon the records of Complaint No. ADJ/12201825420 from the Regulatory Authority, Lucknow.