CASE ID: 0901126016262022

Appellant / Complainant

A.K. Agrawal

VS

Respondent

Ajpa Parishad Sehkari Awas Samiti Ltd, Ekdant Buildtech Pvt. Ltd., U.P. Real Estate Regulatory Authority Lucknow

Developer Firm

ekdant buildtech pvt. ltd.

Disputed Amount

11,80,174

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionRefund of InvestmentDelay Compensation / InterestUnfair Cancellation & ForfeitureJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

28 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126016262022 by A.K. Agrawal against Ajpa Parishad Sehkari Awas Samiti Ltd, Ekdant Buildtech Pvt. Ltd., U.P. Real Estate Regulatory Authority Lucknow before up_rera.

Delay in PossessionRefund of InvestmentDelay Compensation / InterestUnfair Cancellation & ForfeitureJurisdiction & Maintainability
2
Stage 123/01/2025

For Order

The Tribunal set aside the RERA Authority's order and directed Respondent No.1 (AJPA Parishad Sehkari Awas Samiti Ltd.) to refund the remaining balance of Rs. 4,80,174 to the appellant, along with interest at MCLR+1% on both the remaining amount and the amounts previously refunded.

3
Stage 217/01/2025

For Order

Upon a joint request from the counsel for both parties, the hearing/orders for this case have been adjourned to 23.01.2025.

4
Stage 310/09/2024

Further Hearing

The U.P. Real Estate Appellate Tribunal heard arguments in Appeal-186/2022 between Dr. A.K. Agrawal and AJPA Parishad Sehkari Awas Samiti Ltd and has reserved its judgment.

5
Stage 427/08/2024

Hearing

The Tribunal adjourned the matter to 10.09.2024 for further arguments, noting that the appeal has proceeded ex parte against respondent No. 2.

6
Stage 524/07/2024

Hearing

The Tribunal noted sufficient service of notice on respondent no.2 via publication and scheduled the case for an ex parte hearing on 27.08.2024.

7
Stage 624/05/2024

Hearing

The Tribunal granted an adjournment requested by the respondent's counsel and scheduled the appeal for hearing on 24.07.2024.

8
Stage 724/04/2024

Hearing

The Tribunal noted that pleadings have been exchanged and scheduled the defective appeal for orders or hearing on 24.05.2024.

9
Stage 819/03/2024

Hearing

The Tribunal has scheduled the appeal for a hearing or orders on 24.04.2024 due to the respondent's counsel being out of station.

10
Stage 921/02/2024

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel and rescheduled the hearing for 19.03.2024.

11
Stage 1012/01/2024

For Order

The Tribunal noted the absence of both counsels due to illness and travel and adjourned the matter for hearing on 21.02.2024.

12
Stage 1111/10/2023

For Order

No text available.

13
Stage 1225/08/2023

For Order

The Tribunal granted an adjournment requested by the respondent's counsel on health grounds and rescheduled the hearing for 11.10.2023.

14
Stage 1321/07/2023

For Order

The Tribunal granted an adjournment requested by the appellant's counsel due to his unavailability and rescheduled the hearing for 25.08.2023.

15
Stage 1410/05/2023

For Order

No text available.

16
Stage 1529/03/2023

For Order

The Tribunal directed the Registry to identify any existing defects in the appeal; if no defects are found, the matter is to be converted into a Regular Appeal and listed for hearing on 10.05.2023.

17
Stage 1620/02/2023

Further Order

The Tribunal granted the appellant 10 days to file a reply to the respondent's objection and scheduled the case for hearing on March 29, 2023.

18
Stage 1718/01/2023

Further Order

No text available.

19
Stage 1813/12/2022

Further Order

No text available.

20
Stage 1916/11/2022

Further Order

The Tribunal granted an adjournment application filed by the appellant's counsel and rescheduled the defective appeal for further orders on 13.12.2022.

21
Stage 2018/10/2022

Notice

The Tribunal noted the publication of notice in a newspaper for respondent no. 2 and directed the appellant to file a reply to the objections submitted by respondent no. 1.

22
Stage 2114/09/2022

Notice

The Tribunal noted that notice had not been served on respondent No. 2 and directed the appellant to file proof of newspaper publication within three days, adjourning the matter to 18.10.2022.

23
Stage 2216/08/2022

Notice

The Tribunal directed the appellant to file a replication/rejoinder against the respondent's reply and ordered publication of notice in daily newspapers for respondent No. 2, M/s. Ekdant Developers Pvt. Ltd., due to improper service.

24
Stage 2320/07/2022

Defect Removal

The Tribunal granted the respondent one week to file objections to the appeal and permitted the applicant to serve respondent No. 2 via 'Dasti' summons, scheduling the next hearing for August 16, 2022.

25
Stage 2410/05/2022

Defect Removal

The Tribunal adjourned the case to 20.07.2022 because no one appeared for the appellant due to a lawyer strike/abstention by the Oudh Bar Association.

26
Stage 2511/04/2022

Defect Removal

The Tribunal granted the applicant one week to rectify registry defects and directed the issuance of notice to respondent no. 2, with the next hearing scheduled for 10.05.2022.

27
Stage 26Final Ruling Order

Tribunal Order #0901126016262022-23-01-2025

The Tribunal set aside the RERA Authority's order and directed Respondent No.1 (AJPA Parishad Sehkari Awas Samiti Ltd.) to refund the remaining balance of Rs. 4,80,174 to the appellant, along with interest at MCLR+1% on both the remaining amount and the amounts previously refunded.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal set aside the RERA Authority's order and directed Respondent No.1 (AJPA Parishad Sehkari Awas Samiti Ltd.) to refund the remaining balance of Rs. 4,80,174 to the appellant, along with interest at MCLR+1% on both the remaining amount and the amounts previously refunded. Awarded in favor of Appellant. Awarded interest rate: MCLR + 1%.

Disposal Winner: AppellantInterest Rate: MCLR + 1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal set aside the RERA Authority's order and directed Respondent No.1 (AJPA Parishad Sehkari Awas Samiti Ltd.) to refund the remaining balance of Rs. 4,80,174 to the appellant, along with interest at MCLR+1% on both the remaining amount and the amounts previously refunded.

Ruling Awarded To

Appellant

Awarded Interest Rate

MCLR + 1%

Interest Period

till the date of actual payment

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(5)Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Krishna Kumar Singh
  • Gautam Johri

Respondent Advocate(s)

  • Amit Yadav

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126016262022-23-01-2025

The Tribunal set aside the RERA Authority's order and directed Respondent No.1 (AJPA Parishad Sehkari Awas Samiti Ltd.) to refund the remaining balance of Rs. 4,80,174 to the appellant, along with interest at MCLR+1% on both the remaining amount and the amounts previously refunded.

TathyaGrid RERA Intelligence AI

Need to research all rulings for ekdant buildtech pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →