Appellant / Complainant
Ghaziabad Development Authority
Respondent
Abhinav Kumar Verma
₹50,72,173
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126016242020 by Ghaziabad Development Authority against Abhinav Kumar Verma before up_rera.
For Order
The Tribunal corrected a clerical error in the previous order dated 14.12.2022, replacing the incorrectly transcribed 'Lucknow Development Authority' with 'Ghaziabad Development Authority'.
for delivery of Judgment/Order
The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay and dismissed the appeal due to lack of sufficient cause, while directing that the statutory pre-deposit be transferred to the Regulatory Authority for disposal.
Further Order
The Tribunal reserved its judgment on the application for condonation of delay filed by the Ghaziabad Development Authority, allowing both parties to submit legal rulings on the point of limitation.
Delay condonation
The Tribunal adjourned the matter to 17.11.2021 after both parties expressed their intent to file relevant case law regarding the points of argument.
Delay condonation
The Tribunal granted the respondent three days to file a reply to the applicant's improved affidavit for condonation of delay and scheduled the matter for hearing on 22.10.2021.
For Order
The Tribunal granted a final 10-day opportunity to the applicant to file a better affidavit for condonation of delay, failing which the right to do so will be closed.
For Order
The case is adjourned to 10.03.2021 because lawyers are abstaining from work due to a call by the Oudh Bar Association.
For Order
The Tribunal granted the applicant three days to file a reply to the respondent's objections and scheduled the matter for 24.02.2021 to consider the application for condonation of delay.
Delay condonation
The Tribunal granted an adjournment request and directed the applicant's counsel to email, upload, and file original copies of their reply to the respondent's objections before the next hearing on 05.02.2021.
Tribunal Order #0901126016242020-08-12-2021
The Tribunal reserved its judgment on the application for condonation of delay filed by the Ghaziabad Development Authority, allowing both parties to submit legal rulings on the point of limitation.
Tribunal Order #0901126016242020-14-12-2022
The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay and dismissed the appeal due to lack of sufficient cause, while directing that the statutory pre-deposit be transferred to the Regulatory Authority for disposal.
Tribunal Disposal & Final Award Ruling
The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay and dismissed the appeal due to lack of sufficient cause, while directing that the statutory pre-deposit be transferred to the Regulatory Authority for disposal. Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay and dismissed the appeal due to lack of sufficient cause, while directing that the statutory pre-deposit be transferred to the Regulatory Authority for disposal.
Ruling Awarded To
Respondent
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Ram Raj
- Rishabh Raj
Respondent Advocate(s)
- Savita Jain
Official RERA Tribunal Orders (2)
The Tribunal reserved its judgment on the application for condonation of delay filed by the Ghaziabad Development Authority, allowing both parties to submit legal rulings on the point of limitation.
The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay and dismissed the appeal due to lack of sufficient cause, while directing that the statutory pre-deposit be transferred to the Regulatory Authority for disposal.
Need to research all rulings for a builder?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.