up_reraStatus: Completed
CASE ID: 0901126016232023

Appellant / Complainant

Prem Narain Vijay, Archana Vijay

VS

Respondent

Royalgolf Link City Projects Private Limited

Developer Firm

royalgolf link city projects private limited

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

23 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126016232023 by Prem Narain Vijay, Archana Vijay against Royalgolf Link City Projects Private Limited before up_rera.

2
Stage 121/05/2025

Hearing

The appeal was dismissed as withdrawn following a settlement reached between the parties through court-sponsored mediation.

3
Stage 230/04/2025

Hearing

The court granted the respondent time to file a settlement deed following an out-of-court amicable settlement between the parties and scheduled the matter for orders on 21.05.2025.

4
Stage 302/04/2025

Hearing

The Tribunal granted the respondent 10 days to file objections and share a soft copy, with the appellant permitted one week thereafter to file a reply. The matter is scheduled for hearing on 30.04.2025.

5
Stage 410/03/2025

Hearing

The Tribunal has adjourned the appeal to 02.04.2025 at the request of the respondent and directed the parties to exchange pleadings in the interim.

6
Stage 513/02/2025

Hearing

The Tribunal granted a request to list the appeal for orders/hearing on 10.03.2025 and directed that pleadings be completed in the interim.

7
Stage 621/01/2025

Hearing

The Tribunal granted the respondent 10 days to file objections and directed that a rejoinder be filed within one week thereafter, scheduling the next hearing for 13.02.2025.

8
Stage 716/12/2024

Hearing

The Tribunal granted the respondent 10 days to file objections and directed the appellant to file a reply within one week thereafter, scheduling the next hearing for 21.01.2025.

9
Stage 828/11/2024

For Order

No text available.

10
Stage 923/10/2024

For Order

The Tribunal granted the respondent seven days to file objections and scheduled the appeal for a hearing on November 28, 2024.

11
Stage 1016/09/2024

For Order

No text available.

12
Stage 1113/08/2024

For Order

The Tribunal granted the respondent an additional seven days to file objections against the appeal and directed the exchange of soft copies between parties, scheduling the next hearing for 16.09.2024.

13
Stage 1215/07/2024

For Order

No text available.

14
Stage 1315/05/2024

For Order

No text available.

15
Stage 1415/04/2024

For Order

The Tribunal noted the absence of the appellant's counsel and scheduled the appeal for a hearing on 15.05.2024.

16
Stage 1511/03/2024

For Order

No text available.

17
Stage 1601/02/2024

For Order

The Tribunal granted the respondent's counsel 10 days to file a vakalatnama and objections, with a subsequent one-week deadline for the appellant to file a reply, and scheduled the next hearing for 11.03.2024.

18
Stage 1704/01/2024

For Order

The Tribunal granted a 10-day extension for filing objections to the grounds of appeal and directed the parties to upload documents to the E-portal following the exchange of replies.

19
Stage 1827/09/2023

For Order

No text available.

20
Stage 1914/08/2023

For Order

No text available.

21
Stage 2031/05/2023

Admission

The Tribunal issued notice to the respondent and outlined the procedural requirements for service of notice and the exchange of objections and replies.

22
Stage 21Final Ruling Order

Tribunal Order #0901126016232023-21-05-2025

The appeal was dismissed as withdrawn following a settlement reached between the parties through court-sponsored mediation.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The appeal was dismissed as withdrawn following a settlement reached between the parties through court-sponsored mediation. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The appeal was dismissed as withdrawn following a settlement reached between the parties through court-sponsored mediation.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Ritesh Srivastava

Respondent Advocate(s)

  • Abhishek Khare
  • Jayant Gupta

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126016232023-21-05-2025

The appeal was dismissed as withdrawn following a settlement reached between the parties through court-sponsored mediation.

TathyaGrid RERA Intelligence AI

Need to research all rulings for royalgolf link city projects private limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →