Appellant / Complainant
Ashoka Sharma
Respondent
Tyagi Construction Company & Others
tyagi construction company
Respondent
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126016102020 by Ashoka Sharma against Tyagi Construction Company & Others before up_rera.
to file objections and its reply
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Ashoka Sharma against M/s Tyagi Construction Company & Others via an order dated 12.04.2022.
to file objections and its reply
The Tribunal granted the appellant a one-week extension to file a reply to the respondent's objections and rescheduled the appeal hearing for 12.04.2022.
Further Order
The Tribunal granted the appellant 10 days to file a reply to the respondent's objections and scheduled the appeal for hearing on 22.03.2022.
Further Order
The Tribunal noted the impossibility of settlement between the parties and granted the appellant permission to file a replication/rejoinder, adjourning the matter to 21.01.2022.
Further Order
The Tribunal granted an adjournment request but directed the applicant to appear in person and ordered the respondent partner, Mr. Vijay Kumar Tyagi, to appear at the next hearing to facilitate an amicable settlement.
Hearing
The Tribunal directed the parties to attempt an out-of-court settlement regarding disputed payments and scheduled the matter for further orders on 28.10.2021.
Hearing
The Tribunal has scheduled the matter for further orders on 29.09.2021 after receiving allegations that the signatures on a submitted compromise application were forged.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel due to her being out of station and rescheduled the hearing for 08.04.2021.
Further Hearing
The matter was adjourned to 12.03.2021 following a dispute between counsel regarding whether the parties had reached a settlement.
Tribunal Order #0901126016102020-12-04-2022
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Ashoka Sharma against M/s Tyagi Construction Company & Others via an order dated 12.04.2022.
Tribunal Order #0901126016102020-28-10-2021
The Tribunal granted an adjournment request but directed the applicant to appear in person and ordered the respondent partner, Mr. Vijay Kumar Tyagi, to appear at the next hearing to facilitate an amicable settlement.
Tribunal Disposal & Final Award Ruling
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Ashoka Sharma against M/s Tyagi Construction Company & Others via an order dated 12.04.2022. Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Ashoka Sharma against M/s Tyagi Construction Company & Others via an order dated 12.04.2022.
Ruling Awarded To
Respondent
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Prashant Kumar
- Fuhar Gupta
Respondent Advocate(s)
- Sanjay Kumar Srivastava
Official RERA Tribunal Orders (2)
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Ashoka Sharma against M/s Tyagi Construction Company & Others via an order dated 12.04.2022.
The Tribunal granted an adjournment request but directed the applicant to appear in person and ordered the respondent partner, Mr. Vijay Kumar Tyagi, to appear at the next hearing to facilitate an amicable settlement.