up_reraStatus: Completed
CASE ID: 0901126016092020

Appellant / Complainant

U.P. Avas Evam Vikas Parishad

VS

Respondent

S.N.S. Diljan

Disputed Amount

66,24,533

Disposal Award

Partial

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

19 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126016092020 by U.P. Avas Evam Vikas Parishad against S.N.S. Diljan before up_rera.

Delay in PossessionDelay Compensation / Interest
2
Stage 124/02/2022

Final Hearing

The Tribunal allowed the limitation application subject to costs and partially allowed the appeal by modifying the impugned order to direct the appellant to pay interest at MCLR+1% on Rs. 50,50,000 for the delay period from 28.03.2017 to 14.09.2018.

3
Stage 213/01/2022

Final Hearing

No text available.

4
Stage 307/01/2022

Final Hearing

The Tribunal granted a request from the appellant's counsel to reschedule the hearing, ordering the case to be listed on 13.01.2022.

5
Stage 405/01/2022

Final Hearing

The court noted that the parties have reached an amicable settlement and the respondent has issued a refund letter; the case is adjourned to 07.01.2022 for instructions regarding the withdrawal of the appeal.

6
Stage 524/12/2021

Hearing

The Tribunal noted a procedural error regarding the incorrect listing date of the case and rescheduled the matter for final hearing on 05.01.2022.

7
Stage 626/11/2021

Further Order

The Tribunal adjourned the matter to 23.12.2021 for further orders due to the absence of the respondent.

8
Stage 717/11/2021

Delay condonation

The Tribunal granted an adjournment requested by the appellant's counsel and directed the appellant to file a replication or rejoinder before the next hearing date.

9
Stage 818/10/2021

Delay condonation

The Tribunal granted the appellant one week to file a better affidavit regarding the application for condonation of delay and permitted the parties to negotiate a settlement in the interim.

10
Stage 929/04/2021

Delay condonation

No text available.

11
Stage 1006/04/2021

Delay condonation

No text available.

12
Stage 1112/03/2021

Delay condonation

No text available.

13
Stage 1224/02/2021

Hearing

The case is adjourned due to lawyers abstaining from work on account of a call by the Oudh Bar Association and is rescheduled for March 12, 2021.

14
Stage 1309/02/2021

For Order

The Tribunal granted the appellant one week to file a reply to the respondent's objections and scheduled the matter for February 24, 2021, to consider the application for condonation of delay.

15
Stage 1420/01/2021

Delay condonation

The Tribunal granted the applicant two weeks to file a reply to the respondent's objections and directed that the reply be emailed to the respondent and uploaded to the e-portal before the next hearing on 09.02.2021.

16
Stage 1504/01/2021

For Order

No text available.

17
Stage 1607/10/2020

For Order

No text available.

18
Stage 17Final Ruling Order

Tribunal Order #0901126016092020-24-02-2022

The Tribunal allowed the limitation application subject to costs and partially allowed the appeal by modifying the impugned order to direct the appellant to pay interest at MCLR+1% on Rs. 50,50,000 for the delay period from 28.03.2017 to 14.09.2018.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal allowed the limitation application subject to costs and partially allowed the appeal by modifying the impugned order to direct the appellant to pay interest at MCLR+1% on Rs. 50,50,000 for the delay period from 28.03.2017 to 14.09.2018. Awarded in favor of Partial. Awarded interest rate: MCLR+1%.

Disposal Winner: PartialInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal allowed the limitation application subject to costs and partially allowed the appeal by modifying the impugned order to direct the appellant to pay interest at MCLR+1% on Rs. 50,50,000 for the delay period from 28.03.2017 to 14.09.2018.

Ruling Awarded To

Partial

Awarded Interest Rate

MCLR+1%

Interest Period

from 28.03.2017 to 14.09.2018

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • N N Pandey

Respondent Advocate(s)

  • Amit Chandra

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126016092020-24-02-2022

The Tribunal allowed the limitation application subject to costs and partially allowed the appeal by modifying the impugned order to direct the appellant to pay interest at MCLR+1% on Rs. 50,50,000 for the delay period from 28.03.2017 to 14.09.2018.

TathyaGrid RERA Intelligence AI

Need to research all rulings for a builder?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →