up_reraStatus: Completed
CASE ID: 0901126016082020

Appellant / Complainant

Alto Projects & Engineering Pvt. Ltd.

VS

Respondent

Tyagi Construction Company & Others

Developer Firm

alto projects & engineering pvt. ltd.

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

18 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126016082020 by Alto Projects & Engineering Pvt. Ltd. against Tyagi Construction Company & Others before up_rera.

2
Stage 112/04/2022

to file objections and its reply

The U.P. Real Estate Appellate Tribunal dismissed Appeal-551/2020 by reference to a previously passed order in Appeal No. 526/2020.

3
Stage 222/03/2022

to file objections and its reply

The Tribunal granted the appellant a one-week extension to file a reply to the respondent's objections and scheduled the next hearing for April 12, 2022.

4
Stage 304/03/2022

Further Order

The Tribunal granted the appellant 10 days to file a reply to the respondent's objections and scheduled the appeal for hearing on March 22, 2022.

5
Stage 421/01/2022

Exchange of pleadings

No text available.

6
Stage 509/12/2021

Further Order

No text available.

7
Stage 611/11/2021

Further Order

No text available.

8
Stage 728/10/2021

Further Order

The Tribunal granted an adjournment requested by the respondent and directed both the applicant and the respondent's partner to appear in person on the next date to attempt an amicable settlement.

9
Stage 804/10/2021

Hearing

The Tribunal directed the parties to attempt an out-of-court settlement regarding disputed payments and scheduled the matter for further orders on 28.10.2021.

10
Stage 909/09/2021

Hearing

The Tribunal noted an allegation of forgery regarding a submitted compromise application and adjourned the matter to 29.09.2021 for further orders.

11
Stage 1005/05/2021

Hearing

No text available.

12
Stage 1108/04/2021

Hearing

No text available.

13
Stage 1212/03/2021

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel due to her being out of station and rescheduled the matter for April 8, 2021.

14
Stage 1311/02/2021

Further Hearing

The Tribunal noted the respondent's claim of a settlement between the parties, while the appellant requested an adjournment to verify this information; the matter is adjourned to 12.03.2021.

15
Stage 1406/01/2021

Further Order

No text available.

16
Stage 1526/11/2020

Further Order

No text available.

17
Stage 16Final Ruling Order

Tribunal Order #0901126016082020-12-04-2022

The U.P. Real Estate Appellate Tribunal dismissed Appeal-551/2020 by reference to a previously passed order in Appeal No. 526/2020.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The U.P. Real Estate Appellate Tribunal dismissed Appeal-551/2020 by reference to a previously passed order in Appeal No. 526/2020. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The U.P. Real Estate Appellate Tribunal dismissed Appeal-551/2020 by reference to a previously passed order in Appeal No. 526/2020.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Prashant Kumar
  • Fuhar Gupta

Respondent Advocate(s)

  • Sanjay Kumar Srivastava

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126016082020-12-04-2022

The U.P. Real Estate Appellate Tribunal dismissed Appeal-551/2020 by reference to a previously passed order in Appeal No. 526/2020.

TathyaGrid RERA Intelligence AI

Need to research all rulings for alto projects & engineering pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →