up_reraStatus: Completed
CASE ID: 0901126016052024

Appellant / Complainant

Uppal Chadha Hi-Tech Developers Pvt. Ltd.

VS

Respondent

K K Tewari

Developer Firm

uppal chadha hi-tech developers pvt. ltd.

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestSale Deed & Title Transfer

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

5 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126016052024 by Uppal Chadha Hi-Tech Developers Pvt. Ltd. against K K Tewari before up_rera.

Delay in PossessionDelay Compensation / InterestSale Deed & Title Transfer
2
Stage 124/05/2024

Delay condonation

The Tribunal rejected the applications for condonation of delay in nine appeals due to lack of sufficient cause and consequently dismissed the appeals; it further directed that the pre-deposited amounts under Section 43(5) be transferred to U.P. RERA for distribution to allottees during execution proceedings.

3
Stage 223/05/2024

Delay condonation

The Tribunal granted an adjournment requested by the appellant's counsel on health grounds and scheduled the matter for hearing/orders on 24.05.2024.

4
Stage 3Final Ruling Order

Tribunal Order #0901126016052024-24-05-2024

The Tribunal rejected the applications for condonation of delay in nine appeals due to lack of sufficient cause and consequently dismissed the appeals; it further directed that the pre-deposited amounts under Section 43(5) be transferred to U.P. RERA for distribution to allottees during execution proceedings.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal rejected the applications for condonation of delay in nine appeals due to lack of sufficient cause and consequently dismissed the appeals; it further directed that the pre-deposited amounts under Section 43(5) be transferred to U.P. RERA for distribution to allottees during execution proceedings. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.

Disposal Winner: RespondentInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal rejected the applications for condonation of delay in nine appeals due to lack of sufficient cause and consequently dismissed the appeals; it further directed that the pre-deposited amounts under Section 43(5) be transferred to U.P. RERA for distribution to allottees during execution proceedings.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+1%

Interest Period

from 08.12.2016 to date of getting OC/CC or to the date when possession of plot was offered whichever is later

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(4)(f)Section 17

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Naveen Kumar Tiwari

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126016052024-24-05-2024

The Tribunal rejected the applications for condonation of delay in nine appeals due to lack of sufficient cause and consequently dismissed the appeals; it further directed that the pre-deposited amounts under Section 43(5) be transferred to U.P. RERA for distribution to allottees during execution proceedings.

TathyaGrid RERA Intelligence AI

Need to research all rulings for uppal chadha hi-tech developers pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →