up_reraStatus: Completed
CASE ID: 0901126016002020

Appellant / Complainant

Rama Mittal

VS

Respondent

Uppal Chaddha High-Tech Developers Pvt. Ltd.

Developer Firm

uppal chaddha high-tech developers pvt. ltd.

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

50 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126016002020 by Rama Mittal against Uppal Chaddha High-Tech Developers Pvt. Ltd. before up_rera.

2
Stage 107/11/2024

Hearing

The appeal was dismissed as withdrawn following an amicable settlement reached between the appellant and the respondent.

3
Stage 217/10/2024

For Order

The court granted a request by the appellant's counsel to list the case for orders on 07.11.2024.

4
Stage 311/09/2024

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel due to the senior counsel being out of station and scheduled the case for orders on 17.10.2024.

5
Stage 429/08/2024

Hearing

The Tribunal granted a request from both counsels for a short adjournment to prepare briefs and listed the case for orders/hearing on 11.09.2024.

6
Stage 513/08/2024

Hearing

The Tribunal directed the office to report on whether the respondent has deposited the previously imposed cost of Rs. 10,000/- and scheduled the matter for hearing on 29.08.2024.

7
Stage 615/07/2024

Hearing

No text available.

8
Stage 715/05/2024

Hearing

No text available.

9
Stage 816/04/2024

Hearing

The Tribunal noted the absence of the appellant's counsel and adjourned the matter to 15.05.2024 for orders/hearing.

10
Stage 914/03/2024

Hearing

The appeal was adjourned to 16.04.2024 because the counsel for the appellant reported being ill.

11
Stage 1023/02/2024

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel to seek instructions and rescheduled the hearing for 14.03.2024.

12
Stage 1116/01/2024

Hearing

The Tribunal directed the Registrar to send a reminder to the Secretary of RERA regarding outstanding information on actions taken following previous orders in the complaint of Rama Mittal vs. Uppal Chaddha High-Tech Developers Pvt. Ltd.

13
Stage 1212/10/2023

Hearing

No text available.

14
Stage 1304/09/2023

Hearing

The Tribunal adjourned the proceedings due to a Bar Council of Uttar Pradesh resolution regarding lawyers abstaining from judicial work and rescheduled the hearing for 12.10.2023.

15
Stage 1416/08/2023

Final Hearing

The Tribunal directed the Registrar to seek information from the Secretary of RERA regarding actions taken against the Respondent for failing to register their project as previously ordered.

16
Stage 1502/08/2023

Final Hearing

The Tribunal granted an adjournment requested by the respondent's counsel due to illness and absence, scheduling the appeal for hearing on 16.08.2023.

17
Stage 1622/05/2023

Final Hearing

The Tribunal noted the absence of the respondent's counsel and adjourned the matter to 02.08.2023 for orders or hearing.

18
Stage 1725/04/2023

Final Hearing

The court adjourned the proceedings due to the appellant's counsel being on sanctioned leave and rescheduled the hearing for 22.05.2023.

19
Stage 1816/03/2023

Final Hearing

The Tribunal granted an adjournment requested by the respondent's counsel due to unavailability and illness, rescheduling the appeal hearing for 25.04.2023.

20
Stage 1907/02/2023

Final Hearing

The Tribunal granted a request from both parties for an adjournment and scheduled the appeal for hearing on 16.03.2023.

21
Stage 2004/01/2023

Final Hearing

The Tribunal granted an adjournment due to the respondent's counsel's illness and directed the appellant to upload missing documents to the portal and file physical copies with the Registry.

22
Stage 2102/12/2022

Final Hearing

The Tribunal granted an adjournment request from the appellant's counsel and scheduled the appeal for a hearing on January 4, 2023.

23
Stage 2207/11/2022

Final Hearing

The Tribunal granted an adjournment requested by the appellant's counsel due to personal difficulties and scheduled the appeal for hearing on December 2, 2022.

24
Stage 2327/09/2022

Part Heard

The Tribunal granted a request for adjournment from both parties and adjourned the proceedings scheduled for September 27, 2022.

25
Stage 2401/09/2022

Further Hearing

The Tribunal has ordered the appeal to be listed for hearing on September 27, 2022.

26
Stage 2503/08/2022

Further Hearing

The Tribunal directed the respondent to issue a fresh offer of possession to the appellant to resolve disputes regarding the adequacy of previous offers. The matter is scheduled for further orders on 01.09.2022.

27
Stage 2630/05/2022

Further Hearing

The Tribunal directed the respondent to comply with a previous order regarding plot possession and ordered the payment of costs previously imposed on 03.11.2020. Additionally, the Respondent is required to appear through an authorized representative empowered to make final decisions at the next hearing.

28
Stage 2722/04/2022

Hearing

The Tribunal directed the respondent counsel to seek instructions from the builder company regarding the handover of plot possession and ordered both parties to file a list of dates, events, and relied-upon cases before the next hearing on 30.05.2022.

29
Stage 2804/03/2022

Hearing

The Tribunal directed the parties to submit a list of dates, events, and relied-upon judgments in the Registry and scheduled the appeal for hearing on 22.04.2022.

30
Stage 2904/01/2022

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel due to a personal emergency and rescheduled the hearing for 21.01.2022.

31
Stage 3010/12/2021

Hearing

The Tribunal granted an adjournment application moved by the respondent's counsel and rescheduled the appeal for hearing on 04.01.2022.

32
Stage 3110/11/2021

Hearing

No text available.

33
Stage 3206/10/2021

Hearing

The Tribunal permitted the appellant's counsel to limit arguments to specific issues regarding interest cut-off dates and PLC charges, and subsequently adjourned the matter for hearing on 10.11.2021.

34
Stage 3313/09/2021

Hearing

The Tribunal granted a final adjournment to the respondent due to counsel's personal difficulty but issued a warning that if no one appears at the next hearing on 06.10.2021, the matter will proceed ex parte.

35
Stage 3429/04/2021

Hearing

No text available.

36
Stage 3506/04/2021

Hearing

No text available.

37
Stage 3616/03/2021

For Order

The Tribunal granted an adjournment request made by the respondent's counsel and rescheduled the appeal for hearing on 06.04.2021.

38
Stage 3723/02/2021

For Order

The Tribunal granted an adjournment requested by the respondent's counsel due to illness and rescheduled the hearing for 16.03.2021.

39
Stage 3808/02/2021

For Order

The appeal is adjourned following a request for adjournment by the respondent's counsel due to illness, with the matter rescheduled for 23.02.2021.

40
Stage 3918/01/2021

Hearing on Appeal

No text available.

41
Stage 4024/07/2020

Hearing on Appeal

No text available.

42
Stage 4106/07/2020

Hearing on Appeal

No text available.

43
Stage 42Interim Order

Tribunal Order #0901126016002020-13-08-2024

The Tribunal directed the office to report on whether the respondent has deposited the previously imposed cost of Rs. 10,000/- and scheduled the matter for hearing on 29.08.2024.

44
Stage 43Interim Order

Tribunal Order #0901126016002020-16-01-2024

The Tribunal directed the Registrar to send a reminder to the Secretary of RERA regarding outstanding information on actions taken following previous orders in the complaint of Rama Mittal vs. Uppal Chaddha High-Tech Developers Pvt. Ltd.

45
Stage 44Interim Order

Tribunal Order #0901126016002020-30-05-2022

The Tribunal directed the respondent to comply with a previous order regarding plot possession and ordered the payment of costs previously imposed on 03.11.2020. Additionally, the Respondent is required to appear through an authorized representative empowered to make final decisions at the next hearing.

46
Stage 45Interim Order

Tribunal Order #0901126016002020-22-04-2022

The Tribunal directed the respondent counsel to seek instructions from the builder company regarding the handover of plot possession and ordered both parties to file a list of dates, events, and relied-upon cases before the next hearing on 30.05.2022.

47
Stage 46Interim Order

Tribunal Order #0901126016002020-13-09-2021

The Tribunal granted a final adjournment to the respondent due to counsel's personal difficulty but issued a warning that if no one appears at the next hearing on 06.10.2021, the matter will proceed ex parte.

48
Stage 47Interim Order

Tribunal Order #0901126016002020-16-08-2023

The Tribunal directed the Registrar to seek information from the Secretary of RERA regarding actions taken against the Respondent for failing to register their project as previously ordered.

49
Stage 48Interim Order

Tribunal Order #0901126016002020-03-08-2022

The Tribunal directed the respondent to issue a fresh offer of possession to the appellant to resolve disputes regarding the adequacy of previous offers. The matter is scheduled for further orders on 01.09.2022.

Disposal Phase

Tribunal Disposal & Final Award Ruling

Dismissed as withdrawn Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

Dismissed as withdrawn

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Harish Pandey

Respondent Advocate(s)

  • Bal Kishor Verma
  • Amit Yadav

Official RERA Tribunal Orders (7)

INTERIM_ORDEROrder ID: 0901126016002020-13-08-2024

The Tribunal directed the office to report on whether the respondent has deposited the previously imposed cost of Rs. 10,000/- and scheduled the matter for hearing on 29.08.2024.

INTERIM_ORDEROrder ID: 0901126016002020-16-01-2024

The Tribunal directed the Registrar to send a reminder to the Secretary of RERA regarding outstanding information on actions taken following previous orders in the complaint of Rama Mittal vs. Uppal Chaddha High-Tech Developers Pvt. Ltd.

INTERIM_ORDEROrder ID: 0901126016002020-30-05-2022

The Tribunal directed the respondent to comply with a previous order regarding plot possession and ordered the payment of costs previously imposed on 03.11.2020. Additionally, the Respondent is required to appear through an authorized representative empowered to make final decisions at the next hearing.

INTERIM_ORDEROrder ID: 0901126016002020-22-04-2022

The Tribunal directed the respondent counsel to seek instructions from the builder company regarding the handover of plot possession and ordered both parties to file a list of dates, events, and relied-upon cases before the next hearing on 30.05.2022.

INTERIM_ORDEROrder ID: 0901126016002020-13-09-2021

The Tribunal granted a final adjournment to the respondent due to counsel's personal difficulty but issued a warning that if no one appears at the next hearing on 06.10.2021, the matter will proceed ex parte.

INTERIM_ORDEROrder ID: 0901126016002020-16-08-2023

The Tribunal directed the Registrar to seek information from the Secretary of RERA regarding actions taken against the Respondent for failing to register their project as previously ordered.

INTERIM_ORDEROrder ID: 0901126016002020-03-08-2022

The Tribunal directed the respondent to issue a fresh offer of possession to the appellant to resolve disputes regarding the adequacy of previous offers. The matter is scheduled for further orders on 01.09.2022.

TathyaGrid RERA Intelligence AI

Need to research all rulings for uppal chaddha high-tech developers pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →