up_reraStatus: Completed
CASE ID: 0901126015932020

Appellant / Complainant

Paarth Infrabuild Pvt. Ltd.

VS

Respondent

Sanjeev Kumar, Ors

Developer Firm

paarth infrabuild pvt. ltd.

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Jurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

22 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126015932020 by Paarth Infrabuild Pvt. Ltd. against Sanjeev Kumar, Ors before up_rera.

Jurisdiction & Maintainability
2
Stage 108/03/2022

Hearing

The Tribunal allowed the appellant to withdraw the appeal on the grounds of maintainability and directed that any amount deposited under Section 43(5) be handled by the Regulatory Authority for distribution to the allottee or return to the promoter after due diligence.

3
Stage 204/01/2022

Final Hearing

The Tribunal directed the appellant to deposit a deficiency of Rs. 3,84,000/- to comply with Section 43(5) of the Act and issued notices to respondent nos. 2 and 3 for the next hearing on 25.01.2022.

4
Stage 320/12/2021

Hearing

The Tribunal adjourned the appeal to 04.01.2022 and directed the appellant's counsel to ensure complete compliance with the provisions of Section 43(5) of the Act in the interim.

5
Stage 430/11/2021

Hearing

The Tribunal adjourned the case to 20.12.2021 and issued a final opportunity to the appellant to comply with the provisions of Section 43(5) of the Act.

6
Stage 511/11/2021

Hearing

The Tribunal has scheduled the appeal for a hearing on 30.11.2021, referencing a previous order passed in a related matter.

7
Stage 608/10/2021

Hearing

The Tribunal issued a warning to the appellant's counsel against seeking adjournments via email and subsequently adjourned the appeal to 11.11.2021 following a request by a substitute advocate.

8
Stage 722/04/2021

Hearing

No text available.

9
Stage 805/04/2021

For Order

No text available.

10
Stage 915/03/2021

Compliance of section 43(5)

The Tribunal issued notices to respondent nos. 2 and 3 and directed the appellant to serve them via dasti summons and email, establishing a timeline for filing objections and replies.

11
Stage 1019/02/2021

For Order

The Tribunal granted the respondent two weeks to file objections regarding the condonation of delay and grounds of appeal, while also directing the Registry to comply with a previous order to convert the defective appeal into a regular appeal.

12
Stage 1101/02/2021

For Order

The Tribunal granted a request for adjournment due to the counsel being out of station and rescheduled the case for 19.02.2021.

13
Stage 1211/01/2021

Hearing on Recall App

No text available.

14
Stage 1320/11/2020

Hearing on Recall App

No text available.

15
Stage 1423/10/2020

Hearing on Recall App

No text available.

16
Stage 15Final Ruling Order

Tribunal Order #0901126015932020-08-03-2022

The Tribunal allowed the appellant to withdraw the appeal on the grounds of maintainability and directed that any amount deposited under Section 43(5) be handled by the Regulatory Authority for distribution to the allottee or return to the promoter after due diligence.

17
Stage 16Interim Order

Tribunal Order #0901126015932020-20-12-2021

The Tribunal adjourned the appeal to 04.01.2022 and directed the appellant's counsel to ensure complete compliance with the provisions of Section 43(5) of the Act in the interim.

18
Stage 17Interim Order

Tribunal Order #0901126015932020-08-10-2021

The Tribunal issued a warning to the appellant's counsel against seeking adjournments via email and subsequently adjourned the appeal to 11.11.2021 following a request by a substitute advocate.

19
Stage 18Interim Order

Tribunal Order #0901126015932020-04-01-2022

The Tribunal directed the appellant to deposit a deficiency of Rs. 3,84,000/- to comply with Section 43(5) of the Act and issued notices to respondent nos. 2 and 3 for the next hearing on 25.01.2022.

20
Stage 19Interim Order

Tribunal Order #0901126015932020-30-11-2021

The Tribunal adjourned the case to 20.12.2021 and issued a final opportunity to the appellant to comply with the provisions of Section 43(5) of the Act.

21
Stage 20Interim Order

Tribunal Order #0901126015932020-19-02-2021

The Tribunal granted the respondent two weeks to file objections regarding the condonation of delay and grounds of appeal, while also directing the Registry to comply with a previous order to convert the defective appeal into a regular appeal.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal allowed the appellant to withdraw the appeal on the grounds of maintainability and directed that any amount deposited under Section 43(5) be handled by the Regulatory Authority for distribution to the allottee or return to the promoter after due diligence. Awarded in favor of Appellant.

Disposal Winner: AppellantStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal allowed the appellant to withdraw the appeal on the grounds of maintainability and directed that any amount deposited under Section 43(5) be handled by the Regulatory Authority for distribution to the allottee or return to the promoter after due diligence.

Ruling Awarded To

Appellant

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Rajiv Shukla
  • Rahul Shukla

Respondent Advocate(s)

  • Anurag Arora

Official RERA Tribunal Orders (6)

FINAL_ORDEROrder ID: 0901126015932020-08-03-2022

The Tribunal allowed the appellant to withdraw the appeal on the grounds of maintainability and directed that any amount deposited under Section 43(5) be handled by the Regulatory Authority for distribution to the allottee or return to the promoter after due diligence.

INTERIM_ORDEROrder ID: 0901126015932020-20-12-2021

The Tribunal adjourned the appeal to 04.01.2022 and directed the appellant's counsel to ensure complete compliance with the provisions of Section 43(5) of the Act in the interim.

INTERIM_ORDEROrder ID: 0901126015932020-08-10-2021

The Tribunal issued a warning to the appellant's counsel against seeking adjournments via email and subsequently adjourned the appeal to 11.11.2021 following a request by a substitute advocate.

INTERIM_ORDEROrder ID: 0901126015932020-04-01-2022

The Tribunal directed the appellant to deposit a deficiency of Rs. 3,84,000/- to comply with Section 43(5) of the Act and issued notices to respondent nos. 2 and 3 for the next hearing on 25.01.2022.

INTERIM_ORDEROrder ID: 0901126015932020-30-11-2021

The Tribunal adjourned the case to 20.12.2021 and issued a final opportunity to the appellant to comply with the provisions of Section 43(5) of the Act.

INTERIM_ORDEROrder ID: 0901126015932020-19-02-2021

The Tribunal granted the respondent two weeks to file objections regarding the condonation of delay and grounds of appeal, while also directing the Registry to comply with a previous order to convert the defective appeal into a regular appeal.

TathyaGrid RERA Intelligence AI