up_reraStatus: Completed
CASE ID: 0901126015902024

Appellant / Complainant

Excella Infrazone LLP

VS

Respondent

Uttar Pradesh Real Estate Regulatory Authority, Bullman Reality India Limited

Developer Firm

bullman reality india limited

Disputed Amount

3,00,000

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Promotional Misrepresentation

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

14 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126015902024 by Excella Infrazone LLP against Uttar Pradesh Real Estate Regulatory Authority, Bullman Reality India Limited before up_rera.

Promotional Misrepresentation
2
Stage 121/11/2024

Hearing

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Excella Infrazone LLP, upholding a Rs. 3,00,000 penalty imposed for a violation of Section 11(2) of the RERA Act regarding improper project advertisements.

3
Stage 218/10/2024

Hearing

The Tribunal granted an adjournment requested by the respondent's counsel despite opposition from the appellant, rescheduling the matter for 21.11.2024 with a warning that no further adjournments will be permitted.

4
Stage 309/09/2024

Hearing

The Tribunal directed the intervener to serve a soft copy of application MA No. 705 of 2024 on the appellant and set a timeline for filing replies, subsequently listing the case for hearing on 18.10.2024.

5
Stage 430/07/2024

Hearing

The Tribunal granted a seven-day extension to the counsel for the allottee to upload a vakalatnama and intervention application due to technical glitches, and rescheduled the hearing to September 9, 2024.

6
Stage 529/07/2024

Hearing

The Tribunal granted the appellant's request to list the appeal for an ex parte hearing against the respondent on 30.07.2024.

7
Stage 623/07/2024

Hearing

The Tribunal granted an adjournment requested by the respondent's counsel and directed them to file their vakalatnama within three days, scheduling the next hearing for 29.07.2024.

8
Stage 723/05/2024

Notice

The Tribunal decided to proceed ex parte against the respondent due to their non-appearance and directed the Registry to convert the defective appeal into a regular appeal as it was filed within the limitation period.

9
Stage 823/04/2024

Notice

The Tribunal disposed of an application regarding a clerical error in the notice, confirmed that the appeal was filed within the limitation period, and granted the respondents 10 days to file objections.

10
Stage 908/04/2024

Defect Removal

The Tribunal issued notice to the respondent regarding the appellant's application for condonation of delay and directed specific procedures for service of notice and filing of objections. The matter is listed for 23.04.2024 to consider the delay condonation and the appeal.

11
Stage 10Final Ruling Order

Tribunal Order #0901126015902024-21-11-2024

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Excella Infrazone LLP, upholding a Rs. 3,00,000 penalty imposed for a violation of Section 11(2) of the RERA Act regarding improper project advertisements.

12
Stage 11Interim Order

Tribunal Order #0901126015902024-23-05-2024

The Tribunal decided to proceed ex parte against the respondent due to their non-appearance and directed the Registry to convert the defective appeal into a regular appeal as it was filed within the limitation period.

13
Stage 12Interim Order

Tribunal Order #0901126015902024-08-04-2024

The Tribunal issued notice to the respondent regarding the appellant's application for condonation of delay and directed specific procedures for service of notice and filing of objections. The matter is listed for 23.04.2024 to consider the delay condonation and the appeal.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Excella Infrazone LLP, upholding a Rs. 3,00,000 penalty imposed for a violation of Section 11(2) of the RERA Act regarding improper project advertisements. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Excella Infrazone LLP, upholding a Rs. 3,00,000 penalty imposed for a violation of Section 11(2) of the RERA Act regarding improper project advertisements.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 12

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Deepak Agarwal
  • Unnati Vijay
  • Rajat Bhatia

Respondent Advocate(s)

  • Saghar Mehdi

Official RERA Tribunal Orders (3)

FINAL_ORDEROrder ID: 0901126015902024-21-11-2024

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Excella Infrazone LLP, upholding a Rs. 3,00,000 penalty imposed for a violation of Section 11(2) of the RERA Act regarding improper project advertisements.

INTERIM_ORDEROrder ID: 0901126015902024-23-05-2024

The Tribunal decided to proceed ex parte against the respondent due to their non-appearance and directed the Registry to convert the defective appeal into a regular appeal as it was filed within the limitation period.

INTERIM_ORDEROrder ID: 0901126015902024-08-04-2024

The Tribunal issued notice to the respondent regarding the appellant's application for condonation of delay and directed specific procedures for service of notice and filing of objections. The matter is listed for 23.04.2024 to consider the delay condonation and the appeal.

TathyaGrid RERA Intelligence AI

Need to research all rulings for bullman reality india limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →