up_reraStatus: Completed
CASE ID: 0901126015892022

Appellant / Complainant

Uppal Chadha Hi-Tech Developers Pvt. Ltd.

VS

Respondent

Sunil Kumar Agarwal

Developer Firm

uppal chadha hi-tech developers pvt. ltd.

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

8 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126015892022 by Uppal Chadha Hi-Tech Developers Pvt. Ltd. against Sunil Kumar Agarwal before up_rera.

2
Stage 123/04/2025

Delay condonation

The Tribunal rejected the appellant's application for condonation of a 933-day delay due to lack of sufficient cause and dismissed the appeal, while directing that the amount deposited by the promoter be released to the respondent-allottee or remitted to U.P. RERA for disbursement.

3
Stage 225/03/2025

Delay condonation

The Tribunal granted an adjournment requested by the appellant's counsel and scheduled the case for orders on 23.04.2025.

4
Stage 328/02/2025

Delay condonation

The Tribunal granted the respondent 10 days to file objections, with the appellant permitted to file a reply within one week thereafter, and scheduled the next hearing for 25.03.2025.

5
Stage 404/02/2025

Delay condonation

The Tribunal has granted a request by the appellant's counsel to list the case for orders on 28.02.2025.

6
Stage 502/01/2025

Delay condonation

The Tribunal issued notice to the respondent and provided procedural instructions for the service of the appeal and the application for condonation of delay, scheduling the next hearing for 04.02.2025.

7
Stage 6Final Ruling Order

Tribunal Order #0901126015892022-23-04-2025

The Tribunal rejected the appellant's application for condonation of a 933-day delay due to lack of sufficient cause and dismissed the appeal, while directing that the amount deposited by the promoter be released to the respondent-allottee or remitted to U.P. RERA for disbursement.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal rejected the appellant's application for condonation of a 933-day delay due to lack of sufficient cause and dismissed the appeal, while directing that the amount deposited by the promoter be released to the respondent-allottee or remitted to U.P. RERA for disbursement. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal rejected the appellant's application for condonation of a 933-day delay due to lack of sufficient cause and dismissed the appeal, while directing that the amount deposited by the promoter be released to the respondent-allottee or remitted to U.P. RERA for disbursement.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Surangama Sharma
  • Naveen Kumar Tiwari

Respondent Advocate(s)

  • Mandeep Singh

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126015892022-23-04-2025

The Tribunal rejected the appellant's application for condonation of a 933-day delay due to lack of sufficient cause and dismissed the appeal, while directing that the amount deposited by the promoter be released to the respondent-allottee or remitted to U.P. RERA for disbursement.

TathyaGrid RERA Intelligence AI

Need to research all rulings for uppal chadha hi-tech developers pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →