up_reraStatus: Completed
CASE ID: 0901126015822020

Appellant / Complainant

Gobind Lal Khanna, Kapil Sethi

VS

Respondent

Wave Megacity Centre Pvt. Limited

Developer Firm

wave megacity centre pvt. limited

Disputed Amount

2,90,62,800

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionRefund of InvestmentDelay Compensation / InterestSale Deed & Title TransferStructural Defects & QualityPromotional MisrepresentationNon-Compliance & ExecutionJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

37 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126015822020 by Gobind Lal Khanna, Kapil Sethi against Wave Megacity Centre Pvt. Limited before up_rera.

Delay in PossessionRefund of InvestmentDelay Compensation / InterestSale Deed & Title TransferStructural Defects & QualityPromotional MisrepresentationNon-Compliance & ExecutionJurisdiction & Maintainability
2
Stage 104/09/2024

for delivery of Judgment/Order

The Tribunal set aside the Regulatory Authority's order dated 18.03.2020, ruling it illegal and perverse for failing to address the project's non-registration status, and remanded the matter back to the Authority for a fresh decision.

3
Stage 204/07/2024

Hearing

The Tribunal heard arguments from both parties, who noted that the issues are covered by a previous judgment; consequently, the judgment has been reserved.

4
Stage 306/05/2024

Hearing

The appeal was adjourned to 04.07.2024 because the respondent was not present and the appellant's counsel requested leave to attend a High Court proceeding.

5
Stage 416/04/2024

Hearing

The Tribunal granted the respondent a one-week extension to file objections to the amended appeal and directed that soft copies be shared with the appellant. The matter is scheduled for further orders/hearing on 06.05.2024.

6
Stage 514/03/2024

Hearing

The Tribunal allowed the appellant's application to amend the grounds of appeal and add further prayers, directing the filing of an amended memo of appeal within one week.

7
Stage 620/02/2024

Hearing

The Tribunal granted the respondent one week to file objections regarding a proposed amendment and scheduled the hearing for March 14, 2024.

8
Stage 701/02/2024

Hearing

The Tribunal granted the appellant one week to amend the grounds of their appeal and directed the respondent to file objections within a subsequent week, scheduling the next hearing for February 20, 2024.

9
Stage 817/01/2024

Hearing

The Tribunal granted a request for an urgent short date due to the age of the case and scheduled the appeal for hearing on 01.02.2024.

10
Stage 913/10/2023

Hearing

No text available.

11
Stage 1005/09/2023

Hearing

The Tribunal adjourned the proceedings due to a call by the Bar Council of Uttar Pradesh for lawyers to abstain from judicial work and rescheduled the hearing for 13.10.2023.

12
Stage 1124/08/2023

Hearing

The Tribunal has rescheduled the hearing of Appeal-298/2020 to 05.09.2023 based on a joint request from the counsels for both parties.

13
Stage 1207/08/2023

Hearing

No text available.

14
Stage 1325/05/2023

Hearing

No text available.

15
Stage 1413/04/2023

Hearing

The tribunal granted a request for adjournment from the respondent's counsel and rescheduled the appeal hearing to 25.05.2023.

16
Stage 1502/03/2023

Hearing

The Tribunal noted that pleadings have been exchanged and adjourned the matter for a hearing scheduled on 13.04.2023.

17
Stage 1621/02/2023

Hearing

This is a procedural entry for Appeal-298/2020 before the U.P. Real Estate Appellate Tribunal, noting the presence of counsel for the appellant and the absence of counsel for the respondent.

18
Stage 1713/02/2023

For Order

The Tribunal granted permission for the appellant to file a Vakalatnama within 24 hours and scheduled the appeal for hearing on 21.02.2023.

19
Stage 1811/01/2023

For Order

No text available.

20
Stage 1908/12/2022

For Order

This text is the header of a legal document from the U.P. Real Estate Appellate Tribunal involving an appeal by Gobind Lal Khanna and Kapil Sethi against M/S Wave Megacity Centre Pvt. Limited; no substantive ruling or directive is present in this excerpt.

21
Stage 2014/11/2022

For Order

No text available.

22
Stage 2114/10/2022

For Order

No text available.

23
Stage 2213/09/2022

Further Order

The Tribunal noted that pleadings have been exchanged and directed the parties to submit a list of dates, events, and relied-upon judgments before the next hearing on 14.10.2022.

24
Stage 2317/08/2022

Further Order

The Tribunal granted the appellant additional time to file an objection against a maintainability application and scheduled the next hearing for 13.09.2022.

25
Stage 2404/08/2022

Further Order

The Tribunal noted that the respondent's case was dismissed by the NCLT, Delhi, and directed the appellant to file an objection regarding the appeal's maintainability due to the project's non-registration with RERA.

26
Stage 2527/05/2022

Further Order

The Tribunal adjourned the matter to 04.08.2022 because the respondent-builder's case is currently pending before the NCLT with judgment reserved.

27
Stage 2622/03/2022

For Order

The Tribunal granted an adjournment at the request of both counsels due to pending proceedings before the NCLT and listed the case for hearing on 27.05.2022.

28
Stage 2703/03/2022

Further Order

The Tribunal granted an adjournment requested by the appellant's counsel due to the unavailability of the NCLT order and rescheduled the hearing for 22.03.2022.

29
Stage 2824/12/2021

Further Order

The parties conceded that the matter is currently pending before the NCLT; consequently, the Tribunal adjourned the case to 20.01.2022 for further orders.

30
Stage 2924/11/2021

Further Order

The Tribunal adjourned the matter to 24.12.2021 and directed the parties to submit the NCLT order once obtained.

31
Stage 3001/11/2021

Further Order

The Tribunal granted an adjournment requested by the respondent's counsel due to illness and scheduled the appeal for a hearing on 24.11.2021.

32
Stage 3129/09/2021

Hearing

The Tribunal penalized the respondent with a cost of Rs. 10,000 for defying previous orders and filing a preliminary objection instead of detailed objections, while permitting them to file the detailed objections today.

33
Stage 3209/09/2021

Notice

No text available.

34
Stage 33Interim Order

Tribunal Order #0901126015822020-29-09-2021

The Tribunal penalized the respondent with a cost of Rs. 10,000 for defying previous orders and filing a preliminary objection instead of detailed objections, while permitting them to file the detailed objections today.

35
Stage 34Final Ruling Order

Tribunal Order #0901126015822020-04-09-2024

The Tribunal set aside the Regulatory Authority's order dated 18.03.2020, ruling it illegal and perverse for failing to address the project's non-registration status, and remanded the matter back to the Authority for a fresh decision.

36
Stage 35Interim Order

Tribunal Order #0901126015822020-04-08-2022

The Tribunal noted that the respondent's case was dismissed by the NCLT, Delhi, and directed the appellant to file an objection regarding the appeal's maintainability due to the project's non-registration with RERA.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal set aside the Regulatory Authority's order dated 18.03.2020, ruling it illegal and perverse for failing to address the project's non-registration status, and remanded the matter back to the Authority for a fresh decision. Awarded in favor of Appellant. Awarded interest rate: MCLR+1%.

Disposal Winner: AppellantInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal set aside the Regulatory Authority's order dated 18.03.2020, ruling it illegal and perverse for failing to address the project's non-registration status, and remanded the matter back to the Authority for a fresh decision.

Ruling Awarded To

Appellant

Awarded Interest Rate

MCLR+1%

Interest Period

from 22.06.2017 till receipt of OC/CC or offer of possession, whichever is later

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(4)(f)Section 17Section 14(3)Section 12Section 40Section 63Section 64Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Abhishek Khare
  • Aahuti Agarwal

Respondent Advocate(s)

  • Amit Yadav
  • Bal Kishor Verma

Official RERA Tribunal Orders (3)

INTERIM_ORDEROrder ID: 0901126015822020-29-09-2021

The Tribunal penalized the respondent with a cost of Rs. 10,000 for defying previous orders and filing a preliminary objection instead of detailed objections, while permitting them to file the detailed objections today.

FINAL_ORDEROrder ID: 0901126015822020-04-09-2024

The Tribunal set aside the Regulatory Authority's order dated 18.03.2020, ruling it illegal and perverse for failing to address the project's non-registration status, and remanded the matter back to the Authority for a fresh decision.

INTERIM_ORDEROrder ID: 0901126015822020-04-08-2022

The Tribunal noted that the respondent's case was dismissed by the NCLT, Delhi, and directed the appellant to file an objection regarding the appeal's maintainability due to the project's non-registration with RERA.

TathyaGrid RERA Intelligence AI

Need to research all rulings for wave megacity centre pvt. limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →