Appellant / Complainant
Uppal Chadha Hi-Tech Developers Pvt. Ltd.
Respondent
Anubhav Singh
uppal chadha hi-tech developers pvt. ltd.
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126015812022 by Uppal Chadha Hi-Tech Developers Pvt. Ltd. against Anubhav Singh before up_rera.
Delay condonation
The Tribunal rejected the applications for condonation of delay due to lack of sufficient cause and dismissed all six appeals; consequently, it directed the transfer of the appellants' pre-deposited amounts to the U.P. RERA for distribution to the allottees.
Delay condonation
The Tribunal has scheduled the hearing for May 29, 2024, following a joint request from counsel to consider an application for condonation of delay in this defective appeal.
For Order
The Tribunal scheduled the defective appeal for consideration regarding the application for condonation of delay on May 14, 2024.
For Order
The Tribunal noted that pleadings have been exchanged and adjourned the matter to 12.04.2024 for consideration of the application for condonation of delay.
For Order
The Tribunal granted the appellant's counsel one week to file a reply to the respondent's objections and scheduled the next hearing for March 7, 2024.
For Order
The Tribunal granted the appellant's counsel one week to file a reply to the respondent's objections and scheduled the matter for hearing on October 31, 2023.
For Order
The Tribunal has scheduled the matter for orders or hearing on 17.05.2023 due to the absence of the respondent's counsel.
Defect Removal
The Tribunal granted the appellant one week to comply with the provisions of Section 43(5) of the Act 2016 and scheduled the matter for orders on 26.04.2023.
Tribunal Order #0901126015812022-29-05-2024
The Tribunal rejected the applications for condonation of delay due to lack of sufficient cause and dismissed all six appeals; consequently, it directed the transfer of the appellants' pre-deposited amounts to the U.P. RERA for distribution to the allottees.
Tribunal Disposal & Final Award Ruling
The Tribunal rejected the applications for condonation of delay due to lack of sufficient cause and dismissed all six appeals; consequently, it directed the transfer of the appellants' pre-deposited amounts to the U.P. RERA for distribution to the allottees. Awarded in favor of Respondent. Awarded interest rate: 10/- per sq.ft. per month and MCLR+1%.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal rejected the applications for condonation of delay due to lack of sufficient cause and dismissed all six appeals; consequently, it directed the transfer of the appellants' pre-deposited amounts to the U.P. RERA for distribution to the allottees.
Ruling Awarded To
Respondent
Awarded Interest Rate
10/- per sq.ft. per month and MCLR+1%
Interest Period
from 01.02.2015 to 30.04.2016 and from 01.05.2016 till date of receipt of OC/CC or to the date when possession of plot was offered whichever is later
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Bal Kishor Verma
- Amit Yadav
Respondent Advocate(s)
- Harish Pandey
Official RERA Tribunal Orders (1)
The Tribunal rejected the applications for condonation of delay due to lack of sufficient cause and dismissed all six appeals; consequently, it directed the transfer of the appellants' pre-deposited amounts to the U.P. RERA for distribution to the allottees.
Need to research all rulings for uppal chadha hi-tech developers pvt. ltd.?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.