Appellant / Complainant
Uppal Chadha Hi-Tech Developers Pvt. Ltd.
Respondent
Kusum
uppal chadha hi-tech developers pvt. ltd.
₹20,10,428
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126015802022 by Uppal Chadha Hi-Tech Developers Pvt. Ltd. against Kusum before up_rera.
for delivery of Judgment/Order
The Tribunal dismissed the appellant's appeal, ruling that farmer agitation does not constitute 'force majeure' to exempt a promoter from paying delay interest to an allottee under Section 18 of the RERA Act.
Delay condonation
The Tribunal condoned the delay in filing the appeal based on Supreme Court COVID-19 limitation guidelines and directed the Registry to convert the defective appeal into a regular appeal, subsequently reserving judgment.
Delay condonation
The Tribunal granted an adjournment requested by the appellant's counsel due to illness and rescheduled the hearing for 16.09.2024.
Delay condonation
The Tribunal granted the appellant's counsel one week to seek instructions from their client and scheduled the defective appeal for orders/hearing on 20.08.2024.
Delay condonation
The Tribunal noted the unavailability of counsel for both parties and adjourned the matter to 20.05.2024 to consider the application for condonation of delay.
Delay condonation
The Tribunal granted the appellant a one-week extension to file a reply to the respondent's objection and scheduled the matter for hearing on April 19, 2024.
Delay condonation
The Tribunal granted an adjournment to the respondent on health grounds and allowed one week for the applicant to file a reply to objections, scheduling the matter for March 14, 2024.
Delay condonation
The Tribunal noted that the appellant has complied with Section 43(5) of the Act by depositing the required amount and directed that notice be issued to the respondent regarding the application for condonation of delay.
Delay condonation
The Tribunal granted the appellant one week to comply with Section 43(5) of the Act 2016, warning that failure to achieve complete compliance by the next hearing on 25.09.2023 will result in the dismissal of the defective appeal.
Delay condonation
The Tribunal granted the appellant three days to ensure complete compliance with Section 43(5) of the Act and scheduled the next hearing for May 17, 2023.
Delay condonation
The Tribunal granted the appellant a one-week extension to rectify a deficiency of Rs. 1,00,000 regarding compliance with Section 43(5) of the Act, 2016.
Tribunal Order #0901126015802022-02-12-2024
The Tribunal dismissed the appellant's appeal, ruling that farmer agitation does not constitute 'force majeure' to exempt a promoter from paying delay interest to an allottee under Section 18 of the RERA Act.
Tribunal Order #0901126015802022-25-09-2023
The Tribunal noted that the appellant has complied with Section 43(5) of the Act by depositing the required amount and directed that notice be issued to the respondent regarding the application for condonation of delay.
Tribunal Order #0901126015802022-23-10-2024
The Tribunal condoned the delay in filing the appeal based on Supreme Court COVID-19 limitation guidelines and directed the Registry to convert the defective appeal into a regular appeal, subsequently reserving judgment.
Tribunal Order #0901126015802022-18-09-2023
The Tribunal granted the appellant one week to comply with Section 43(5) of the Act 2016, warning that failure to achieve complete compliance by the next hearing on 25.09.2023 will result in the dismissal of the defective appeal.
Tribunal Disposal & Final Award Ruling
The Tribunal dismissed the appellant's appeal, ruling that farmer agitation does not constitute 'force majeure' to exempt a promoter from paying delay interest to an allottee under Section 18 of the RERA Act. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal dismissed the appellant's appeal, ruling that farmer agitation does not constitute 'force majeure' to exempt a promoter from paying delay interest to an allottee under Section 18 of the RERA Act.
Ruling Awarded To
Respondent
Awarded Interest Rate
MCLR+1%
Interest Period
from 28.08.2015 till the date of obtaining Occupancy/Completion certificate (OC/CC) or till the date of offer of possession whichever is later
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Bal Kishor Verma
- Amit Yadav
Respondent Advocate(s)
- Prasoon Kumar Anjor
Official RERA Tribunal Orders (4)
The Tribunal dismissed the appellant's appeal, ruling that farmer agitation does not constitute 'force majeure' to exempt a promoter from paying delay interest to an allottee under Section 18 of the RERA Act.
The Tribunal noted that the appellant has complied with Section 43(5) of the Act by depositing the required amount and directed that notice be issued to the respondent regarding the application for condonation of delay.
The Tribunal condoned the delay in filing the appeal based on Supreme Court COVID-19 limitation guidelines and directed the Registry to convert the defective appeal into a regular appeal, subsequently reserving judgment.
The Tribunal granted the appellant one week to comply with Section 43(5) of the Act 2016, warning that failure to achieve complete compliance by the next hearing on 25.09.2023 will result in the dismissal of the defective appeal.
Need to research all rulings for uppal chadha hi-tech developers pvt. ltd.?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.