Appellant / Complainant
Greater Noida Industrial Development Authority
Respondent
Pratima Gupta
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126015772020 by Greater Noida Industrial Development Authority against Pratima Gupta before up_rera.
for delivery of Judgment/Order
The Appellate Tribunal dismissed the appeal filed by Greater Noida Industrial Development Authority, upholding the Regulatory Authority's order to pay interest for delayed possession and directing that the promoter's pre-deposited amount be transferred to U.P. RERA for disbursement to the allottee.
Hearing
The Tribunal examined an appeal regarding the grant of interest for delay in possession, noting that while an offer was made in June 2019, the Occupancy Certificate/Completion Certificate was only received later; the judgment is reserved.
For Order
The Tribunal decided to proceed ex-parte against the respondent due to their failure to appear despite sufficient service of notice and was scheduled the case for further orders on 18.07.2023.
For Order
The tribunal granted an adjournment requested by the appellant's counsel due to illness and rescheduled the matter for orders on 23.05.2023.
For Order
The Tribunal ruled that service of notice to the respondent is sufficient via post and email, granted the respondent 10 days to file objections, and scheduled the next hearing for 17.04.2023.
For Order
The Tribunal granted an adjournment of the proceedings due to the illness of the counsels for both the appellant and the respondent, rescheduling the hearing for 02.03.2023.
For Order
The Tribunal issued a fresh notice to the respondent and provided specific procedural directions for service of notice and filing of pleadings before the next hearing on 30.01.2023.
For Order
The Tribunal granted an adjournment due to the counsel for the appellant meeting with an accident and provided 10 days to upload the required affidavit of service.
For Order
The Tribunal directed the appellant to correct a filing error regarding document placement and ordered the issuance of fresh notice to the respondent for the next hearing on 25.11.2022.
For Order
The Tribunal granted the respondent a final opportunity to file an objection against the appellant's delay condonation application and scheduled the matter for hearing on 19.10.2022.
Delay condonation
The Tribunal allowed the application for condonation of delay in filing the appeal, citing the COVID-19 period relaxations granted by the Supreme Court, and directed the Registry to register the case as a regular appeal.
Hearing
The Tribunal directed the respondent's counsel to file a reply to the delay condonation application and serve a copy to the applicant before the next hearing on 25.08.2022.
Hearing
The Tribunal issued a notice to the respondent and directed the appellant to serve the memo of appeal via speed post and email, with the matter returnable on 08.07.2022.
Hearing
The Tribunal directed the registry to remove Sri Nirmit Srivastava's name from the record and ordered that notice be issued to the respondent, with the case scheduled for April 29, 2022, to address a limitation application.
Delay condonation
The Tribunal granted the respondent 10 days to file objections regarding the application for condonation of delay and the grounds of appeal, with a subsequent deadline for the applicant's reply.
Delay condonation
The Tribunal granted an adjournment requested by the applicant and rescheduled the case to 12.01.2022 to consider the application for condonation of delay and its objections.
Delay condonation
The Tribunal adjourned the case to 21.12.2021 for the disposal of a limitation application and directed both parties to appear, noting that failure to do so will result in the application being decided according to the Act.
Delay condonation
The Tribunal allowed an application for adjournment and rescheduled the case to 24.11.2021 for the disposal of a limitation application and objections.
Delay condonation
The Tribunal adjourned the case to 26.10.2021 and directed the parties to exchange pleadings and file originals in the Registry at least one week before the next hearing.
For Order
The Tribunal adjourned the defective appeal due to an advocates' strike and directed the parties to exchange pleadings before the next hearing on 16.03.2021.
Compliance of section 43(5)
The Tribunal issued notice to the respondent regarding the application for condonation of delay and granted two weeks for filing objections, with a subsequent reply due within one week.
Tribunal Order #0901126015772020-21-07-2023
The Appellate Tribunal dismissed the appeal filed by Greater Noida Industrial Development Authority, upholding the Regulatory Authority's order to pay interest for delayed possession and directing that the promoter's pre-deposited amount be transferred to U.P. RERA for disbursement to the allottee.
Tribunal Order #0901126015772020-18-07-2023
The Tribunal examined an appeal regarding the grant of interest for delay in possession, noting that while an offer was made in June 2019, the Occupancy Certificate/Completion Certificate was only received later; the judgment is reserved.
Tribunal Order #0901126015772020-25-08-2022
The Tribunal allowed the application for condonation of delay in filing the appeal, citing the COVID-19 period relaxations granted by the Supreme Court, and directed the Registry to register the case as a regular appeal.
Tribunal Disposal & Final Award Ruling
The Appellate Tribunal dismissed the appeal filed by Greater Noida Industrial Development Authority, upholding the Regulatory Authority's order to pay interest for delayed possession and directing that the promoter's pre-deposited amount be transferred to U.P. RERA for disbursement to the allottee. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Appellate Tribunal dismissed the appeal filed by Greater Noida Industrial Development Authority, upholding the Regulatory Authority's order to pay interest for delayed possession and directing that the promoter's pre-deposited amount be transferred to U.P. RERA for disbursement to the allottee.
Ruling Awarded To
Respondent
Awarded Interest Rate
MCLR+1%
Interest Period
from 19.09.2017 till receipt of offer of possession (10.07.2019)
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Ajay Kumar Gupta
- Rishindra Vikram Singh
Respondent Advocate(s)
- N A
Official RERA Tribunal Orders (3)
The Appellate Tribunal dismissed the appeal filed by Greater Noida Industrial Development Authority, upholding the Regulatory Authority's order to pay interest for delayed possession and directing that the promoter's pre-deposited amount be transferred to U.P. RERA for disbursement to the allottee.
The Tribunal examined an appeal regarding the grant of interest for delay in possession, noting that while an offer was made in June 2019, the Occupancy Certificate/Completion Certificate was only received later; the judgment is reserved.
The Tribunal allowed the application for condonation of delay in filing the appeal, citing the COVID-19 period relaxations granted by the Supreme Court, and directed the Registry to register the case as a regular appeal.
Need to research all rulings for a builder?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.