up_reraStatus: Completed
CASE ID: 0901126015772020

Appellant / Complainant

Greater Noida Industrial Development Authority

VS

Respondent

Pratima Gupta

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferPromotional MisrepresentationMaintenance & Utility Disputes

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

31 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126015772020 by Greater Noida Industrial Development Authority against Pratima Gupta before up_rera.

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferPromotional MisrepresentationMaintenance & Utility Disputes
2
Stage 121/07/2023

for delivery of Judgment/Order

The Appellate Tribunal dismissed the appeal filed by Greater Noida Industrial Development Authority, upholding the Regulatory Authority's order to pay interest for delayed possession and directing that the promoter's pre-deposited amount be transferred to U.P. RERA for disbursement to the allottee.

3
Stage 218/07/2023

Hearing

The Tribunal examined an appeal regarding the grant of interest for delay in possession, noting that while an offer was made in June 2019, the Occupancy Certificate/Completion Certificate was only received later; the judgment is reserved.

4
Stage 323/05/2023

For Order

The Tribunal decided to proceed ex-parte against the respondent due to their failure to appear despite sufficient service of notice and was scheduled the case for further orders on 18.07.2023.

5
Stage 417/04/2023

For Order

The tribunal granted an adjournment requested by the appellant's counsel due to illness and rescheduled the matter for orders on 23.05.2023.

6
Stage 502/03/2023

For Order

The Tribunal ruled that service of notice to the respondent is sufficient via post and email, granted the respondent 10 days to file objections, and scheduled the next hearing for 17.04.2023.

7
Stage 630/01/2023

For Order

The Tribunal granted an adjournment of the proceedings due to the illness of the counsels for both the appellant and the respondent, rescheduling the hearing for 02.03.2023.

8
Stage 721/12/2022

For Order

The Tribunal issued a fresh notice to the respondent and provided specific procedural directions for service of notice and filing of pleadings before the next hearing on 30.01.2023.

9
Stage 825/11/2022

For Order

The Tribunal granted an adjournment due to the counsel for the appellant meeting with an accident and provided 10 days to upload the required affidavit of service.

10
Stage 919/10/2022

For Order

The Tribunal directed the appellant to correct a filing error regarding document placement and ordered the issuance of fresh notice to the respondent for the next hearing on 25.11.2022.

11
Stage 1023/09/2022

For Order

The Tribunal granted the respondent a final opportunity to file an objection against the appellant's delay condonation application and scheduled the matter for hearing on 19.10.2022.

12
Stage 1125/08/2022

Delay condonation

The Tribunal allowed the application for condonation of delay in filing the appeal, citing the COVID-19 period relaxations granted by the Supreme Court, and directed the Registry to register the case as a regular appeal.

13
Stage 1211/07/2022

Hearing

The Tribunal directed the respondent's counsel to file a reply to the delay condonation application and serve a copy to the applicant before the next hearing on 25.08.2022.

14
Stage 1329/04/2022

Hearing

The Tribunal issued a notice to the respondent and directed the appellant to serve the memo of appeal via speed post and email, with the matter returnable on 08.07.2022.

15
Stage 1423/03/2022

Hearing

The Tribunal directed the registry to remove Sri Nirmit Srivastava's name from the record and ordered that notice be issued to the respondent, with the case scheduled for April 29, 2022, to address a limitation application.

16
Stage 1522/02/2022

Delay condonation

The Tribunal granted the respondent 10 days to file objections regarding the application for condonation of delay and the grounds of appeal, with a subsequent deadline for the applicant's reply.

17
Stage 1612/01/2022

Delay condonation

No text available.

18
Stage 1721/12/2021

Delay condonation

The Tribunal granted an adjournment requested by the applicant and rescheduled the case to 12.01.2022 to consider the application for condonation of delay and its objections.

19
Stage 1824/11/2021

Delay condonation

The Tribunal adjourned the case to 21.12.2021 for the disposal of a limitation application and directed both parties to appear, noting that failure to do so will result in the application being decided according to the Act.

20
Stage 1926/10/2021

Delay condonation

The Tribunal allowed an application for adjournment and rescheduled the case to 24.11.2021 for the disposal of a limitation application and objections.

21
Stage 2024/09/2021

Delay condonation

The Tribunal adjourned the case to 26.10.2021 and directed the parties to exchange pleadings and file originals in the Registry at least one week before the next hearing.

22
Stage 2112/04/2021

Delay condonation

No text available.

23
Stage 2216/03/2021

Delay condonation

No text available.

24
Stage 2326/02/2021

For Order

The Tribunal adjourned the defective appeal due to an advocates' strike and directed the parties to exchange pleadings before the next hearing on 16.03.2021.

25
Stage 2429/01/2021

Compliance of section 43(5)

The Tribunal issued notice to the respondent regarding the application for condonation of delay and granted two weeks for filing objections, with a subsequent reply due within one week.

26
Stage 2506/01/2021

Compliance of section 43(5)

No text available.

27
Stage 2614/12/2020

Compliance of section 43(5)

No text available.

28
Stage 27Final Ruling Order

Tribunal Order #0901126015772020-21-07-2023

The Appellate Tribunal dismissed the appeal filed by Greater Noida Industrial Development Authority, upholding the Regulatory Authority's order to pay interest for delayed possession and directing that the promoter's pre-deposited amount be transferred to U.P. RERA for disbursement to the allottee.

29
Stage 28Interim Order

Tribunal Order #0901126015772020-18-07-2023

The Tribunal examined an appeal regarding the grant of interest for delay in possession, noting that while an offer was made in June 2019, the Occupancy Certificate/Completion Certificate was only received later; the judgment is reserved.

30
Stage 29Interim Order

Tribunal Order #0901126015772020-25-08-2022

The Tribunal allowed the application for condonation of delay in filing the appeal, citing the COVID-19 period relaxations granted by the Supreme Court, and directed the Registry to register the case as a regular appeal.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Appellate Tribunal dismissed the appeal filed by Greater Noida Industrial Development Authority, upholding the Regulatory Authority's order to pay interest for delayed possession and directing that the promoter's pre-deposited amount be transferred to U.P. RERA for disbursement to the allottee. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.

Disposal Winner: RespondentInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Appellate Tribunal dismissed the appeal filed by Greater Noida Industrial Development Authority, upholding the Regulatory Authority's order to pay interest for delayed possession and directing that the promoter's pre-deposited amount be transferred to U.P. RERA for disbursement to the allottee.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+1%

Interest Period

from 19.09.2017 till receipt of offer of possession (10.07.2019)

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(4)(f)Section 17Section 12Section 11(4)(d)Section 19(6)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Ajay Kumar Gupta
  • Rishindra Vikram Singh

Respondent Advocate(s)

  • N A

Official RERA Tribunal Orders (3)

FINAL_ORDEROrder ID: 0901126015772020-21-07-2023

The Appellate Tribunal dismissed the appeal filed by Greater Noida Industrial Development Authority, upholding the Regulatory Authority's order to pay interest for delayed possession and directing that the promoter's pre-deposited amount be transferred to U.P. RERA for disbursement to the allottee.

INTERIM_ORDEROrder ID: 0901126015772020-18-07-2023

The Tribunal examined an appeal regarding the grant of interest for delay in possession, noting that while an offer was made in June 2019, the Occupancy Certificate/Completion Certificate was only received later; the judgment is reserved.

INTERIM_ORDEROrder ID: 0901126015772020-25-08-2022

The Tribunal allowed the application for condonation of delay in filing the appeal, citing the COVID-19 period relaxations granted by the Supreme Court, and directed the Registry to register the case as a regular appeal.

TathyaGrid RERA Intelligence AI

Need to research all rulings for a builder?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →