12 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126015732020 by Greater Noida Industrial Development Authority against Gunjan Sharma before up_rera.

2
Stage 120/12/2021

Delay condonation

The Tribunal rejected the application for condonation of delay and dismissed the appeal, ruling that the applicant failed to show sufficient cause for the 357-day delay and could not benefit from the Supreme Court's Suo Motu extension as the limitation had already expired.

3
Stage 225/11/2021

Delay condonation

No text available.

4
Stage 302/11/2021

Delay condonation

The Tribunal adjourned the case to 25.11.2021 and directed the parties to exchange pleadings and file originals in the Registry prior to the next hearing.

5
Stage 408/10/2021

Delay condonation

The Tribunal granted the appellant a 10-day extension to file a reply to the respondent's objection regarding the application for condonation of delay and the grounds of appeal.

6
Stage 522/04/2021

Delay condonation

No text available.

7
Stage 605/04/2021

Delay condonation

No text available.

8
Stage 715/03/2021

Hearing

The Tribunal granted the appellant 10 days to file a reply to the respondent's objections and scheduled the next hearing for April 5, 2021.

9
Stage 817/02/2021

Hearing

The Tribunal granted the appellant 10 days to file a reply to the respondent's objections and scheduled the matter for March 15, 2021, to consider the application for condonation of delay.

10
Stage 918/01/2021

Hearing

No text available.

11
Stage 10Final Ruling Order

Tribunal Order #0901126015732020-20-12-2021

The Tribunal rejected the application for condonation of delay and dismissed the appeal, ruling that the applicant failed to show sufficient cause for the 357-day delay and could not benefit from the Supreme Court's Suo Motu extension as the limitation had already expired.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal rejected the application for condonation of delay and dismissed the appeal, ruling that the applicant failed to show sufficient cause for the 357-day delay and could not benefit from the Supreme Court's Suo Motu extension as the limitation had already expired. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal rejected the application for condonation of delay and dismissed the appeal, ruling that the applicant failed to show sufficient cause for the 357-day delay and could not benefit from the Supreme Court's Suo Motu extension as the limitation had already expired.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Rajesh Chadha

Respondent Advocate(s)

  • Anilesh Tewari

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126015732020-20-12-2021

The Tribunal rejected the application for condonation of delay and dismissed the appeal, ruling that the applicant failed to show sufficient cause for the 357-day delay and could not benefit from the Supreme Court's Suo Motu extension as the limitation had already expired.