up_reraStatus: Completed
CASE ID: 0901126015542022

Appellant / Complainant

Uppal Chadha Hi-Tech Developers Pvt. Ltd.

VS

Respondent

Girraj Jee Maharaj Family Trust

Developer Firm

uppal chadha hi-tech developers pvt. ltd.

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

12 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126015542022 by Uppal Chadha Hi-Tech Developers Pvt. Ltd. against Girraj Jee Maharaj Family Trust before up_rera.

2
Stage 112/08/2025

Delay condonation

The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay due to lack of sufficient cause and subsequently dismissed the appeal (Appeal-462/2024).

3
Stage 229/07/2025

Delay condonation

The Tribunal noted the appellant's offer of an alternate unit to settle the dispute and adjourned the matter to 12.08.2025 to allow the respondent's counsel to seek instructions.

4
Stage 310/07/2025

Delay condonation

The Tribunal granted the appellant a one-week extension to file a rejoinder affidavit and scheduled the next hearing for July 29, 2025.

5
Stage 419/05/2025

Delay condonation

The Tribunal granted the respondent 10 days to file objections, with a subsequent one-week deadline for any rejoinder affidavit, and scheduled the next hearing for July 10, 2025.

6
Stage 528/04/2025

Delay condonation

The Tribunal granted the appellant's counsel time to file a rejoinder affidavit and scheduled the case for orders on 19.05.2025.

7
Stage 628/03/2025

Delay condonation

The Tribunal granted the respondent 10 days to file objections and directed the appellant to file a reply within one week thereafter, scheduling the hearing for the condonation of delay on 28.04.2025.

8
Stage 725/02/2025

Delay condonation

The court adjourned the appeal and scheduled it for a new hearing date on March 28, 2025, noting that counsels are abstaining from work due to a U.P. Bar Council resolution.

9
Stage 804/02/2025

Delay condonation

The Tribunal has adjourned the matter to 25.02.2025 and directed the respondent to file any objections in the interim.

10
Stage 902/01/2025

Delay condonation

The Tribunal issued notice to the respondent and provided procedural directions for the service of the appeal and the application for condonation of delay, scheduling the next hearing for 04.02.2025.

11
Stage 10Final Ruling Order

Tribunal Order #0901126015542022-12-08-2025

The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay due to lack of sufficient cause and subsequently dismissed the appeal (Appeal-462/2024).

Disposal Phase

Tribunal Disposal & Final Award Ruling

The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay due to lack of sufficient cause and subsequently dismissed the appeal (Appeal-462/2024). Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay due to lack of sufficient cause and subsequently dismissed the appeal (Appeal-462/2024).

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Bal Kishor Verma
  • Amit Yadav

Respondent Advocate(s)

  • Ujjval Gupta

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126015542022-12-08-2025

The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay due to lack of sufficient cause and subsequently dismissed the appeal (Appeal-462/2024).

TathyaGrid RERA Intelligence AI

Need to research all rulings for uppal chadha hi-tech developers pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →