up_reraStatus: Completed
CASE ID: 0901126015532022

Appellant / Complainant

Uppal Chadha Hi-Tech Developers Pvt. Ltd.

VS

Respondent

Santosh Kumar Bansal

Developer Firm

uppal chadha hi-tech developers pvt. ltd.

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

10 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126015532022 by Uppal Chadha Hi-Tech Developers Pvt. Ltd. against Santosh Kumar Bansal before up_rera.

2
Stage 109/01/2024

Hearing

The Tribunal permitted the appellant to withdraw the appeal following a settlement between the parties and directed that an application be filed for the release of the amount deposited under Section 43(5) of the Act.

3
Stage 203/10/2023

Hearing

No text available.

4
Stage 323/08/2023

Hearing

The Tribunal granted the applicant's request for fresh notice to the respondent due to failed service and outlined specific procedural steps for service via speed-post and email before the next hearing on 03.10.2023.

5
Stage 405/07/2023

Hearing

The Tribunal granted the appellant one week's time to file an affidavit of service due to a procedural defect and adjourned the matter to 23.08.2023.

6
Stage 526/04/2023

Defect Removal

The Tribunal verified the appellant's compliance with Section 43(5) of the Act regarding the mandatory deposit and issued notice to the respondent for a hearing on the application for condonation of delay scheduled for 05.07.2023.

7
Stage 617/04/2023

Delay condonation

The Tribunal noted the appellant's deposit of Rs. 7,71,318/- in compliance with Section 43(5) and adjourned the defective appeal to 26.04.2023 for further orders.

8
Stage 7Final Ruling Order

Tribunal Order #0901126015532022-09-01-2024

The Tribunal permitted the appellant to withdraw the appeal following a settlement between the parties and directed that an application be filed for the release of the amount deposited under Section 43(5) of the Act.

9
Stage 8Interim Order

Tribunal Order #0901126015532022-26-04-2023

The Tribunal verified the appellant's compliance with Section 43(5) of the Act regarding the mandatory deposit and issued notice to the respondent for a hearing on the application for condonation of delay scheduled for 05.07.2023.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal permitted the appellant to withdraw the appeal following a settlement between the parties and directed that an application be filed for the release of the amount deposited under Section 43(5) of the Act. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal permitted the appellant to withdraw the appeal following a settlement between the parties and directed that an application be filed for the release of the amount deposited under Section 43(5) of the Act.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Bal Kishor Verma
  • Amit Yadav

Respondent Advocate(s)

  • Prasoon Kumar Anjor

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126015532022-09-01-2024

The Tribunal permitted the appellant to withdraw the appeal following a settlement between the parties and directed that an application be filed for the release of the amount deposited under Section 43(5) of the Act.

INTERIM_ORDEROrder ID: 0901126015532022-26-04-2023

The Tribunal verified the appellant's compliance with Section 43(5) of the Act regarding the mandatory deposit and issued notice to the respondent for a hearing on the application for condonation of delay scheduled for 05.07.2023.

TathyaGrid RERA Intelligence AI

Need to research all rulings for uppal chadha hi-tech developers pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →