up_reraStatus: Completed
CASE ID: 0901126015522020

Appellant / Complainant

Archana Saxena

VS

Respondent

Lucknow Development Authority

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

13 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126015522020 by Archana Saxena against Lucknow Development Authority before up_rera.

2
Stage 105/10/2021

to file objections and its reply

The appeal was dismissed for want of prosecution due to the non-appearance of the appellant or their counsel.

3
Stage 208/09/2021

Hearing

The Tribunal granted the respondent a final two-week extension to file objections at the cost of Rs. 10,000/-, conditional upon the prior payment of previously imposed costs, and directed specific timelines for electronic service and filing of replies.

4
Stage 301/04/2021

For Order

No text available.

5
Stage 405/03/2021

For Order

The Tribunal granted a final two-week extension to the respondent for filing objections to the condonation of delay and grounds of appeal, warning that failure to comply will result in the forfeiture of their right to file objections.

6
Stage 518/02/2021

For Order

The Tribunal granted the respondent a final one-week extension to file objections to the application for condonation of delay and grounds of appeal, subject to a cost of Rs. 5,000 to be used for the Tribunal's library.

7
Stage 625/01/2021

For Order

The Tribunal granted an adjournment requested by the respondent's counsel due to illness and provided a final two-week extension for the respondent to file objections to the application for condonation of delay and grounds of appeal.

8
Stage 705/01/2021

Delay condonation

No text available.

9
Stage 816/12/2020

Delay condonation

No text available.

10
Stage 9Interim Order

Tribunal Order #0901126015522020-05-03-2021

The Tribunal granted a final two-week extension to the respondent for filing objections to the condonation of delay and grounds of appeal, warning that failure to comply will result in the forfeiture of their right to file objections.

11
Stage 10Interim Order

Tribunal Order #0901126015522020-18-02-2021

The Tribunal granted the respondent a final one-week extension to file objections to the application for condonation of delay and grounds of appeal, subject to a cost of Rs. 5,000 to be used for the Tribunal's library.

12
Stage 11Interim Order

Tribunal Order #0901126015522020-08-09-2021

The Tribunal granted the respondent a final two-week extension to file objections at the cost of Rs. 10,000/-, conditional upon the prior payment of previously imposed costs, and directed specific timelines for electronic service and filing of replies.

Disposal Phase

Tribunal Disposal & Final Award Ruling

Dismissed Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

Dismissed

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Awaneesh Yadav

Respondent Advocate(s)

  • Prashant Kumar Singh

Official RERA Tribunal Orders (3)

INTERIM_ORDEROrder ID: 0901126015522020-05-03-2021

The Tribunal granted a final two-week extension to the respondent for filing objections to the condonation of delay and grounds of appeal, warning that failure to comply will result in the forfeiture of their right to file objections.

INTERIM_ORDEROrder ID: 0901126015522020-18-02-2021

The Tribunal granted the respondent a final one-week extension to file objections to the application for condonation of delay and grounds of appeal, subject to a cost of Rs. 5,000 to be used for the Tribunal's library.

INTERIM_ORDEROrder ID: 0901126015522020-08-09-2021

The Tribunal granted the respondent a final two-week extension to file objections at the cost of Rs. 10,000/-, conditional upon the prior payment of previously imposed costs, and directed specific timelines for electronic service and filing of replies.

TathyaGrid RERA Intelligence AI

Need to research all rulings for a builder?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →