CASE ID: 0901126015492020

Appellant / Complainant

Paarth Infrabuild Pvt. Ltd.

VS

Respondent

Kaushal Porwal, Anr.

Developer Firm

paarth infrabuild pvt. ltd.

Disputed Amount

3,52,800

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

19 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126015492020 by Paarth Infrabuild Pvt. Ltd. against Kaushal Porwal, Anr. before up_rera.

2
Stage 104/01/2022

Hearing

The Tribunal dismissed the appeal as withdrawn following a request by the applicant and directed the Registry to refund the deposited amount of Rs. 3,52,800/- to the applicant upon verification of proof of deposit.

3
Stage 220/12/2021

Hearing

The Tribunal granted an adjournment requested by the counsel for the applicant due to the ill health of the Senior Advocate and rescheduled the hearing for January 4, 2022.

4
Stage 330/11/2021

Hearing

The Tribunal adjourned the case to 20.12.2021 and issued a final opportunity to the applicant to comply with the provisions of Section 43(5) of the Act.

5
Stage 411/11/2021

Further Hearing

The Tribunal refers to a previous order dated 11.11.2020 and schedules the matter for a hearing on 30.11.2021.

6
Stage 508/10/2021

Further Hearing

The Tribunal granted an adjournment requested by the appellant's counsel due to the unavailability of the Senior Advocate and rescheduled the matter for 11.11.2021.

7
Stage 622/04/2021

Compliance of section 43(5)

No text available.

8
Stage 705/04/2021

Compliance of section 43(5)

No text available.

9
Stage 815/03/2021

Further Hearing

No text available.

10
Stage 924/02/2021

For Order

The tribunal adjourned the defective appeal due to an advocate strike by the Oudh Bar Association and rescheduled the matter for 15.03.2021.

11
Stage 1022/02/2021

For Order

The Tribunal granted a request from the appellant's counsel to adjourn the matter and rescheduled the hearing for 24.02.2021.

12
Stage 1103/02/2021

For Order

The Tribunal denied further routine adjournments and issued a strict directive that the case shall not be adjourned again on any account, noting that the applicant appeared to be intentionally dragging out the matter to avoid compliance with Section 43(5).

13
Stage 1218/01/2021

Arguments

No text available.

14
Stage 1315/12/2020

Arguments

No text available.

15
Stage 1420/11/2020

Admission

No text available.

16
Stage 15Interim Order

Tribunal Order #0901126015492020-03-02-2021

The Tribunal denied further routine adjournments and issued a strict directive that the case shall not be adjourned again on any account, noting that the applicant appeared to be intentionally dragging out the matter to avoid compliance with Section 43(5).

17
Stage 16Final Ruling Order

Tribunal Order #0901126015492020-04-01-2022

The Tribunal dismissed the appeal as withdrawn following a request by the applicant and directed the Registry to refund the deposited amount of Rs. 3,52,800/- to the applicant upon verification of proof of deposit.

18
Stage 17Interim Order

Tribunal Order #0901126015492020-30-11-2021

The Tribunal adjourned the case to 20.12.2021 and issued a final opportunity to the applicant to comply with the provisions of Section 43(5) of the Act.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal dismissed the appeal as withdrawn following a request by the applicant and directed the Registry to refund the deposited amount of Rs. 3,52,800/- to the applicant upon verification of proof of deposit. Awarded in favor of Appellant.

Disposal Winner: AppellantStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal dismissed the appeal as withdrawn following a request by the applicant and directed the Registry to refund the deposited amount of Rs. 3,52,800/- to the applicant upon verification of proof of deposit.

Ruling Awarded To

Appellant

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Rajeev Shukla
  • Rahul Shukla

Respondent Advocate(s)

  • In Person
  • Anurag Arora

Official RERA Tribunal Orders (3)

INTERIM_ORDEROrder ID: 0901126015492020-03-02-2021

The Tribunal denied further routine adjournments and issued a strict directive that the case shall not be adjourned again on any account, noting that the applicant appeared to be intentionally dragging out the matter to avoid compliance with Section 43(5).

FINAL_ORDEROrder ID: 0901126015492020-04-01-2022

The Tribunal dismissed the appeal as withdrawn following a request by the applicant and directed the Registry to refund the deposited amount of Rs. 3,52,800/- to the applicant upon verification of proof of deposit.

INTERIM_ORDEROrder ID: 0901126015492020-30-11-2021

The Tribunal adjourned the case to 20.12.2021 and issued a final opportunity to the applicant to comply with the provisions of Section 43(5) of the Act.

TathyaGrid RERA Intelligence AI

Need to research all rulings for paarth infrabuild pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →