up_reraStatus: Completed
CASE ID: 0901126015482020

Appellant / Complainant

Paarth Infrabuild Pvt. Ltd.

VS

Respondent

Gaurav Pant

Developer Firm

paarth infrabuild pvt. ltd.

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Jurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

20 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126015482020 by Paarth Infrabuild Pvt. Ltd. against Gaurav Pant before up_rera.

Jurisdiction & Maintainability
2
Stage 108/03/2022

Hearing

The Tribunal allowed the appellant to withdraw the appeal and directed that the amount deposited under Section 43(5) of the Act be handled by the Regulatory Authority to ensure proper distribution to the allottee or refund to the promoter.

3
Stage 204/01/2022

Hearing

The Tribunal issued notice to the respondent following compliance with Section 43(5) of the Act and directed the parties to exchange objections and replies before the next hearing on 25.01.2022.

4
Stage 320/12/2021

Hearing

The Tribunal granted an adjournment requested by the counsel for the applicant due to the ill health of the Senior Advocate and rescheduled the hearing for 04.01.2022.

5
Stage 430/11/2021

Hearing

The Tribunal adjourned the case to 20.12.2021 and issued a final opportunity for the applicant to comply with the provisions of Section 43(5) of the Act.

6
Stage 511/11/2021

Further Hearing

The Tribunal has scheduled the matter for a hearing on 30.11.2021, noting a previous order dated 11.11.2020.

7
Stage 608/10/2021

Further Hearing

The Tribunal reprimanded the appellant's counsel for seeking an adjournment via email and subsequently adjourned the matter to 11.11.2021 following a request from a substitute advocate.

8
Stage 722/04/2021

Compliance of section 43(5)

No text available.

9
Stage 805/04/2021

Compliance of section 43(5)

No text available.

10
Stage 915/03/2021

Further Hearing

No text available.

11
Stage 1024/02/2021

Compliance of section 43(5)

The Tribunal adjourned the defective appeal due to an advocates' strike called by the Oudh Bar Association and rescheduled the matter for 15.03.2021.

12
Stage 1122/02/2021

For Order

The tribunal granted a request from the appellant's counsel to adjourn the matter and rescheduled the hearing for 24.02.2021.

13
Stage 1203/02/2021

For Order

The Tribunal directed the applicant to comply with Section 43(5) of the Act and file a reply to the respondent's objections within one week, noting that the applicant appeared to be unnecessarily delaying the matter.

14
Stage 1318/01/2021

Admission

No text available.

15
Stage 1415/12/2020

Admission

No text available.

16
Stage 1520/11/2020

Admission

No text available.

17
Stage 16Interim Order

Tribunal Order #0901126015482020-30-11-2021

The Tribunal adjourned the case to 20.12.2021 and issued a final opportunity for the applicant to comply with the provisions of Section 43(5) of the Act.

18
Stage 17Interim Order

Tribunal Order #0901126015482020-03-02-2021

The Tribunal directed the applicant to comply with Section 43(5) of the Act and file a reply to the respondent's objections within one week, noting that the applicant appeared to be unnecessarily delaying the matter.

19
Stage 18Final Ruling Order

Tribunal Order #0901126015482020-08-03-2022

The Tribunal allowed the appellant to withdraw the appeal and directed that the amount deposited under Section 43(5) of the Act be handled by the Regulatory Authority to ensure proper distribution to the allottee or refund to the promoter.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal allowed the appellant to withdraw the appeal and directed that the amount deposited under Section 43(5) of the Act be handled by the Regulatory Authority to ensure proper distribution to the allottee or refund to the promoter. Awarded in favor of Appellant.

Disposal Winner: AppellantStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal allowed the appellant to withdraw the appeal and directed that the amount deposited under Section 43(5) of the Act be handled by the Regulatory Authority to ensure proper distribution to the allottee or refund to the promoter.

Ruling Awarded To

Appellant

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Rajiv Shukla
  • Rahul Shukla

Respondent Advocate(s)

  • In Person

Official RERA Tribunal Orders (3)

INTERIM_ORDEROrder ID: 0901126015482020-30-11-2021

The Tribunal adjourned the case to 20.12.2021 and issued a final opportunity for the applicant to comply with the provisions of Section 43(5) of the Act.

INTERIM_ORDEROrder ID: 0901126015482020-03-02-2021

The Tribunal directed the applicant to comply with Section 43(5) of the Act and file a reply to the respondent's objections within one week, noting that the applicant appeared to be unnecessarily delaying the matter.

FINAL_ORDEROrder ID: 0901126015482020-08-03-2022

The Tribunal allowed the appellant to withdraw the appeal and directed that the amount deposited under Section 43(5) of the Act be handled by the Regulatory Authority to ensure proper distribution to the allottee or refund to the promoter.

TathyaGrid RERA Intelligence AI

Need to research all rulings for paarth infrabuild pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →