Appellant / Complainant
Kavita
Respondent
Gardenia Aims Developers Pvt. Ltd.
gardenia aims developers pvt. ltd.
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126015462023 by Kavita against Gardenia Aims Developers Pvt. Ltd. before up_rera.
Execution
The Tribunal refers to a previous order passed in a related appeal and lists the current matter for orders/hearing on 22.05.2026.
Execution
The Tribunal directed that the appeal be listed for order or hearing on May 13, 2026, referring to a previous order passed in a related matter.
Execution
The Tribunal refers to a previous order passed in a related appeal and lists the current matter for hearing on 06.05.2026.
Execution
The Tribunal refers to a previous order passed in a related case (Appeal No. 70/2020) and lists the current Execution Application (EA-976/2023) for hearing on 10.04.2026.
Execution
The Tribunal refers to a previous order passed in a related case and lists the application for hearing on 20.03.2026.
Execution
The Tribunal has scheduled the Execution Application (EA-976/2023) for a hearing on 16.02.2026, to be heard alongside Appeal No. 867/2020.
Execution
The Tribunal has scheduled the Execution Application (EA-976/2023) to be listed for a hearing on January 30, 2026.
Execution
The Tribunal refers to a previous order passed in Appeal No. 867 of 2020 and lists the case for orders on December 12, 2025.
Execution
The Tribunal refers the matter to the orders passed in Appeal No. 867 of 2020.
Execution
The Tribunal closed the respondent's opportunity to file objections against the appellant's calculation sheet due to non-compliance and scheduled the appeal for hearing on 14.07.2025, explicitly stating no further adjournments will be granted.
Execution
The Tribunal directed the applicant to provide a hard copy of the calculation sheet due to technical portal issues and granted the respondent seven days to file an objection or calculation sheet.
Execution
The Tribunal noted the absence of both parties due to the respondent's counsel's illness and the appellant's non-appearance, subsequently adjourning the matter to 06.05.2025.
Execution
The Tribunal has adjourned the matter to 15.04.2025 because lawyers are abstaining from judicial work following a resolution by the Real Estate Bar Association, Lucknow.
Hearing on Recall App
The matter is adjourned to 18.03.2025 upon the request of the learned counsel for the appellant.
Hearing on Recall App
The Tribunal granted both parties time to file calculation sheets and scheduled the case for orders on 17.02.2025.
Hearing on Recall App
The Tribunal adjourned the Execution Application to 20.01.2025 to be heard alongside a related appeal and directed the appellant's counsel to file a rejoinder to the respondent's objections.
Execution
The Tribunal directed the judgment debtor to serve copies of their objections against the Execution Application to the decree holder and upload them to the web portal within one week, adjourning the matter to 06.01.2025.
Execution
The Tribunal noted the absence of both parties and ordered the case to be listed on 06.12.2024 for orders.
Execution
The Tribunal directed the respondent to serve a copy of their objections to the Execution Application upon the appellant within one week and ordered the appellant to file a reply within 10 days thereafter.
Execution
The Tribunal granted the respondent a final 10-day extension to file their Vakalatnama and objections to the execution application, directing that a soft copy be shared with the appellant.
For Order
The Tribunal adjourned the proceedings due to the absence of the respondent's counsel and scheduled the case for a final hearing on 23.08.2024.
For Order
The Tribunal granted the respondent 10 days to file a vakalatnama and objections to the execution application, allowing the applicant one week thereafter to file a reply.
For Order
The Tribunal issued a show-cause notice to the respondent regarding non-compliance with a previous order dated 21.03.2022 and directed specific procedures for service of notice and filing of objections.
For Order
The execution application was dismissed for want of prosecution as no one appeared to press the case and no request for adjournment was received.
For Order
The Tribunal issued a show-cause notice to the respondent regarding non-compliance with an order dated 21.03.2022 and directed the applicant to serve the execution application via speed-post and email.
Tribunal Order #0901126015462023-26-05-2025
The Tribunal closed the respondent's opportunity to file objections against the appellant's calculation sheet due to non-compliance and scheduled the appeal for hearing on 14.07.2025, explicitly stating no further adjournments will be granted.
Tribunal Order #0901126015462023-10-04-2023
The Tribunal issued a show-cause notice to the respondent regarding non-compliance with an order dated 21.03.2022 and directed the applicant to serve the execution application via speed-post and email.
Tribunal Order #0901126015462023-13-05-2024
The Tribunal issued a show-cause notice to the respondent regarding non-compliance with a previous order dated 21.03.2022 and directed specific procedures for service of notice and filing of objections.
Tribunal Disposal & Final Award Ruling
Dismissed Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
Dismissed
Ruling Awarded To
Respondent
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Shailesh Kumar Srivastava
Respondent Advocate(s)
- Shuchita Singh
Official RERA Tribunal Orders (3)
The Tribunal closed the respondent's opportunity to file objections against the appellant's calculation sheet due to non-compliance and scheduled the appeal for hearing on 14.07.2025, explicitly stating no further adjournments will be granted.
The Tribunal issued a show-cause notice to the respondent regarding non-compliance with an order dated 21.03.2022 and directed the applicant to serve the execution application via speed-post and email.
The Tribunal issued a show-cause notice to the respondent regarding non-compliance with a previous order dated 21.03.2022 and directed specific procedures for service of notice and filing of objections.