up_reraStatus: Active
CASE ID: 0901126015462023

Appellant / Complainant

Kavita

VS

Respondent

Gardenia Aims Developers Pvt. Ltd.

Developer Firm

gardenia aims developers pvt. ltd.

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Non-Compliance & Execution

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

36 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126015462023 by Kavita against Gardenia Aims Developers Pvt. Ltd. before up_rera.

Non-Compliance & Execution
2
Stage 122/05/2026

Execution

No text available.

3
Stage 213/05/2026

Execution

The Tribunal refers to a previous order passed in a related appeal and lists the current matter for orders/hearing on 22.05.2026.

4
Stage 306/05/2026

Execution

The Tribunal directed that the appeal be listed for order or hearing on May 13, 2026, referring to a previous order passed in a related matter.

5
Stage 410/04/2026

Execution

The Tribunal refers to a previous order passed in a related appeal and lists the current matter for hearing on 06.05.2026.

6
Stage 520/03/2026

Execution

The Tribunal refers to a previous order passed in a related case (Appeal No. 70/2020) and lists the current Execution Application (EA-976/2023) for hearing on 10.04.2026.

7
Stage 616/02/2026

Execution

The Tribunal refers to a previous order passed in a related case and lists the application for hearing on 20.03.2026.

8
Stage 730/01/2026

Execution

The Tribunal has scheduled the Execution Application (EA-976/2023) for a hearing on 16.02.2026, to be heard alongside Appeal No. 867/2020.

9
Stage 812/12/2025

Execution

The Tribunal has scheduled the Execution Application (EA-976/2023) to be listed for a hearing on January 30, 2026.

10
Stage 915/11/2025

Execution

The Tribunal refers to a previous order passed in Appeal No. 867 of 2020 and lists the case for orders on December 12, 2025.

11
Stage 1005/09/2025

Execution

No text available.

12
Stage 1114/07/2025

Execution

The Tribunal refers the matter to the orders passed in Appeal No. 867 of 2020.

13
Stage 1226/05/2025

Execution

The Tribunal closed the respondent's opportunity to file objections against the appellant's calculation sheet due to non-compliance and scheduled the appeal for hearing on 14.07.2025, explicitly stating no further adjournments will be granted.

14
Stage 1306/05/2025

Execution

The Tribunal directed the applicant to provide a hard copy of the calculation sheet due to technical portal issues and granted the respondent seven days to file an objection or calculation sheet.

15
Stage 1415/04/2025

Execution

The Tribunal noted the absence of both parties due to the respondent's counsel's illness and the appellant's non-appearance, subsequently adjourning the matter to 06.05.2025.

16
Stage 1518/03/2025

Execution

The Tribunal has adjourned the matter to 15.04.2025 because lawyers are abstaining from judicial work following a resolution by the Real Estate Bar Association, Lucknow.

17
Stage 1617/02/2025

Hearing on Recall App

The matter is adjourned to 18.03.2025 upon the request of the learned counsel for the appellant.

18
Stage 1720/01/2025

Hearing on Recall App

The Tribunal granted both parties time to file calculation sheets and scheduled the case for orders on 17.02.2025.

19
Stage 1806/01/2025

Hearing on Recall App

The Tribunal adjourned the Execution Application to 20.01.2025 to be heard alongside a related appeal and directed the appellant's counsel to file a rejoinder to the respondent's objections.

20
Stage 1906/12/2024

Execution

The Tribunal directed the judgment debtor to serve copies of their objections against the Execution Application to the decree holder and upload them to the web portal within one week, adjourning the matter to 06.01.2025.

21
Stage 2005/11/2024

Execution

The Tribunal noted the absence of both parties and ordered the case to be listed on 06.12.2024 for orders.

22
Stage 2125/09/2024

Execution

The Tribunal directed the respondent to serve a copy of their objections to the Execution Application upon the appellant within one week and ordered the appellant to file a reply within 10 days thereafter.

23
Stage 2223/08/2024

Execution

The Tribunal granted the respondent a final 10-day extension to file their Vakalatnama and objections to the execution application, directing that a soft copy be shared with the appellant.

24
Stage 2308/08/2024

For Order

The Tribunal adjourned the proceedings due to the absence of the respondent's counsel and scheduled the case for a final hearing on 23.08.2024.

25
Stage 2410/07/2024

For Order

The Tribunal granted the respondent 10 days to file a vakalatnama and objections to the execution application, allowing the applicant one week thereafter to file a reply.

26
Stage 2513/05/2024

For Order

The Tribunal issued a show-cause notice to the respondent regarding non-compliance with a previous order dated 21.03.2022 and directed specific procedures for service of notice and filing of objections.

27
Stage 2610/04/2024

For Order

No text available.

28
Stage 2728/03/2024

For Order

No text available.

29
Stage 2822/05/2023

For Order

The execution application was dismissed for want of prosecution as no one appeared to press the case and no request for adjournment was received.

30
Stage 2910/04/2023

For Order

The Tribunal issued a show-cause notice to the respondent regarding non-compliance with an order dated 21.03.2022 and directed the applicant to serve the execution application via speed-post and email.

31
Stage 3006/04/2023

For Order

No text available.

32
Stage 3105/04/2023

For Order

No text available.

33
Stage 32Interim Order

Tribunal Order #0901126015462023-26-05-2025

The Tribunal closed the respondent's opportunity to file objections against the appellant's calculation sheet due to non-compliance and scheduled the appeal for hearing on 14.07.2025, explicitly stating no further adjournments will be granted.

34
Stage 33Interim Order

Tribunal Order #0901126015462023-10-04-2023

The Tribunal issued a show-cause notice to the respondent regarding non-compliance with an order dated 21.03.2022 and directed the applicant to serve the execution application via speed-post and email.

35
Stage 34Interim Order

Tribunal Order #0901126015462023-13-05-2024

The Tribunal issued a show-cause notice to the respondent regarding non-compliance with a previous order dated 21.03.2022 and directed specific procedures for service of notice and filing of objections.

Disposal Phase

Tribunal Disposal & Final Award Ruling

Dismissed Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Active

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

Dismissed

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 40Section 63Section 64

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Shailesh Kumar Srivastava

Respondent Advocate(s)

  • Shuchita Singh

Official RERA Tribunal Orders (3)

INTERIM_ORDEROrder ID: 0901126015462023-26-05-2025

The Tribunal closed the respondent's opportunity to file objections against the appellant's calculation sheet due to non-compliance and scheduled the appeal for hearing on 14.07.2025, explicitly stating no further adjournments will be granted.

INTERIM_ORDEROrder ID: 0901126015462023-10-04-2023

The Tribunal issued a show-cause notice to the respondent regarding non-compliance with an order dated 21.03.2022 and directed the applicant to serve the execution application via speed-post and email.

INTERIM_ORDEROrder ID: 0901126015462023-13-05-2024

The Tribunal issued a show-cause notice to the respondent regarding non-compliance with a previous order dated 21.03.2022 and directed specific procedures for service of notice and filing of objections.

TathyaGrid RERA Intelligence AI

Need to research all rulings for gardenia aims developers pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →