up_reraStatus: Completed
CASE ID: 0901126015452023

Appellant / Complainant

Usha Tulsiyan

VS

Respondent

CBS International Projects Private Limited

Developer Firm

cbs international projects private limited

Disputed Amount

1,11,65,000

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestStructural Defects & QualityPromotional Misrepresentation

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

26 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126015452023 by Usha Tulsiyan against CBS International Projects Private Limited before up_rera.

Delay in PossessionDelay Compensation / InterestStructural Defects & QualityPromotional Misrepresentation
2
Stage 126/09/2025

for delivery of Judgment/Order

The Tribunal partially allowed the appeals, ruling that the developer is liable for delay interest at MCLR+1% from the assured possession date until the offer of possession, granting only a six-month exemption for the COVID-19 pandemic and rejecting all other force majeure claims.

3
Stage 203/07/2025

Hearing

The Tribunal heard arguments from both parties regarding the appeal and its objections, subsequently reserving the judgment for a later date.

4
Stage 302/05/2025

Hearing

The Tribunal granted an adjournment requested by the respondent's counsel and scheduled the case for orders on July 3, 2025.

5
Stage 410/04/2025

Hearing

The Tribunal granted the respondent 10 days to file a reply and scheduled the appeal for hearing on May 2, 2025.

6
Stage 517/03/2025

Hearing

The Tribunal has adjourned the appeal to 10.04.2025 upon a joint request from counsel and directed that pleadings be completed by both parties in the interim.

7
Stage 619/02/2025

Hearing

The Tribunal granted time to the appellant to rebut an affidavit and to the respondent to file a revised offer regarding alternative shop availability, adjourning the matter to 17.03.2025.

8
Stage 729/01/2025

Hearing

The Tribunal granted an adjournment requested by the respondent's counsel due to his absence from the station and rescheduled the matter for orders/hearing on 19.02.2025.

9
Stage 806/01/2025

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel due to illness and rescheduled the matter for orders on 29.01.2025.

10
Stage 918/11/2024

For Order

The Tribunal recalled the order dated 18.04.2024 and imposed a cost of Rs. 100/- payable to the respondent, subsequently scheduling the appeal for hearing on 06.01.2025.

11
Stage 1017/10/2024

For Order

The Tribunal has granted a request from the appellant's counsel to list the case for orders on 18.11.2024.

12
Stage 1124/09/2024

For Order

The Tribunal granted the appellant one week to file a rejoinder to the respondent's objections in RA No. 62/2024 and scheduled the next hearing for October 17, 2024.

13
Stage 1222/08/2024

For Order

The Tribunal directed the respondent to file objections to the appellant's recall application (RA No. 62/2024) within 10 days and scheduled the matter for hearing on 24.09.2024.

14
Stage 1318/07/2024

For Order

The appeal was adjourned due to the absence of the appellant's counsel, with the matter rescheduled for orders on 22.08.2024.

15
Stage 1417/05/2024

For Order

No text available.

16
Stage 1518/04/2024

For Order

The Tribunal refers the parties to a previous order passed in Appeal No. 213/2023 for further directions.

17
Stage 1612/03/2024

For Order

The Tribunal granted the appellant one week's time to file a reply to the respondent's objections and scheduled the next hearing for April 18, 2024.

18
Stage 1709/02/2024

For Order

The Tribunal refers the parties to a previously passed order dated in Appeal No. 213/2023 for the current order.

19
Stage 1809/10/2023

For Order

No text available.

20
Stage 1929/08/2023

For Order

No text available.

21
Stage 2011/07/2023

For Order

No text available.

22
Stage 2101/05/2023

For Order

No text available.

23
Stage 2219/04/2023

Admission

The Tribunal granted the appellant one week to submit the application for allotment of the unit and the corresponding Allotment Letter, and scheduled the next hearing for May 1, 2023.

24
Stage 23Final Ruling Order

Tribunal Order #0901126015452023-26-09-2025

The Tribunal partially allowed the appeals, ruling that the developer is liable for delay interest at MCLR+1% from the assured possession date until the offer of possession, granting only a six-month exemption for the COVID-19 pandemic and rejecting all other force majeure claims.

25
Stage 24Interim Order

Tribunal Order #0901126015452023-18-11-2024

The Tribunal recalled the order dated 18.04.2024 and imposed a cost of Rs. 100/- payable to the respondent, subsequently scheduling the appeal for hearing on 06.01.2025.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal partially allowed the appeals, ruling that the developer is liable for delay interest at MCLR+1% from the assured possession date until the offer of possession, granting only a six-month exemption for the COVID-19 pandemic and rejecting all other force majeure claims. Awarded in favor of Appellant. Awarded interest rate: MCLR+1%.

Disposal Winner: AppellantInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal partially allowed the appeals, ruling that the developer is liable for delay interest at MCLR+1% from the assured possession date until the offer of possession, granting only a six-month exemption for the COVID-19 pandemic and rejecting all other force majeure claims.

Ruling Awarded To

Appellant

Awarded Interest Rate

MCLR+1%

Interest Period

from the assured date of possession till the date of offer of possession along with OC/CC excluding six months Covid-19 pandemic period

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 14(3)Section 12

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Vikas Agrawal

Respondent Advocate(s)

  • Amit Yadav

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126015452023-26-09-2025

The Tribunal partially allowed the appeals, ruling that the developer is liable for delay interest at MCLR+1% from the assured possession date until the offer of possession, granting only a six-month exemption for the COVID-19 pandemic and rejecting all other force majeure claims.

INTERIM_ORDEROrder ID: 0901126015452023-18-11-2024

The Tribunal recalled the order dated 18.04.2024 and imposed a cost of Rs. 100/- payable to the respondent, subsequently scheduling the appeal for hearing on 06.01.2025.

TathyaGrid RERA Intelligence AI

Need to research all rulings for cbs international projects private limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →