Appellant / Complainant
Greater Noida Industrial Development Authority
Respondent
Sachin Verma
Respondent
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126015412020 by Greater Noida Industrial Development Authority against Sachin Verma before up_rera.
Hearing
The Tribunal permitted the appellant to withdraw the appeal following a settlement and directed that the pre-deposited amount under Section 43(5) be transferred to U.P. RERA for disbursement to the respondent during execution proceedings.
Hearing
The Tribunal adjourned the proceedings to July 2, 2024, to allow the parties time to pursue an amicable settlement, noting that arguments will proceed if no settlement is reached.
Hearing
The Tribunal granted an adjournment to allow the parties to pursue an amicable settlement through negotiations, rescheduling the matter for hearing on 08.05.2024.
Hearing
The Tribunal has ordered the appeal to be listed for a hearing on 05.04.2024.
Hearing
The Tribunal granted the appellant a final three-day window to file a reply to the respondent's objections, failing which the opportunity will be closed, and adjourned the matter to 29.02.2024.
Hearing
The Tribunal granted the appellant one week to file a reply to the respondent's objection and scheduled the matter for hearing on 24.07.2023 regarding an application for additional documents.
Hearing
The Tribunal granted a final one-week extension to the respondent for filing objections to the appeal, noting that failure to do so will result in the opportunity being closed and the appeal being decided on existing records.
Hearing
The Tribunal directed the respondent to file objections within a week and share them via email, with the appellant permitted one week thereafter to file a reply; the matter is listed for hearing on 26.04.2023.
For Order
The Tribunal granted an adjournment due to counsel illness and directed the respondent to file objections within 10 days, with a subsequent reply from the appellant allowed within one week.
for delivery of Judgment/Order
The Tribunal allowed the appellant's application for condonation of delay regarding a 46-day period prior to the COVID-19 pandemic, subject to a cost of Rs. 12,000 to be split between the Tribunal Fund and the respondent.
Hearing
This is a procedural order recording the presence of counsel for the respondent during the calling of the case on 29.04.2022.
Hearing
The Tribunal adjourned the matter to 29.04.2022 for the disposal of a limitation application and any related objections, following a joint request from both parties' counsel.
Delay condonation
The Tribunal granted the applicant 10 days to file a better affidavit regarding the application for condonation of delay and scheduled the next hearing for March 23, 2022.
Delay condonation
The Tribunal granted an adjournment requested by the applicant and rescheduled the case to 12.01.2022 to consider the application for condonation of delay.
Delay condonation
The Tribunal adjourned the case to 21.12.2021 for the disposal of a limitation application and its objection, noting that while notice was served, the respondent failed to appear.
Delay condonation
The Tribunal adjourned the matter to 24.11.2021 for the disposal of a limitation application and directed that failure to appear may result in the application being disposed of in the absence of counsel.
Delay condonation
The Tribunal adjourned the case to 26.10.2021 and directed both parties to exchange pleadings and file originals in the Registry at least one week before the next hearing.
For Order
The court adjourned the defective appeal due to an advocates' strike and rescheduled the matter for 16.03.2021, while directing the applicant's counsel to file a reply to the respondent's objections.
Delay condonation
The Tribunal noted the appellant's intent to file a reply to objections and scheduled the defective appeal for February 26, 2021, to consider the application for condonation of delay.
Tribunal Order #0901126015412020-19-12-2022
The Tribunal allowed the appellant's application for condonation of delay regarding a 46-day period prior to the COVID-19 pandemic, subject to a cost of Rs. 12,000 to be split between the Tribunal Fund and the respondent.
Tribunal Order #0901126015412020-02-07-2024
The Tribunal permitted the appellant to withdraw the appeal following a settlement and directed that the pre-deposited amount under Section 43(5) be transferred to U.P. RERA for disbursement to the respondent during execution proceedings.
Tribunal Disposal & Final Award Ruling
The Tribunal permitted the appellant to withdraw the appeal following a settlement and directed that the pre-deposited amount under Section 43(5) be transferred to U.P. RERA for disbursement to the respondent during execution proceedings. Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal permitted the appellant to withdraw the appeal following a settlement and directed that the pre-deposited amount under Section 43(5) be transferred to U.P. RERA for disbursement to the respondent during execution proceedings.
Ruling Awarded To
Respondent
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Ajay Kumar Gupta
- Pankaj Gupta
Respondent Advocate(s)
- Adrija Tiwari
- Kaviya Singh
Official RERA Tribunal Orders (2)
The Tribunal allowed the appellant's application for condonation of delay regarding a 46-day period prior to the COVID-19 pandemic, subject to a cost of Rs. 12,000 to be split between the Tribunal Fund and the respondent.
The Tribunal permitted the appellant to withdraw the appeal following a settlement and directed that the pre-deposited amount under Section 43(5) be transferred to U.P. RERA for disbursement to the respondent during execution proceedings.
Need to research all rulings for a builder?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.